The Committee: (1) Noted the current position/progress on the planned maintenance programme; (2) Noted the changes made to the programme under authority delegated to Officers; (3) Authorised the carry forward of unspent budget in 2017/18 to 2018/19 (4) Authorised Officers to proceed with the 2018/19 proposed planned maintenance works; (5) Authorised virement from the property reserve to fund shortfall for 2018/19.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
Report of the: Head of Property and Regeneration Contact: Mark Shephard Urgent Decision?(yes/no) No If yes, reason urgent decision required: N/A Annexes/Appendices (attached): Annexe 1: 2017/18 current position Annexe 2: 2018/19 Proposed works Other available papers (not attached):
Report summary The report notes progress and changes to the current planned maintenance programme and seeks approval for 2018/19 programme of proposed works
Recommendation (s) (1) Notes the current position/progress on the planned maintenance programme
(2) Notes the changes made to the programme under officer delegated authority
(3) Requests that remainder of unspent budget in 2017/18 be carried forward
(4) Requests authorisation to proceed with 2018/19 proposed planned maintenance works
(5) Requests authorisation to vire from the property reserve to fund shortfall for 2018/19
1 Implications for the Council’s Key Priorities, Service Plans and Sustainable Community Strategy
1.1Ensuring that assets are protected and enhanced supports the delivery of the Council’s key priorities
1.2The programme supports a number of specific key priorities including measures to enhance sustainability and combat the impact of climate change
1.3There is no specific key service priority for this programme Strategy and Resources Committee 17 April 2018 2 Background
2.1The 2017/18 budget for prioritised planned maintenance repairs was agreed at Strategy and Resources Committee on 4 April 2017 and was set at £210k. The £210k consisted of a base maintenance budget of £175k and £35k for regulatory and legislative works.
2.2A further £24k was agreed at April’s Committee to support the 2017/18 programme, £102k was carried forward from 2016/17 for works still in progress at last year-end and £2.7k was drawn down from reserves in- year.
2.3Total resources available for 2017/18 therefore amounted to £339k.
3 Current Position
3.1Annexe 1 sets out the forecast expenditure against each scheme at the end of March 2018.
3.2The changes carried out under delegated authority are set out within Annexe 1.
3.3The end of year forecast predicts an underspend of £27k.
3.4Members are asked to note the progress on schemes and the changes to the programme
4 Proposed schemes for 2018/19
4.1The proposed schemes are set out in Annexe 2 and authority is sought to approve these for 2018/19
4.2In the event that the monies are not spent before the end of the financial year 2018/19, it is proposed that the remainder of the unspent budget is carried over to the following year.
4.3The proposed schemes will cost a projected £280k, which exceeds the £210k base budget by £70k. Approval is sought to fund this deficit with the £27k projected 2017/18 underspend and £43k from the property reserve.
5 Financial and Manpower Implications
5.1The resources are available within the Projects team to accommodate the proposed works for 2018/19.
5.2Under S33 of the VAT Act 1994, the Council is permitted to recover VAT on expenditure related to exempt income, provided that the amount does not exceed 5% of total VAT recovered from HMRC in any one year. The most significant exempt income to the Council is generated by rents and lettings. Strategy and Resources Committee 17 April 2018 5.3 As reported to this Committee in November 2017, the Council breached this 5% limit in 2016/17. To mitigate the risk of having to repay over £176k to HMRC, Officers requested HMRC’s permission to use a seven- year average method of calculating the 5%. HMRC agreed to this which means that if EEBC can average below 5% across years 2012/13 – 2018/19, the £176k repayment will not fall due.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.