Bury Metropolitan Borough Council
Cabinet, Wednesday 3 December 2025 at 6.00pm

Prestwich Village Regeneration Project: Phase 1B and 2 Development Strategy

Approved Executive 2 papers

AI summaryBury Cabinet approves around £3.475m commitment for Prestwich Village regeneration Phase 1B and 2 design, planning, demolition and vacant possession work needed to unlock GMCA funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTo deliver design, planning, demolition and vacant possession activities
Money£3,475,000Split £2.25m design, £1m demolition, £225k vacant possession
What happens nextProject timeline November to MarchDesign, planning submissions, demolition procurement and library works
Who it affectsPrestwich Village and library usersPlus Joint Venture partner Muse Places funding design fees

What was decided

Cabinet approved commitment of circa £3,475,000 to deliver design, planning, demolition and vacant possession activities needed to meet agreed milestones to secure GMCA funding.

The sum is broken down as £2,250,000 underwriting of design fees (initially funded by Muse Places on behalf of the Joint Venture), £1,000,000 in demolition costs and £225,000 to achieve vacant possession.

Cabinet noted the risks and proposed mitigations associated with implementing the development strategy.

Why

The funding is required to reach agreed milestones that will secure GMCA funding for the wider Prestwich Village regeneration.

What happens next

Phase 1B design (RIBA Stage 2/3) and planning application with EIA run November to February, with validation in February to March. Report P2, P3

Longfield demolition procurement runs November to February, with works in March to April, alongside procurement of main works and entry into a PCSA for Phase 1B. Report P4

Library works include design in November to December, DCMS approval in December, tender documents December to January, backlog maintenance February to March, and furniture fit out and decant in March. Report P4

The money

  • £2,250,000 Underwriting of design fees, funded initially by Muse Places on behalf of the Joint Venture
  • £1,000,000 Demolition costs
  • £225,000 Costs to achieve vacant possession
  • £3,475,000 Total commitment to deliver design, planning, demolition and vacant possession activities needed to secure GMCA funding

Implications

  • Financial: Around £3.475m is committed, with £2.25m initially underwritten by Muse Places on behalf of the Joint Venture rather than the council's own funds.
  • Risk: Cabinet noted risks and proposed mitigations associated with the development strategy, although the appendix does not set these out in detail. Report P1

Who and where

  • The Joint Venture, with Muse Places underwriting design fees
  • Residents and visitors to Prestwich Village, including library users facing decant Report P4
  • Contractors procured for Longfield demolition and library works Report P4

Timeline

  • November to February: Design for Phase 1B, RIBA Stage 2/3 Report P2
  • November to February: Planning application submission for Phase 1B (EIA) Report P3
  • February to March: Validation of Phase 1B planning application Report P3
  • November to February: Procurement for Longfield demolition Report P4
  • March to April: Longfield demolition works, Phase 1 Report P4
  • November to February: Procurement of main works and entry into PCSA for Phase 1B Report P4
  • November to February: Design for Phase 2, RIBA Stages 2+ Report P4
  • January to March: RIBA Stage 3 for Phase 2 Report P4
  • November to February: Planning application submission for Phase 2 (EIA) Report P4
  • November to February: Procurement of main works and entry into PCSA for Phase 2 Report P4
  • November to December: Design of library space Report P4
  • December: DCMS approval for library works Report P4
  • December to January: Tender documents for library works Report P4
  • February to March: Library backlog maintenance works (latest) Report P4
  • March: Library furniture fit out (latest) Report P4
  • March: Library decant and vacant possession (latest) Report P4
  • Ongoing: Communications with all stakeholders Report P5
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.86

Resolved

Cabinet: 1. Approved the commitment of circa £3,475,000 to deliver design, planning demolition and vacant possession activities required to achieve agreed milestones required to secure GMCA funding. This funding requirement is broken down as follows: · Underwriting of £2,250,000 in design fees (funded initially by Muse Places on behalf of the Joint Venture) · £1,000,000 in demolition costs · £225,000 to achieve vacant possession 2. Noted the risks and proposed mitigations associated with the implementation of this development strategy.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Appendix A - Project Delivery Plan

Item Timeline 2026 Start Finish Nov Dec Jan Feb March 24 1 8 15 22 29 5 12 19 26 2 9 16 23 2 9 16 23 30 Design - Phase 1B RIBA Stage 2/3 November February

Planning - Phase 1B Application submission (EIA) November February Validation February March

Procurement/Works - Phase 1B Procurement - Longfield demolition November February Works - Longfield demolition (Phase 1) March April C Procurement - main works/enter into PCSA November February H R Design - Phase 2 I RIBA Stages 2+ November February S RIBA Stage 3 January March T M Planning - Phase 2 A Application submission (EIA) November February S Validation February March P Procurement/Works - Phase 2 E Procurement - main works/enter into PCSA November February R I Provision of Library Facilities O Approval for works, costs, contractor etc January January D Design of library space November December DCMS approval December December Tender documents December January Works - backlog maintenance (latest) February March Library furniture fit out (latest) March March Library decant/VP (latest) March March

Comms All stakeholders Ongoing Ongoing

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix: Prestwich Village Regeneration Project Phase 1B and 2 Development StrategyDecisions 124 KB DownloadRead as text
PDF
Prestwich Village Regeneration Project: Phase 1B and 2 Development StrategyDecisions 414 KB Download

At this meeting

Whole meeting

Who was there

8 of 22 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, apologies
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
SA
Councillor Shahbaz ArifCommittee Member, apologies
RB
Councillor Russell BernsteinCommittee Member, in attendance
MS
Councillor Mike SmithCommittee Member, in attendance

All 22 on the meeting page

On this subject at Bury

Search all
  1. Prestwich Village Regeneration Project: Phase 1B and 2 Development StrategyThis decision
  2. Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations StrategyApproved
  3. Prestwich Village Regeneration Project: Delivery of Phase 1A (Travel Hub) - Additional Funding RequestApproved
  4. Prestwich Village Regeneration Project: Phases 1B & 2 Appointment of Pre-Construction Services Agreement Contractor Part AApproved
  5. Prestwich Village Regeneration Project: Delegated Authority to Appoint the Third-Party Operator for Phase 1A (Travel Hub)Approved
  6. Prestwich Village Regeneration Project: Phase 1B & 2 Appointment of Demolition Contractor - Part AApproved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies