Corporate Plan Quarter 1 2026-27 Performance & Delivery

Noted Executive 1 paper

AI summaryBury Cabinet noted the Quarter 1 2026-27 Corporate Plan position: 18 of 31 objectives on track, one flagged as a significant delivery risk.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarter 1 position on 2026-27 Corporate Plan progress
MoneyNot stated
What happens nextQuarter 2 focusFinance Improvement Plan recovery, children's programmes, housing, workforce
Who it affectsBorough-wideResidents, council services and workforce

What was decided

Cabinet noted the Quarter 1 position on progress against the Corporate Plan 2026-27. Report P6

No alternative options were considered. Report P6

Why

To enable transparency and robust monitoring of performance and delivery of the Corporate Plan. Report P6

What happens next

Recovery activity is needed in Quarter 2 for the Finance Improvement Plan and Unit4 implementation. Report P46

Recovery of milestones within Best Start in Life, Family Hubs, Families First and Youth Justice programmes. Report P46

Continued focus on housing demand, homelessness pressures, workforce wellbeing and Prestwich regeneration dependencies. Report P46

Options considered

  • Rejected: Not applicable. No alternative options were considered for this noting report. Report P6

Implications

  • Risk: The Finance Improvement Plan is the only objective identified as a significant delivery risk, with Unit4 implementation delays and the Digital Roadmap affected by the Housing QL project. Report P46, P66, P68
  • Staffing: Sickness absence continues to rise, with mental health the largest single cause; a wider review of workforce wellbeing support is ongoing. Report P40, P41
  • Other: Housing demand and statutory homelessness continue to increase, and health inequalities remain a long-term challenge. Report P30, P31, P38
  • Legal: There are no direct legal implications arising from this updating report. Report P10
  • Equalities: An EIA was completed with the finalisation of the Corporate Plan; activities within the plan will require individual EQIAs. Report P6
  • Climate: The data tracks progress towards the Council's environmental commitments, though there are no specific environmental considerations in this report. Report P7
  • Financial: There are no financial implications arising directly from this report. Report P11

Who and where

  • Bury residents Report P5, P18, P25, P34
  • Children, young people and families Report P21, P24, P25
  • Adult Social Care service users and carers Report P31, P35
  • Council workforce Report P40, P41
  • Voluntary, community and faith sector partners Report P61

Timeline

  • April 2026: Cabinet approved the 2026-27 Corporate Plan. Report P3, P6
  • April to June 2026: Quarter 1 reporting period covered by this performance update. Report P4
  • July 2026: Live Well Centre in Whitefield is planned to be operating. Report P60
  • Quarter 2 2026-27: Recovery action required for Finance Improvement Plan and slipped children's programmes. Report P27, P46

Plain English for the jargon

  • LET'S Do It!: Bury's long-term community strategy and vision for the borough to 2030.
  • RAG: Red, Amber, Green performance status used to indicate progress and risk.
  • CQC: Care Quality Commission.
  • SEND: Special Educational Needs and Disabilities.
  • NEET: Not in Education, Employment or Training.
  • CRSTS: City Region Sustainable Transport Settlement.
  • Unit4: The Council's Enterprise Resource Planning and finance system.
  • STAR Chamber: Corporate challenge and assurance process used to review service performance, priorities and resources.
  • EIA / EQIA: Equality Impact Assessment.
  • VCFA: Voluntary, Community and Faith Alliance.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.64

Resolved

Decision(s): Cabinet: - Noted the Quarter One position on progress against the Corporate Plan 2026-27. Reasons for decision(s) - To enable transparency and robust monitoring of performance and delivery of the Corporate Plan. Alternative options considered and rejected - Not applicable.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Non-Key

Date: 09 September Report to: Cabinet 2026 Subject: Corporate Plan Quarter 1 2026-27 Performance & Delivery Deputy Leader and Cabinet Member for Finance and Corporate Report of Services

Summary 1. In April 2026, Cabinet approved the Council’s Corporate Plan for 2026-27. The Plan sets out the Council’s strategic priorities and delivery objectives for the financial year and our role in delivering the overarching vision of the borough’s LET’S Do It! Strategy.

This report provides an overview of progress during Quarter One (April to June 2026). The Council has made a positive start to delivery of the 2026-27 Corporate Plan, of the Council's 31 objectives, 18 are on track, 12 are progressing with mitigating actions in place and one objective has been identified as a potential risk.

Performance data presents a mixed but generally positive picture with improvements in a number of areas and pressures remaining in others. The quarter has also seen substantial visible delivery across the borough, with residents seeing progress on key initiatives, schemes and developments.

Recommendation(s) 2. Cabinet is asked to: • Note the Quarter One position on progress against the Corporate Plan 2026-27. Reasons for recommendation(s) 3. To enable transparency and robust monitoring of performance and delivery of the Corporate Plan. Alternative options considered and rejected 4. Not applicable. _________________________________________________________ Report Author and Contact Details: Name: Sarah Hammersley Position: Performance & Intelligence Manager Department: Corporate Core E-mail: [email protected] ________________________________________________________________ Background 5. The 2026/27 Corporate Plan was agreed by Cabinet in April 2026 and sets out the Council’s strategic priorities and delivery objectives for the year. The final version of the Plan is available in the appendix. _________________________________________________________ Links with the Corporate Priorities: 6. This report supplements the LET’s Do It! Outcomes Report in terms of providing further information on the contribution of the Council to the 2030 vision. The Corporate Plan priorities are linked to the seven objectives of the LET’S vision. _________________________________________________________ Equality Impact and Considerations: 7. An EIA was completed with the finalisation of the Corporate Plan for 2026/2027 ensuring inclusion was at the heart of it. The corporate plan is set out to improve outcomes for all residents with equity and inclusion threaded throughout. The plan has no negative impacts however activities within the plan will require individual EQIAs to ensure equity and inclusion is carried through from this plan into the activities and outcomes. This report demonstrates the continuing commitment to inclusion in all that we do as a Council.

Environmental Impact and Considerations: 8. There are no specific environmental considerations within this report however the data tracks progress towards the environmental commitments within the Council’s Corporate Plan.

Assessment and Mitigation of Risk: Risk / opportunity Mitigation

Lack of capacity to deliver against the Corporate Plan priorities which reduces our ability to achieve the LET’S Vision ___________________________________________________________________ Procurement Implications: 9. No procurement implications ___________________________________________________________________ Legal Implications:

This is an updating report to Cabinet and is part of our governance assurance process, there are no direct legal implications arising from this report.

Financial Implications 10. There are no financial implications arising directly from this report.

Appendices: Appendix One – Corporate Plan 2026/27 on a page Appendix Two – Corporate Plan 2026/27 Q1 Delivery Summary Appendix Three - Corporate Plan 2026-27 Q1 Performance Dashboards

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Plan Quarter 1 2026-27 Performance & DeliveryDecisions 990 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, apologies due to council business
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. Corporate Plan Quarter 1 2026-27 Performance & DeliveryThis decision
  2. Corporate Plan Quarter Four 2025-26 Performance & DeliveryNoted
  3. Corporate Plan 2026-27Approved
  4. Corporate Plan Quarter Three 2025-26 Performance & DeliveryNoted
  5. Corporate Plan Quarter Two 2025-26 Performance & DeliveryNoted
  6. 2025/26 Corporate Plan - Quarter One UpdateNoted

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open