Following consideration, it was resolved: (1) to note the anticipated spend at the end of the current year 2019-20; (2) to approve the carry over funds from 2019/20 to complete works from the 2019-20 programme as set out in paragraph 5.7 of the Report; (3) to approve the 2020/21 planned maintenance programme at an estimated cost of £455,000 as set out in Annex 2 to the report; (4) subject to the Council’s financial and contract requirements, to delegate authority to the Head of Property and Regeneration to make changes within the 2020/21 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1At its meeting on 2nd April 2019, Strategy and Resources Committee agreed the planned maintenance programme in the sum of £280,000.
2.2The approved works are set out in Annex 1.
3 Budget Savings
3.1The procurement process to obtain best value from suppliers has resulted in some 2019/20 schemes being delivered under budget, some slightly over budget and some were removed from the programme due to a change in priorities.
3.2In accordance with previously agreed recommendations, officers are authorised to make changes to the programme up to but not exceeding £10,000.
3.3Heating pressure systems works were identified at various venues under the Pressure Vessel Regulations 2000 and a budget of £30,000 was allocated. The works were delivered under budget at a cost of £5,700. Bourne Hall was removed as a future Capital Bid will be prepared for consideration to replace all boiler and air handling plant.
3.4The provision of heater batteries to the kitchen at Ewell Court House had a budget allocation of £20,000, but was delivered for £4,000.
3.5Design proposals for replacing the boiler and air handling plant at Bourne Hall is anticipated to be delivered well within budget following receipt of tender prices ranging from a very favourable £2,640 to £16,315.
3.6The total saving from these schemes has been used to fund emergency works that have occurred during the year and to cover any over-budget tender returns from other schemes.
4 New emergency works
4.1The Auriol Park retaining wall to the bowling green was identified as high risk due to the possibility of collapse. Structural advice was obtained and the existing wall removed and rebuilt at a cost of £21,000. Strategy and Resources Committee 30 January 2020 4.2 Replacement windows (at high level) costing £8,000 were required to some parts of the Community & Wellbeing Centre. There was the potential for risk of injury if the works were not carried out.
4.3Urgent roof repair works were required to West Park Cottage, Horton Country Park, to prevent damp penetration at a cost of £2,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.