The Committee: (1) Authorised Officers to make adjustments to the recommended programme, within the overall budget, as a result of improved estimates becoming available where the adjustment was less than £20K; (2) Approved the allocation of the planned maintenance budget for schemes for 2016/17.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1An end of year report went to Strategy and Resources Committee on 5 April 2016.
2.2Annexe 1 shows the 2016/17 current position for spend and commitments a forecast spend on schemes. STRATEGY AND RESOURCES COMMITTEE 27 JUNE 2016
2.3So far work in 2016/17 has been undertaken on those schemes which were placed “on hold” during spending restrictions in place during 201/16.
2.4Officers have delegated authority to make adjustments to schemes of up to £20,000 subject to the programme being completed within the approved budget.
3 Planned Maintenance – 2016/17 new schemes
3.1The corporate property group and building managers have contributed to a working ten year plan of building maintenance works required for the Council’s property. This will be presented to Committee on 27 September 2016.
3.2The plan has been used to prepare a set of planned maintenance schemes to be carried out during 2016/17 and these are contained in Annexe 1
3.3The proposed schemes in the schedule are all urgent priority.
3.4Required works totalled £690k for the year, after prioritising the urgent works into categories this was reduced to a more manageable figure of £322k.
3.5This value still exceeds the budgets available and so further consideration has been given to reprioritising. In the event that one of the schemes now excluded from the plan requires emergency work, then this will be funded from the property maintenance reserve by delegated authority.
3.6Annexe 2 contains the final list of proposed works at the reduced figure of £175k this includes some additional budgets for Regulatory works
3.7Approval is sought in principle for the whole schedule with the proviso that the overall budgets are not exceeded. This will enable some flexibility within the overall programme should some schemes, once priced, be of a lower value.
3.8Where there is scope to carry out further schemes then approval for the drawdown of funds from the property maintenance reserve will be sought.
4 Planned Maintenance - 2016/17 – held over schemes progress
4.1Annexe 1 contains the current position of actual spend and forecast outturn for the current year schemes.
4.2Financial resources were released for works on hold following financial restrictions last year.
5 Financial and Manpower Implications
5.1The property maintenance reserve as at 1 April 201 was £239,000. Of this £159,000 is earmarked for the 2015/16 carried forward schemes. STRATEGY AND RESOURCES COMMITTEE 27 JUNE 2016
2016/17 planned funding of schemes
£000s Backlog maintenance base budget 175 Regulatory works base budget 30 Watercourses works base budget 5 2016/17 total 210 S106 drawdown re path works at Longmead 20 2015/16 carried forward schemes from property maintenance reserve 159 (including £17k for 2015/16 schemes in progress) 2015/16 carried forward schemes total 179 Total scheme funding 389
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.