Approved Executive 1 paper

AI summaryBury Cabinet approves two contracts for kitchen, bathroom, heating and electrical works to 186 council homes in the South and North of the Borough, with an option to extend for a further year.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedInternal works to 186 council homes, split North and South
Money£855,589.05 and £899,041.44Each contract includes £50K contingency
What happens nextOption to extend for 1 yearEstimated total value between £4 and 5 million, subject to funding
Who it affects186 council homes93 in the South and 93 in the North of the Borough

What was decided

Cabinet approved the contract award to Emanuel Whittaker Limited for internal works to 93 properties in the South of the Borough for £855,589.05 including £50K contingency. Report 2.1

Cabinet approved the contract award to Jackson Jackson and Sons Limited for internal works to 93 properties in the North of the Borough for £899,041.44 including £50K contingency. Report 2.2

Cabinet noted the option to extend for a further period of 1 year up to an estimated total contract value of between £4 and 5 million, subject to the availability of funding. Report 2.3

Why

The works are needed to maintain council homes at the Decent Home Standard, which the Regulator for Social Housing expects. Report 3.1

The in-house contractor does not have the capacity to carry out these major contracts, ruling out in-house delivery. Report P27

Using the Procure Plus framework via mini-competition is compliant with procurement rules and faster than open tender. Report 3.3, P28

What happens next

Both contracts will be delivered as supply and fit arrangements by the two building contractors following award. Report 3.4

Social value offers from the two contractors will be confirmed at the contract award meetings. Report 4.2, 4.4

Legal and procurement advice will be provided, with JCT contracts prepared through the Procure Plus framework. Report P37

The money

  • £855,589.05 South contract price for Emanuel Whittaker Limited, including £50K contingency Report 2.1
  • £899,041.44 North contract price for Jackson Jackson and Sons Limited, including £50K contingency Report 2.2
  • between £4 and 5 million Estimated total contract value of a potential 1 year extension, subject to funding Report 2.3

Options considered

  • Rejected: Do nothing. Council would quickly become non-compliant with the Home Standard Report P26
  • Rejected: Deliver in-house. In-house contractor does not have the capacity for these major works Report P27
  • Rejected: Open tender. Significantly extended procurement time and cost compared with the Procure Plus mini-competition Report P28
  • Chosen: Mini-competition through the Procure Plus framework. Compliant with procurement regulations and tailored to the Council's specific requirements Report 3.3, P28

Implications

  • Financial: The contract awards are in line with the approved capital programme. Report P39
  • Legal: Legal and procurement advice will be provided on the arrangements, and JCT contracts will be prepared through the Procure Plus framework. Report P37
  • Equalities: The project does not bring about changes that would impact one protected characteristic over another, or change access to services. Report P33
  • Climate: Modern boilers reduce fuel consumption and CO2 emissions, and new kitchens and bathrooms reduce water use; emissions from manufacturing can be mitigated by sourcing recycled or local materials. Report P34
  • Risk: A stock condition survey is underway, with 87% completion, and full scoping and surveys have been carried out for each scheme. Report P36
  • Other: The contracts support the Let's Do It Strategy priorities of improved quality of life and the 2025 Vision aims of tackling inequality, improving health and creating stronger communities. Report P30, P31, P32

Who and where

  • 93 council properties in the South of the Borough (51 kitchens, 43 bathrooms, 54 boilers) Report P14, 3.2
  • 93 council properties in the North of the Borough (54 kitchens, 26 bathrooms, 55 boilers) Report P15, 3.2
  • Council housing tenants Report 3.1, P31

Timeline

  • February 2025: Cabinet agreed the Housing Revenue Account Capital Works Programme budget for 2025/26 Report 1.2
  • 3 December 2025: Cabinet decision to approve the two contract awards and note the extension option

Plain English for the jargon

  • Decent Home Standard: The regulatory standard that social housing must meet as a minimum
  • HRA: Housing Revenue Account, the ring-fenced account for council housing
  • JCT: Joint Contracts Tribunal, a standard form of building contract
  • Procure Plus: A procurement framework for social housing investment works
  • Mini-competition: A tender run between prequalified suppliers on a framework
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.91

Resolved

Cabinet: 1. Approved the contract award to Emanuel Whittaker Limited in respect of internal works consisting of new kitchens and bathrooms, heating and electrical works to 93 properties in the South of the Borough for the sum of £855,589.05 including £50K contingency. 2. Approved the contract award to Jackson Jackson and Sons Limited in respect of internal works consisting of new kitchens and bathrooms, heating and electrical works to 93 properties in the North of the Borough for the sum of £899,041.44 including £50K contingency 3. Noted that there is the option to extend for a further period of 1 year up to an estimated total contract value of between £4 and 5 million subject to the availability of funding.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1.1The purpose of this report is to seek formal approval of two contract awards which form part of the Housing Major Works Programme.

1.2At the Cabinet meeting on 12 th February 2025 Cabinet agreed the Housing Revenue Account Capital Works Programme budget for 2025/26.

1.3The procurement approach on the tenders and contract extensions included in this report has been developed in conjunction with Bury Council’s Procurement Team.

1.4Our Internal Contract Award recommendation has been made, via the Procure Plus Framework selecting prequalified Contractors and Suppliers with additional elements of Social Value included.

1.5The framework submissions are scored by Procure Plus based on 60% Price, 40% Quality (social value, site delivery, tenant engagement, health & safety etc.). In addition, we will discuss with the contractors/suppliers the options they will commit to in respect of social value for the communities included as part of their contract delivery.

1.6All contracts for the Major Works Programme more than £500k require approval from Cabinet

Recommendations

2.1Approve contract award to Emanuel Whittaker Limited in respect of internal works consisting of new kitchens and bathrooms, heating and electrical works to 93 properties in the South of the Borough for the sum of £855,589.05 including £50K contingency.

2.2Approve contract award to Jackson Jackson and Sons Limited in respect of internal works consisting of new kitchens and bathrooms, heating and electrical works to 93 properties in the North of the Borough for the sum of £899,041.44 including £50K contingency

2.3There is the option to extend for a further period of 1 year up to an estimated total contract value of between £4 and 5 million subject to the availability of funding.

1 3.0 Background

Internals

3.1A key regulatory requirement for housing is to ensure all Bury Council homes are maintained, as a minimum, at the Decent Home Standard. A key expectation of the Regulator for Social Housing is that all our homes are ‘of good quality, well maintained and safe homes for tenants and comply with the decent homes’ standard.

3.2To maintain our homes at this standard we seek approval to enter two contracts for renewal of Kitchens and Bathrooms, heating and electrical works to be carried out to Council properties in the South and North of the Borough. They are supply and fit contracts and the breakdown of the proposed works is as follows:

South  51 kitchens  43 bathrooms  54 boilers

North  54 kitchens  26 bathrooms  55 boilers

3.3After consultation with Bury Council’s Procurement Team this work will be awarded via a mini competition through the pre-tendered Procure Plus contractor and supplier framework. This arrangement is compliant with all relevant procurement regulations and Council protocols.

3.4This work will be delivered by two building contractors, Emanuel Whittaker Limited and Jackson Jackson and Sons Limited who will fit new kitchens and bathrooms, heating and electrical works.

3.59 organisations registered for the tender and 3 bids were received.

3.6Emanuel Whittaker Limited were ranked first for both lots, North and South but specified they would prefer the South, and it is recommended that they be awarded this area (1st ranked bidder) and Jackson Jackson and Sons (2nd ranked bidder) be recommended for the North.

4.0Social Value 4.1 As part of the procurement process, we require bidders to make proposals on social value initiatives which detail how they will contribute to our social value agenda under the following headings:

2  Contribute to Tenant well-being  Support and protect the Environment  Develop local skills  Contribute to the Bury economy  Contribute to safety of local communities.

4.2Both contracts will ensure that social value is maximised with project specific outcomes agreed at the contract award meetings.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Major Works Programme 2025/26: Part ADecisions 400 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, apologies
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
SA
Councillor Shahbaz ArifCommittee Member, apologies
RB
Councillor Russell BernsteinCommittee Member, in attendance
MS
Councillor Mike SmithCommittee Member, in attendance

All 22 on the meeting page

On this subject at Bury

Search all
  1. Housing Major Works Programme 2025/26 - Part AThis decision
  2. Housing Major Works Programme 2025/26 - Part AApproved
  3. Housing Major Works Programme 2025/26 - Part AApproved
  4. Housing Major Works Programme 2025/26Approved
  5. Proposed Major Works Programme for the Councils housing stock 2024/25Approved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies