Prestwich Village Regeneration Project: Phase 1B and 2 Development Strategy
ApprovedExecutive2 papers
AI summaryBury Cabinet approves around £3.475m commitment for Prestwich Village regeneration Phase 1B and 2 design, planning, demolition and vacant possession work needed to unlock GMCA funding.
What happens nextProject timeline November to MarchDesign, planning submissions, demolition procurement and library works
Who it affectsPrestwich Village and library usersPlus Joint Venture partner Muse Places funding design fees
What was decided
Cabinet approved commitment of circa £3,475,000 to deliver design, planning, demolition and vacant possession activities needed to meet agreed milestones to secure GMCA funding.
The sum is broken down as £2,250,000 underwriting of design fees (initially funded by Muse Places on behalf of the Joint Venture), £1,000,000 in demolition costs and £225,000 to achieve vacant possession.
Cabinet noted the risks and proposed mitigations associated with implementing the development strategy.
Why
The funding is required to reach agreed milestones that will secure GMCA funding for the wider Prestwich Village regeneration.
What happens next
Phase 1B design (RIBA Stage 2/3) and planning application with EIA run November to February, with validation in February to March. Report P2, P3
Longfield demolition procurement runs November to February, with works in March to April, alongside procurement of main works and entry into a PCSA for Phase 1B. Report P4
Library works include design in November to December, DCMS approval in December, tender documents December to January, backlog maintenance February to March, and furniture fit out and decant in March. Report P4
The money
£2,250,000 Underwriting of design fees, funded initially by Muse Places on behalf of the Joint Venture
£1,000,000 Demolition costs
£225,000 Costs to achieve vacant possession
£3,475,000 Total commitment to deliver design, planning, demolition and vacant possession activities needed to secure GMCA funding
Implications
Financial: Around £3.475m is committed, with £2.25m initially underwritten by Muse Places on behalf of the Joint Venture rather than the council's own funds.
Risk: Cabinet noted risks and proposed mitigations associated with the development strategy, although the appendix does not set these out in detail. Report P1
Who and where
The Joint Venture, with Muse Places underwriting design fees
Residents and visitors to Prestwich Village, including library users facing decant Report P4
Contractors procured for Longfield demolition and library works Report P4
Timeline
November to February: Design for Phase 1B, RIBA Stage 2/3 Report P2
November to February: Planning application submission for Phase 1B (EIA) Report P3
February to March: Validation of Phase 1B planning application Report P3
November to February: Procurement for Longfield demolition Report P4
March to April: Longfield demolition works, Phase 1 Report P4
November to February: Procurement of main works and entry into PCSA for Phase 1B Report P4
November to February: Design for Phase 2, RIBA Stages 2+ Report P4
January to March: RIBA Stage 3 for Phase 2 Report P4
November to February: Planning application submission for Phase 2 (EIA) Report P4
November to February: Procurement of main works and entry into PCSA for Phase 2 Report P4
November to December: Design of library space Report P4
December: DCMS approval for library works Report P4
December to January: Tender documents for library works Report P4
February to March: Library backlog maintenance works (latest) Report P4
March: Library furniture fit out (latest) Report P4
March: Library decant and vacant possession (latest) Report P4
Ongoing: Communications with all stakeholders Report P5
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.86
Resolved
Cabinet: 1. Approved the commitment of circa £3,475,000 to deliver design, planning demolition and vacant possession activities required to achieve agreed milestones required to secure GMCA funding. This funding requirement is broken down as follows: · Underwriting of £2,250,000 in design fees (funded initially by Muse Places on behalf of the Joint Venture) · £1,000,000 in demolition costs · £225,000 to achieve vacant possession 2. Noted the risks and proposed mitigations associated with the implementation of this development strategy.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Item Timeline 2026 Start Finish Nov Dec Jan Feb March 24 1 8 15 22 29 5 12 19 26 2 9 16 23 2 9 16 23 30 Design - Phase 1B RIBA Stage 2/3 November February
Planning - Phase 1B Application submission (EIA) November February Validation February March
Procurement/Works - Phase 1B Procurement - Longfield demolition November February Works - Longfield demolition (Phase 1) March April C Procurement - main works/enter into PCSA November February H R Design - Phase 2 I RIBA Stages 2+ November February S RIBA Stage 3 January March T M Planning - Phase 2 A Application submission (EIA) November February S Validation February March P Procurement/Works - Phase 2 E Procurement - main works/enter into PCSA November February R I Provision of Library Facilities O Approval for works, costs, contractor etc January January D Design of library space November December DCMS approval December December Tender documents December January Works - backlog maintenance (latest) February March Library furniture fit out (latest) March March Library decant/VP (latest) March March
Comms All stakeholders Ongoing Ongoing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.