Following consideration, it was resolved: That the Committee: (1) Approved the 2019/20 planned maintenance programme at an estimated cost of £280,000. (2) Approved the carry forward of the underspend on 2018/19’s programme, for use as funding towards the proposed 2019/20 programme and outstanding Legionella remedial works. (3) Authorised officers to make changes within the programme up to but not exceeding £10,000.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
(1) To approve the 2019/20 planned maintenance programme at an estimated cost of £280,000.
(2) To approve the carry forward of the underspend on 2018/19’s programme, for use as funding towards the proposed 2019/20 programme and outstanding Legionella remedial works.
(3) To authorise officers to make changes within the programme up to but not exceeding £10,000. Strategy and Resources Committee 2 April 2019 1 Implications for the Council’s Key Priorities, Service Plans and Sustainable Community Strategy
1.1Ensuring assets are protected and enhanced supports the delivery of the councils key priorities, including managing our resources.
1.2The programme supports a number of specific key priorities including measures to enhance sustainability and combat the impact of climate change.
Background
2.1At Strategy and Resources Committee on 27th November 2018 the revised planned maintenance programme was updated and additional expenditure of £41,500 to be funded from the property maintenance reserve was approved.
2.2The approved 2018/19 maintenance programme is set out in Annex 2 and officers are progressing well with proposed works.
2.3Due to the tendering process and getting best value from suppliers some schemes have been delivered under budget, in particular the following;
2.4The Horton Country Park relay of water mains cost was £15,000 compared to a budget allocation of £26,000. This has been achieved by smarter working using a new system to lay pipework. The works have commenced on site and are due for completion by end of March 2019.
2.5Community and Wellbeing Centre external decorations order placed for £7k, works are awaiting good weather to commence with a saving of £3k.
2.6Walls and fences - fewer inspections have been carried out due to the extensive works programme resulting in an unspent budget saving of £18k.
2.7Bridges in Hogsmill have been replaced and repaired for £10k, with a saving of 5k.
2.8Legionella works, proposed in the action plan following water risk assessments, are currently being priced up by various contractors, therefore no spend is anticipated against a £20k budget until end March/April. When prices are received additional funds may be requested.
2.9Other minor schemes have produced savings through competitive pricing, bringing the total forecast underspend on the 2018/19 programme to £70k. Strategy and Resources Committee 2 April 2019 2.10 A further £30k budget – for Clocktower brick and stonework repairs – will remain unspent, as the scheme has been deferred with more extensive works required, beyond the existing budget. A new specification is being prepared for full costings to be tendered. A new budget will be requested as necessary within the Capital programme for next year.
2.11The Town Hall internal lighting management upgrade order has been raised, with works planned to commence in March.
2.12It is anticipated that 2018-19 programme will now be delivered at a total estimated cost of £222,000, delivering an under spend of circa £70,000 plus the £30,000 removed for the Clocktower scheme against the current approved budget of £321,500.
2.13The planned maintenance budget is set at £210,000 each year, with variations to the budget subject to Committee approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.