That the Board noted: · The project remains paused until there is a significant change in the funding prospects. · Ongoing funding applications and work to manage scheme risk around buried services will be concluded . · A decision may be required in 2023/24 whether to continue to pursue the construction phase of the approved scheme.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
Board/Committee: COMMUNITY AND ENVIRONMENT BOARD Date of meeting: 10TH JANUARY 2023 Title: CONSTRUCTION OF FLOOD DEFENCE STRUCTURES AT ALVERSTOKE Author: HEAD OF STREETSCENE Status: FOR NOTING
Purpose This report updates Members on the Alverstoke coastal defence scheme since the update in September 2022 and sets out the next stages for the project. Recommendation That the Board notes that:
The project remains paused until there is a significant change in the funding prospects. Ongoing funding applications and work to manage scheme risk around buried services will be concluded. A decision may be required in 2023/24 whether to continue to pursue the construction phase of the approved scheme. 1.0 Background
1.1The proposed scheme at Alverstoke will reduce flood risk to 130 properties in Alverstoke over the next 50 years. The scheme will provide flood defence to a 1 in 100-year event (1% Annual Exceedance Probability) up to 2069 through provision of a flood wall and road flood gate.
1.2The preferred works contractor was approved by the Community Board 10 February 2021. Construction of the scheme started in January 2022, with an estimated six-months duration.
1.3During construction several risks were realised, including high voltage cables which significantly impacted the safety of the construction, delayed the programme and increased costs. The site work also coincided with unprecedented challenges from cost inflation and supply of construction materials. A decision was made in April 2022 to pause construction works and to reinstate the site to ensure the mandated budget was not exceeded.
1.4A status update was given to the Community and Environment Board on 14 September 2022. This report provides a further progress update to the Board.
2.0Report
2.1Progress Update:
Over the past four months the following actions have been completed:
The site has been reinstated to pre-works condition with full public access. The current works contract has been closed out. Any future construction will require a new works tender process. The project budget has been reassessed, covering outstanding contractor payments and project overheads. Further details are contained in Section 2.3. Funding sources have been explored; however no further funding has yet been secured. There has been further engagement with Scottish & Southern Electricity Networks (SSEN) over their buried apparatus. An Exception Plan has been developed and is presented in Section 2.4.
2.2Stakeholder communications:
A brief update has been issued on the project webpage and responses provided to enquiries from the public. Stakeholders have been updated and future stakeholder communications will be developed and delivered through the Exception Plan. Information on the ongoing programme pause will be provided to the local community and public.
2.3Funding:
The scheme is primarily funded from Environment Agency Grant Aid totalling £932,238. Since 2018, £903,847 has been spent to complete the detailed design, licenses and consents, procurement and site works, with £28,390 of grant aid remaining.
By aborting construction work, the project has avoided exceeding its approved funding limit. This has protected the following funds which have been ring- fenced, including a Grant Aid contingency fund of up to £181,000 and £212,269 of underwriting by Gosport Borough Council.
The available funding remains insufficient to meet the expected outturn costs of the construction which have risen through inflation. Furthermore, there are insufficient funds to progress any new investigations to de-risk the project and close the funding gap. The remaining funds are however sufficient to enable ongoing discussions with potential funders and the risks around the high voltage cable to be concluded.
2.4Way Forward:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.