Prestwich Village Regeneration Project: Delegated Authority to Appoint the Third-Party Operator for Phase 1A (Travel Hub)
ApprovedExecutive1 paper
AI summaryBury Cabinet delegates authority to appoint a third party operator for the Prestwich Travel Hub, with contract award expected by 31 March 2026 and construction due to complete July 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo delegations to senior officers to award and execute contract
MoneyNot yet finalisedOperator costs expected to be fully recovered from car parking income
What happens nextAward by 31 March 2026Contract execution expected 3 April 2026, commencement w/c 6 April
Who it affectsPrestwich Village Travel HubOperator, contractor, future users and local businesses
What was decided
Cabinet delegated authority to the Executive Director of Place, with the Director of Regeneration and Project Delivery, to approve completion of the procurement and award the contract to the preferred third party operator. Report P7
Cabinet delegated authority to the Director of Place, with the Director of Law and Governance and the Director of Finance, to finalise contractual arrangements and execute the contract. Report 2.2
The delegation removes the need to return to Cabinet and lets the council meet the procurement timetable. Report 10.2, P32, 5.17
Why
The Travel Hub is due to reach practical completion in July 2026, and an operator must be in contract from day one to manage the facility and replace parking lost when later phases begin. Report 1.2, 1.3, 5.6, 5.7
Appointing the operator early lets them work with VINCI Construction UK Limited on operational management items such as security, payment systems, signage and access, avoiding abortive work and extra cost. Report 1.4, 5.9
Using the Crown Commercial Services Framework via a two stage process complies with procurement law and the council's Contract Procedure Rules. Report 5.11, 5.12, 10.1
What happens next
Consensus call with CCS to confirm final scores in the week commencing 9 March 2026, followed by award recommendation, standstill and outcome letters in the week commencing 16 March 2026. Report 5.16, P30
Proposed contract award date 31 March 2026, expected execution by both parties on 3 April 2026, and expected commencement in the week commencing 6 April 2026. Report 5.16, P30, P31
The preferred operator will then work with VINCI Construction UK Ltd to finalise design items ahead of the Travel Hub becoming operational. Report P31
Options considered
Chosen: Delegate authority to senior officers to award and execute the contract. Enables the preferred operator to engage with VINCI during the final construction stages and avoids delay to the Travel Hub opening Report P7, 2.2, P12, 4.1
Rejected: Complete the full procurement process and seek Cabinet approval at a future meeting. Would reduce the operator's contact time with VINCI Construction UK Ltd and could delay the opening of the Travel Hub Report P12, 4.1
Implications
Financial: Procurement financial implications are not yet finalised; operator costs are expected to be fully recovered from car parking income. Report 11.1, 11.2
Legal: The route to market is a compliant Framework under the Public Contracts Regulations 2015 and the Procurement Act 2023, and Cabinet can lawfully delegate the award decision under the council's Constitution. Report 10.1, 10.2
Equalities: A full Equality Impact Assessment was completed as part of planning permission and there are no outstanding equalities concerns at this stage. Report 8.2, P59
Climate: The Travel Hub supports low and net zero carbon design and is part of a scheme projected to uplift biodiversity by more than 40%. Report 9.2, P62, P63
Risk: Risks include submitted bids not meeting the specification and delay in appointing the operator, mitigated by regular timeline reviews and early instruction of Legal Services. Report P64, P65, P66
Staffing: The project has created 130 construction jobs, with an estimated 350 new jobs to follow across the regeneration, plus 600+ hours of on site training and 58% of construction supply chain spend directed to local businesses. Report P47, P56
Who and where
Residents and visitors of Prestwich Village who will use the new Travel Hub Report 5.7, P43
VINCI Construction UK Limited as the Travel Hub contractor Report 1.4, 5.6
The preferred third party operator to be appointed through the CSS Framework Report 1.5, 5.12
Local businesses in Prestwich Village benefiting from retained parking and improved access Report P47, P56
Future users of Phase 1B retail, market hall, leisure, library and public realm and Phase 2 housing of 248 new homes Report P19, 5.5
Timeline
13th October 2021: Cabinet approved formation of the Prestwich Regeneration LLP joint venture with Muse Places Report 5.4
12th July 2023: Cabinet received progress update and draft development plan for Prestwich Village Regeneration Report 5.3
15th October 2025: Cabinet approved the external operator model and the two stage procurement process for the Travel Hub Report 1.5, 5.11
31st October to 21st November 2025: Soft market engagement under the Crown Commercial Services Framework Report 5.13
27th January 2026: Invitation to tender launched for the third party operator Report 5.14
27th February 2026: Invitation to tender closed Report 5.14
w/c 9th March 2026: Consensus call with CCS to determine final scores following evaluation Report 5.16, P30
w/c 16th March 2026: CCS award recommendation report, approval, outcome letters and draft contract to preferred operator, with standstill period Report 5.16, P30
31st March 2026: Proposed award date of the operator contract Report 5.16, P30
3rd April 2026: Expected execution of the contract by both parties Report 5.16, P30
w/c 6th April 2026: Expected commencement of the operator contract Report 5.16, P30, P31
July 2026: Travel Hub construction scheduled to reach practical completion Report 1.2, 5.6
Plain English for the jargon
JV: Prestwich Regeneration LLP, the joint venture between Bury Council and Muse Places Ltd delivering the regeneration project
PC: Practical Completion, the stage when construction works are finished save for minor defects, allowing occupation for the intended purpose
ITT: Invitation to Tender, a formal competitive procurement process to invite suppliers to submit offers
CCS: Crown Commercial Services Framework, a public sector framework supporting best value procurement
PCR 2015: Public Contracts Regulations 2015, the primary UK legislation governing public sector procurement above set thresholds
LOT: A specific category within a procurement framework separating products and services by subject
CRSTS: City Region Sustainable Transport Settlement, a UK Government programme to transform local transport networks
MEP: Mechanical, Electrical and Plumbing systems within a building
EIA: Environmental Impact Assessment, a mandatory procedure for large scale development projects likely to have environmental effects
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.138
Resolved
Cabinet: 1. Approved a delegation of authority to the Executive Director of Place in consultation with the Director of Regeneration and Project Delivery to approve the completion of the procurement process and award the contract; and 2. Approved a delegation of authority to the Director of Place in consultation with the Director of Law and Governance and the Director of Finance to finalise contractual arrangements and execute the contract.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1The Prestwich Village Regeneration Project will deliver a comprehensive re- development of the Prestwich Village site including the Longfield Centre. The Council has formed a Joint Venture (the JV) with Muse Places to deliver this activity. The project will deliver a new village centre and contribute to the Council’s strategic aims (Bury 2030) and ‘Let’s Do It’ Strategy.
1.2Extensive progress continues to be made on the development and implementation of the project. The first phase (Phase 1A Travel Hub) remains on site with construction of the new facility still on schedule to be delivered by July 2026.
1.3Once the Travel Hub has reached practical completion (PC), for it to become operational, there will need to be a management team in place from day one to oversee the day-to-day running and facilities management responsibilities.
1.4It is also crucial that the third-party operator is appointed and in contract as soon as possible. This will enable them to connect with VINCI Construction UK Limited who are constructing the Travel Hub and for their input with the operational management items before PC and handover of the building, avoid abortive work and unnecessary costs to the project.
1.5Further to Cabinet on 15th October 2025 that approved the recommended operations management model for the Travel Hub and consequently, the undertaking of a two-stage procurement process for appointment of an external operator, the Crown Commercial Services Framework (CSS) was agreed as the preferred route to market. The first stage (soft market engagement) is complete, and the second stage (invitation to tender [ITT] and evaluation process) is currently being undertaken.
1.6Approval is therefore being requested to delegate authority to appropriate senior management officers to be able to scrutinise and approve the procurement process once complete and approve the awarding of the contract to the preferred third-party operator to avoid unnecessary delay.
Recommendation(s) It is recommended that Cabinet approve: 2.1 Delegation of authority to Executive Director of Place in consultation with the Director of Regeneration and Project Delivery to approve the completion of the procurement process and award the contract.
2.2Delegation of authority to the Director of Place in consultation with the Director of Law and Governance and the Director of Finance to finalise contractual arrangements and execute the contract.
Reasons for recommendation(s) 3.1 Approval of the appointment of the third-party operator is required in order for the Travel Hub to become operational once construction has reached PC and handover has taken place.
3.2As per the 15th October 2025 Cabinet approval, an operator should be appointed as soon as possible in the construction delivery process to enable them to contribute to the final stages the of construction i.e. operational management items. This will also help with the smooth opening of the facility.
3.3Delegating authority to the Director of Law and Governance in consultation with the Executive Director of Place and/or Director of Regeneration and Project Delivery and the Director of Finance will enable the contract to be expediently executed within required timeframes.
Alternative options considered and rejected
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.