Following consideration, it was resolved that the Committee: (1) Agreed to note the progress and anticipated spend at the end of the current year 2020/21; (2) Agreed to transfer the £68,000 projected underspend on 2020/21’s programme back to the Planned Maintenance Reserve for use in 2021/22; (3) Agreed to approve the 2021/22 planned maintenance programme at an estimated cost of £315,000 as set out in Appendix 2; (4) Agreed to delegate authority to the Head of Property and Regeneration to make changes within the 2021/22 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000; subject to the Council’s financial and contract requirements.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1At its meeting on 30th January 2020, Strategy and Resources Committee agreed the planned maintenance programme in the sum of £455,000 to be funded from the Property Maintenance Reserve.
2.2The approved works are set out in Appendix 1.
3 Update on 2020-21 planned maintenance programme
3.1Following the Council’s procurement process to obtain best value from suppliers has resulted in some schemes being delivered under budget and others slightly over budget.
3.2In accordance with previously agreed recommendations, officers are authorised to make changes to the programme up to but not exceeding £20,000.
3.3A brief update on each project is provided below:
3.3.1 The Bourne Hall ladies toilet refurbishment was delayed due to Covid-19 lockdown measures. Works commenced in December 2020 with completion anticipated in January 2021. All works are within budget.
3.3.2 The Ashley Centre car park staircase redecorations and roof repairs commenced in December 2020 with completion expected in January 2021. Works will be within budget.
3.3.3 Longmead Depot security gates and access control works were completed in November 2020. Extra works included line markings, additional card readers, an additional post to incorporate an intercom and a vehicle protection bollard. The works cost £30,000 and exceeded the budget estimate by £10,000.
3.3.4 Longmead Depot toilets are on hold due to Covid-19 but works will be completed before the end of March and within budget. Strategy and Resources Committee 28 January 2021 3.3.5 Playhouse - Legionella Risk Assessments remedial works continue with replacement of pipework above ceilings from kitchen areas to dressing rooms at a cost of approximately £10,000. The budget set aside was £25,000 which included the cost for carrying out new Water Risk Assessments. The budget will be underspent as Water Risk Assessments are being carried out by Rydon Maintenance within the current cost of the M&E contract. The £15,000 saving is available to be returned to the Planned Maintenance Reserves for future essential maintenance.
3.3.6 Ewell Court House grotto wall has been repaired. The work required listed building consent and was undertaken by a specialist brick Restoration Company. The works were completed in September 2020 at a cost of £7,000 which is £3,000 under budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.