Cabinet, Wednesday 11 March 2026 at 6.00pm

Corporate Plan Quarter Three 2025-26 Performance & Delivery

Noted Executive 1 paper

AI summaryCabinet noted Quarter Three 2025-26 progress against the Corporate Plan, with 22 milestones on track, 14 amber, 1 complete and 1 red.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted22 on track, 14 amber, 1 complete, 1 red
MoneyNo direct financial implicationsBut £7.5m 2026/27 funding gap remains
What happens nextQ4 monitoringItems to February Cabinet and Budget Council
Who it affectsBorough residents and servicesCouncil tenants, children, market traders

What was decided

Cabinet noted the Quarter Three position on progress against the Corporate Plan 2025-26.

Of the objectives planned for Quarter Three, 1 is complete, 22 are on track, 14 are not on track but the risks have been addressed, and 1 is highlighted red and will be delivered in this corporate plan. Report P25

Why

To enable transparency and robust monitoring of performance and delivery of the Corporate Plan. Report P10

What happens next

A mitigation plan has been agreed by the Performance, Delivery and Transformation and Finance Boards to support delivery of the red-rated milestone within new timeframes. Report P47

Items due at Cabinet and Budget Council in February 2026 include updated capital programme and capital strategy, further savings proposals to reduce the £7.5m gap, the Let's Tackle Poverty strategy and the Wellness strategy business case. Report P43, P61, P62, P67

A funding application for Prestwich Phases 1B and 2 will be made with a view to Cabinet approval in March or April 2026, subject to meeting three GMCA milestones. Report 2.1, P35

The money

  • £80m Confirmed by central government to upgrade the transport interchange, alongside the market canopies and flexihall investment Report 2.1, P35
  • £80k Delivered to community and Culture Organisations through 25 individual cultural events Report 3.1, P38
  • £3.9m Over 3-years to Bury for 80 additional High Needs places, replacing withdrawn Free Special Primary School funding Report 4.1, P40
  • £7.5m Funding gap for 2026/27 to be further reduced at Cabinet and Budget Council in February Report P43
  • £100k Grant from HNDU secured to progress Heat Network Design Phase Report P51
  • £3m Additional savings targeted over the next 3 financial years through the Procurement and Contract Management Operating Model business case Report P67

Implications

  • Financial: A £7.5m funding gap remains for 2026/27 and further savings proposals are required to be considered at Cabinet and Budget Council in February. Report P43
  • Risk: One milestone is rated red, with a mitigation plan agreed by the Performance, Delivery and Transformation and Finance Boards to support delivery within new timeframes. Report P47
  • Staffing: Sickness absence rose from 10 days in June to 11.7 days in December, partly due to seasonal illness, although year on year sickness has improved. Report P45
  • Other: The Unit 4 finance system upgrade is delayed beyond the original April target while feeder system, process mapping and coding issues are addressed. Report P43

Who and where

  • Council tenants, with average waiting time on the housing register reduced from 788 to 611 days Report 3.1, P38
  • Children and young people with SEND, with 3100 EHCPs in Bury Report 4.1, P40
  • Foster and kinship carers using the new hub at Bury Town Hall Report 4.1, P40
  • Bury Market traders, with new canopies completed ahead of schedule Report 2.1, P35
  • Falcon and Griffin Extra Care Scheme tenants across 69 properties, rated Good by the CQC Report 3.1, P38
  • Council staff, with 71.4 percent of annual employment reviews completed Report P45

Timeline

  • 4 November 2025: Education and Inclusion Strategy launched Report 4.1, P40
  • 25 November 2025: Overview and Scrutiny Committee reviewed Community Safety Partnership work Report 3.1, P38
  • October to December 2025: Reporting period for Quarter Three Report P7
  • 21 January 2026: Let's Tackle Poverty summit held with Team Bury partners Report 3.1, P38
  • February 2026: Cabinet and Budget Council to consider updated capital programme, savings proposals, Let's Tackle Poverty strategy and Wellness strategy business case Report P43, P61, P62, P67
  • March or April 2026: Cabinet approval sought for Prestwich Phases 1B and 2 funding application Report 2.1, P35
  • April 2026: First Live Well centre in Whitefield due to partially open Report 3.1, P38
  • First week of July 2026: Radcliffe Hub due to be complete Report P49

Plain English for the jargon

  • CLA: Children Looked After
  • CPP: Child Protection Plan
  • CVD: Cardiovascular Disease
  • EET: Education, Employment, or Training
  • ELT: Executive Leadership Team
  • KPI: Key Performance Indicator
  • MTFS: Medium Term Financial Strategy
  • SEND: Special Educational Needs and Disabilities
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.142

Resolved

Cabinet noted the Quarter Three position on progress against the Corporate Plan 2025-26.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1. In June 2025, Cabinet approved the Council’s Corporate Plan for 2025/26. The Plan sets out the Council’s strategic priorities and delivery objectives for the financial year and our role in delivering the overarching vision of the borough’s LET’S Do It! Strategy.

Despite the scale of ambition contained with the 2024/25 Corporate Plan, and alongside those other unforeseen activities that required additional capacity, most of the plan was delivered. However, there is still much work to do to deliver the Council’s three priorities, all of which contain multi-year programmes of work, to align with the vision set out in LET’S. Focus will need to continue to be sustained to improve outcomes in these areas:

 Sustainable Inclusive Growth  Improving Children’s Lives  Tackling Inequalities

Within these priorities, the Corporate Plan for 2025/26 includes clear and tangible deliverables, with principal regeneration sites underway and new services up and running. The outcomes of inspections with the CQC and Ofsted, and potentially Housing, will be known during the year and therefore provision has been made within the Plan for the actions which follow. With regards to Tackling Inequalities, the national and regional integrated health and care systems are subject to significant change as part of the NHS reform program. As such, local plans will need to be monitored and reviewed considering new models of care, mapped against our understanding of need at a neighbourhood level.

2. These challenges continue to be worked on by Team Bury as part of the refreshed LET’s Do It! strategy, with particular focus on tackling the root causes of deprivation and ensuring sustainable economic growth that all residents can share success in.

3. To support monitoring of the Plan, alongside measuring delivery of the agreed milestones (Appendix One), an initial set of Key Performance Indicators (KPIs) was set out. The three priorities and an additional enabling priority are repeated for the 2025/26 planning year. Key objectives have been described against each of these priorities, together with a clear set of quarterly delivery milestones.

4. This report describes the progress made in the third quarter of the financial year (October – December 2025

Recommendation(s)

5. Cabinet is asked to: a. Note the Quarter Three position on progress against the Corporate Plan 2025-26

Reasons for recommendation(s) 6. To enable transparency and robust monitoring of performance and delivery of the Corporate Plan.

Alternative options considered and rejected

7. Not applicable. _________________________________________________________ Report Author and Contact Details:

Name: Helen Corbishley Position: Head of Performance and Delivery Department: Corporate Core E-mail: [email protected] ________________________________________________________________ Background

Background

The 2025/26 Corporate Plan was agreed by Cabinet in June 2025 and sets out the Council’s strategic priorities and delivery objectives for the year. The final version of the Plan is below:

_____________________________________ Links with the Corporate Priorities: 9. This report supplements the LET’s Do It! Outcomes Report in terms of providing further information on the contribution of the Council to the 2030 vision. The Corporate Plan priorities are linked to the seven objectives of the LET’S vision. _________________________________________________________ Equality Impact and Considerations: 10. An EIA was completed at the launch of the Corporate Plan for 2025/2026 ensuring inclusion was at the heart of it. This report demonstrates the continuing commitment to inclusion in all that we do as a council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Plan Quarter Three 2025-26 Performance & DeliveryDecisions 1.7 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 18 on the meeting page

On this subject at Bury

Search all
  1. Corporate Plan Quarter Three 2025-26 Performance & DeliveryThis decision
  2. Corporate Plan Quarter 1 2026-27 Performance & DeliveryNoted
  3. Corporate Plan Quarter Four 2025-26 Performance & DeliveryNoted
  4. Corporate Plan 2026-27Approved
  5. Corporate Plan Quarter Two 2025-26 Performance & DeliveryNoted
  6. 2025/26 Corporate Plan - Quarter One UpdateNoted

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open