Prestwich Village Regeneration Project: Phase 1B & 2 Appointment of Demolition Contractor - Part A
ApprovedExecutive1 paper
AI summaryBury Cabinet appoints DSM Demolition Limited to demolish the Longfield Centre for £537,437.14 excluding VAT, part of the Prestwich Village Regeneration Project, to meet a GMCA funding deadline by end March 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDemolition contractor appointed via compliant PCR 2015 tender
Money£537,437.14 excluding VATDemolition contract sum, within £1m underwriting
What happens nextDemolition in two phases from end March 2026. Completion expected by Summer 2026
Who it affectsPrestwich Village, Longfield CentreJV with Muse Places delivering regeneration scheme
What was decided
Cabinet accepted the PCR 2015 tender process as compliant and approved the appointment of DSM Demolition Limited to demolish the Longfield Centre for £537,437.14 excluding VAT, subject to contract terms. Report P7
Cabinet accepted that a small adjustment to the contract sum may be needed, based on an outstanding Refurbishment/Demolition survey that cannot complete until the Prestwich Library vacates. Report 2.2, 5.21
Cabinet delegated authority to the Director of Law and Governance, in consultation with the Executive Director of Place or Director of Regeneration and Project Delivery, to finalise and execute the contract. Report 2.3, 3.2
Why
Approval is needed to achieve a meaningful start on site of demolition works before the end of March 2026, one of three GMCA milestones required to release funding for the next phase of the project. Report 1.3, 1.4, 5.8
Delegation to senior officers is intended to avoid delay and keep the contract execution within the required GMCA timescales. Report 3.2, 4.2
DSM Demolition Limited submitted the Most Economically Advantageous Tender at 90.32%, were the only contractor showing a start on site within the required timescale, and priced below the £1m figure approved in December 2025. Report 5.20, 5.21, 5.22
What happens next
Finalise contractual arrangements and execute the contract with DSM Demolition Limited through the Pagabo Framework for the North. Report 2.3, 5.14, 5.16
Commence demolition of the Longfield Centre in two phases: end March 2026 to mid May 2026, and mid April 2026 to start June 2026, with completion by Summer 2026. Report P31
Complete the R&D (asbestos) survey once the Prestwich Library vacates, then fix the final contract sum (adjustment not to exceed the £1m approval). Report 2.2, 5.21
The money
£537,437.14 excluding VAT Demolition contract sum awarded to DSM Demolition Limited Report P7, 5.21
£1m Underwriting of demolition costs approved at December 2025 Cabinet Report 5.21
£0.537m Cost of demolition within the £1m funding envelope
Options considered
Chosen: Pagabo Framework for the North (Lot 4). Shorter timeframe than the Salford Demolition Framework, both compliant Report 1.4, 5.13, 5.14
Rejected: Salford Demolition Framework. Discounted in favour of the Pagabo Framework because priority is timescale Report 5.14
Implications
Financial: The Council is yet to receive the GMCA Grant Funding Agreement; if the GMCA bid fails, the demolition cost falls to the Council as unbudgeted revenue spend. Report P68, P69, 11.2
Legal: The Pagabo Framework was published in November 2021 and is governed by the Public Contracts Regulations 2015; the award followed a compliant route. Report 10.2
Risk: Site conditions, unforeseen issues, supplier availability and asbestos are the main delivery risks, mitigated through site investigations, cost planning and a robust procurement strategy. Report P70, P71
Equalities: A full Equality Impact Assessment identified some temporary negative impacts during demolition and construction, with mitigations reducing or eliminating them. Report 8.2
Climate: The wider project is low and net zero carbon by design and aims to uplift biodiversity by more than 40%, with sustainable materials, PV panels and air source heat pumps. Report P64, P65
Who and where
Remaining tenants of the Longfield Centre (full vacant possession expected by 7th April 2026)
Users of the Prestwich Library, which is to be rehoused in the new community hub Report P19, 5.21
Prestwich Village residents, businesses and visitors during the demolition period Report 5.2
Bury Council and Muse Places as partners in the Prestwich Regeneration LLP Report 5.4, P81
Timeline
13th October 2021: Cabinet approved formation of the Prestwich Regeneration LLP with Muse Places Report 5.4
12th July 2023: Cabinet progress update and draft development plan Report 5.3
July 2024: Planning application granted enabling demolition activity Report P32
3rd December 2025: Cabinet approved demolition cost underwrite of up to £1m Report 5.21
January 2026: Expression of Interest issued to demolition contractors Report 5.16
January 2026: Tender documents issued to seven contractors Report 5.16
26th January 2026: Stage Two of Travel Hub operator tender commenced
18th February 2026: Tender return date for demolition Report 5.16
27th February 2026: Planning application for Phases 1B and 2 submitted to the Local Planning Authority Report P28
End March 2026: Target for meaningful start on site of demolition works (GMCA milestone) Report 1.3, 5.8
End March 2026 to mid May 2026: Demolition Phase 1 Report P31
Mid April 2026 to start June 2026: Demolition Phase 2 Report P31
Early to mid April 2026: Expected appointment of Travel Hub operator
7th April 2026: Expected full vacant possession of the Longfield Centre
July 2026: Expected practical completion of Phase 1A Travel Hub Report 1.2, 5.6
Summer 2026: Demolition of the Longfield Centre expected to be complete
Plain English for the jargon
JV: Prestwich Regeneration LLP, the Joint Venture company of Bury Council and Muse Places Ltd delivering the project
GMCA: Greater Manchester Combined Authority, the ten Greater Manchester councils and the Mayor working together
PCR 2015: Public Contracts Regulations 2015, the primary UK public sector procurement legislation
PCSA: Pre-Construction Services Agreement, engaging a contractor for pre-construction work before the main building contract
VP: Vacant Possession, when a property is delivered empty by an agreed date
EIA: Environmental Impact Assessment, a mandatory procedure for large developments likely to have environmental effects
R&D (Refurbishment/Demolition) survey: Survey to locate asbestos-containing materials before demolition
GFA: Grant Funding Agreement, the agreement with GMCA to release funding
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.139
Resolved
Cabinet: 1. Accepted that the tender process that was undertaken via a Public Contracts Regulations 2015 (PCR 2015) was a compliant process, and approved the appointment of DSM Demolition Limited (company number 02266325) to undertake the demolition works package with a total estimated contract value of £537,437.14 excluding VAT subject to the agreement of the contract terms and conditions; 2. Accepted there may be a small adjustment required to fix the above contract sum based on an outstanding R&D (Refurbishment/Demolition) survey that cannot be fully carried out until the Prestwich Library vacates its current location; and 3. Delegated authority to the Director of Law and Governance in consultation with the Executive Director of Place or Director of Regeneration and Project Delivery to finalise contractual arrangements and execution of the contract.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1The Prestwich Village Regeneration Project will deliver a comprehensive re- development of the Prestwich Village site including the Longfield Centre. The Council has formed a Joint Venture (the JV) with Muse Places to deliver this activity. The project will deliver a new village centre and contribute to the Council’s strategic aims (Bury 2030) and ‘Let’s Do It’ Strategy.
1.2Extensive progress continues to be made on the development and delivery of the project. The first phase (Phase 1A Travel Hub) remains on site with construction of the new facility still on schedule to be delivered by July 2026.
1.3Work has continued at an incredibly fast pace to prepare for the delivery of the remaining development phases (Phases 1B and 2). This, as previously explained in the approved Cabinet report 3rd December 2025 is to hit three Greater Manchester Combined Authority (GMCA) milestones by end March 2026 to secure funding from the GMCA. These milestones are – a meaningful start on site of demolition works (of the Longfield Centre), submission of the planning application for the next phase and early contractor engagement.
1.4Further to the approval at Cabinet on 3rd December 2025, preparation work in relation to the meaningful start on site of demolition works has been carried out at pace. This milestone has now reached a point where approval from Cabinet is required for the appointment of the demolition contractor following a Public Contracts Regulations 2015-compliant procurement process through the Pagabo National Framework for Demolition and Land Remediation- Lot 4 (Pagabo Framework for the North) to keep the delivery of the project on track.
1.5Approval at Cabinet is requested due to the value of the current demolition contract (£537,437.14 excluding VAT) requiring a key decision to appoint DSM Demolition Limited (company number 02266325) to carry out the required demolition of the Longfield Shopping Centre, noting that this will be undertaken in two phases as explained further in this report. This is a follow-up report to the one approved in December 2025.
Recommendation(s)
It is recommended that Cabinet: 2.1 Accept the tender process that was undertaken via a Public Contracts Regulations 2015 (PCR 2015) was a compliant process, and approve the appointment of DSM Demolition Limited (company number 02266325) to undertake the demolition works package with a total estimated contract value of £537,437.14 excluding VAT subject to the agreement of the contract terms and conditions.
2.2Accept there may be a small adjustment required to fix the above contract sum based on an outstanding R&D (Refurbishment/Demolition) survey that cannot be fully carried out until the Prestwich Library vacates its current location.
2.3Delegate authority to the Director of Law and Governance in consultation with the Executive Director of Place or Director of Regeneration and Project Delivery to finalise contractual arrangements and execution of the contract.
Reasons for recommendation(s) 3.1 Approval of the demolition contractor is required for there to be a meaningful start on site of demolition works ahead of the end March 2026 to meet one of the three GMCA milestones to secure funding to deliver the next phase of the Prestwich Village Regeneration Project.
3.2Delegating authority to the Director of Law and Governance in consultation with the Executive Director of Place or Director of Regeneration and Project Delivery will enable the contract to be executed without delay and within the required timeframes.
Alternative options considered and rejected 4.1 No alternative way(s) of selecting the demolition contractor has been considered as the tender process was via a framework ensuring procurement was conducted in a fair, transparent and open manner.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.