Resolved
That the Board noted that this report provided further project details as requested at the previous Community and Environment Board held on 10 January 2023.
Community & Environment Board noted this item on Wednesday 1 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Board noted that this report provided further project details as requested at the previous Community and Environment Board held on 10 January 2023.
Board/Committee: COMMUNITY AND ENVIRONMENT BOARD Date of meeting: WEDNESDAY 1st MARCH 2023 Title: CONSTRUCTION OF FLOOD DEFENCE STRUCTURES AT FORTON Author: HEAD OF STREETSCENE Status: FOR NOTING
Purpose This report updates Members on progress with the Forton coastal defence scheme since the update in January 2023 and sets out the next stages for project delivery. Recommendation That the Board notes that this report provides further project details as requested at the previous Community and Environment Board held on 10 January 2023. 1.0 Background
1.1A project status update was given to the Community and Environment Board on 10th January 2023. The Board requested a report be brought back to Board containing further information around project expenditure, funding and consents.
2.0Report
2.1Funding
Expenditure to date: The scheme is primarily funded from Environment Agency Grant Aid and Local Levy Funds. Table 1 summarises the amount claimed to date on the project (£664,644), and of that sum, £610,531 has been spent on the project and £53,614 budget remains.
Table 1. Expenditure to date
Since 2019, The total project spend of £610,531 has been spent over four financial years (Table 2). Table 2. Expenditure to date per financial year
This spend can be attributed to the project activities summarised in Figure 1.
The majority of the project expenditure has been utilised on ‘non-construction’ activities and which were required to develop the project from the Outline Business Case to the detailed design stage, gain the required licencing and consents, and then works procurement. This included payments to the design consultant to cover ground investigations and preparation of the design drawings and scope. Construction related activities represent 31% of the overall spend to date. HR, Admin & Other, 3% (£20,205)
Project Management , 27% (£165,097) Construction, Site works and Supervision, 31% (£190,361)
Procurement, 4% (£25,495)
Communications and Engagement, 3% (£20,452) Licensing and Consents & Detailed Design, Environmental Studies, Funding and Mitigation and Approvals and PCS, Enhancements, 10% 20% (£125,091) (£63,830)
Figure 1. Spend breakdown associated with Project activities.
A project timeline which provides further detail on activities and expenditure over the past 4 years is provided in Appendix 1. 2.2. Funding forecast and gap:
Since the previous Community and Environment Board update in January 2023, the project has been allocated £681,184 of funding from the Department for Education Fund. An FDGiA inflation claim is currently being prepared to cover all justifiable inflationary cost increases. The project has a potential estimated £1.4million of funding available (not spent) as shown in Table 3.
Table 3. Secured funding (not spent)
The estimated forecast outturn cost needed to complete the project, with and without risk has been summarised in Table 4, this estimate is pending further financial analysis. The revised funding profile indicates that a provisional sum of £604,734 of funding is required to close the funding gap and enable delivery of the scheme and construction to restart in 2024, following successful mitigation of the badger sett risk. Further funding options are being explored and a bid for additional RFCC Local Levy funding was made in January 2023 to close this gap.
Table 4. Funding required
3.0Way Forward:
The project continues with the phased approach to the exception plan as outlined within the 10th January Community and Environment Board update.
The estimated forecast outturn has assumed that construction works can resume in 2024.
Licences and Consents: A number of licensing and consents have already been obtained for the Forton FCERM Scheme. Due to the delay to the construction start date in 2021 (Covid-19) and the pause of construction works in 2022 (Badger sett & inflation), the status of current licences and consents can be seen in Table 5.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Construction of Flood Defence Structures at FortonReport | 198 KB | DownloadRead as text |
PDF |
Forton_CB_Appendix 1Appendix | 179 KB | Download |
Follow Community & Environment Board at Gosport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the meeting of the board held on 17 June 2026 and 15 July 2026That the minutes of the meetings held on 17 June 2026 and 15 July 2026 were signed as a true and correct record. | Decided | Open |
| 16 Sep 2026 | Project Integra Joint Municipal Waste management Strategy- A Resources and Waste Strategy for HampshireThat the Board approved: i) The revised project Integra Joint Municipal Waste Management Strategy 2026 to 2035 (A Res... | Approved | Open |
| 17 Jun 2026 | Election of ChairmanThat Councillor Ricketts is elected as Chairman for the municipal year 2026-2027 | Decided | Open |
| 17 Jun 2026 | Election of Vice ChairmanThat Councillor Bond was elected as Vice Chairman for the municipal year 2026-2027 | Decided | Open |
| 17 Jun 2026 | Minutes of the meeting of the board held on 25 February 2026That the minutes of the meeting held on 25 February were signed as a true and correct record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.