Construction of Flood Defence Structures at Forton

Noted Committee 1 paper

Community & Environment Board noted this item on Tuesday 10 January 2023. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

That the Board noted: · There remains insufficient funding to construct the scheme, and the location of a badger sett remains a significant risk to the project. · The available project funds will be utilised to progress applications to close the funding gap, while working to confirm the updated scheme costs and relocate the badger sett away from the works area.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Community & Environment Board

Background

1.1The proposed scheme will reduce flood risk to 211 properties in Forton over the next 50 years, to a 1 in 100-year event (1% Annual Exceedance Probability) up to 2069.

1.2The preferred contractor was approved by the Community Board on the 10th February 2021. Construction of the 240m long flood wall started in April 2022, with an estimated four-month duration.

1.3During construction several risks were realised, including a live badger sett in the works area preventing works progress. The site work also coincided with unprecedented challenges from cost inflation and supply of construction materials. A decision was made to pause construction works at the end of April 2022 and to reinstate the site to ensure the mandated budget was not exceeded.

1.4A status update was given to the Community and Environment Board on 14 September 2022, where the next steps were set out. This report provides a further progress update to the Board.

2.0Report

2.1Progress Update:

Over the past four months the following actions have been completed:  The site has been reinstated to pre-works condition with full access returned to St Vincent College.  The works contract has been closed out. Any future construction will require a new works tender process.  The project budget has been reassessed, covering outstanding contractor payments and project costs. Further details are contained in Section 2.3.  Funding sources have been explored; however no further funding has yet been fully secured.  An Exception Plan has been developed to take the scheme forward and is presented in Section 2.4.

2.2Stakeholder Communications:

 A brief update has been issued on the project webpage and responses provided to enquiries from the public.  Future stakeholder communications will be developed and delivered through the Exception Plan.  The Environment Agency and St Vincent College continue to be kept updated.  Information on the proposed programme will be provided to the local community and public.

2.3Funding:

The scheme is primarily funded from Environment Agency Grant Aid and Local Levy Funds (totalling £660,145). Since 2018, £600,599 has been spent to complete the detailed design, licenses and consents, procurement and site works, with £59,545 remaining.

By aborting construction work, the project has avoided exceeding its approved funding limit. This has protected the following funds which remain available and have been ring-fenced: a Grant Aid contingency fund of up to £197,000 and a £288,516 contribution of Other Government Departments Funding (OGD).

The available funding remains insufficient to meet the expected outturn costs of the construction which have risen through inflation. The funding gap will be fully quantified over the next 3 months.

A series of actions are in hand to close the funding gap, including discussions with the Environment Agency and a funding application is being assessed by the Department for Education. Further funding applications are planned covering inflation uplifts, local levy, and Other Government Departments (OGD).

2.4Way Forward:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Construction of Flood Defence Structures at FortonReport 230 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
MZ
Councillor Mrs Zoe HugginsCommittee Member, present
JW
Councillor Julie WesterbyChairman, present
MJ
Councillor Mrs June CullyCommittee Member, present
MJ
Councillor Murray JohnstonCommittee Member, present
MD
Councillor Miss Dawn KellyVice-Chair, apologies, sent representative
BM
Councillor Bob MaynardCommittee Member, present
MM
Councillor Mrs Margaret MorganCommittee Member, present
PC
Councillor Peter Chegwynex-Officio, present
MS
Councillor Ms Sue BallardCommittee Member, present as substitute

On this subject at Gosport

Search all
  1. Construction of Flood Defence Structures at FortonThis decision
  2. Construction of Flood Defence Structures at FortonNoted
  3. Construction of Flood Defence Structures at FortonApproved
  4. Construction of Flood Defence Structures at FortonNoted
  5. Construction of Flood Defence Structures at AlverstokeNoted
  6. Construction of Flood Defence Structures at AlverstokeNoted

More from Gosport Community & Environment Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the meeting of the board held on 17 June 2026 and 15 July 2026That the minutes of the meetings held on 17 June 2026 and 15 July 2026 were signed as a true and correct record. Decided Open
16 Sep 2026 Project Integra Joint Municipal Waste management Strategy- A Resources and Waste Strategy for HampshireThat the Board approved: i) The revised project Integra Joint Municipal Waste Management Strategy 2026 to 2035 (A Res... Approved Open
17 Jun 2026 Election of ChairmanThat Councillor Ricketts is elected as Chairman for the municipal year 2026-2027 Decided Open
17 Jun 2026 Election of Vice ChairmanThat Councillor Bond was elected as Vice Chairman for the municipal year 2026-2027 Decided Open
17 Jun 2026 Minutes of the meeting of the board held on 25 February 2026That the minutes of the meeting held on 25 February were signed as a true and correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies