Resolved
That the Board noted that this report provided further project details as requested at the previous Community and Environment Board held on 10 January 2023
Community & Environment Board noted this item on Wednesday 1 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Board noted that this report provided further project details as requested at the previous Community and Environment Board held on 10 January 2023
Board/Committee: COMMUNITY AND ENVIRONMENT BOARD Date of meeting: WEDNESDAY 1st MARCH 2023 Title: CONSTRUCTION OF FLOOD DEFENCE STRUCTURES AT ALVERSTOKE Author: HEAD OF STREETSCENE Status: FOR NOTING
Purpose This report updates Members on the Alverstoke coastal defence scheme since the update in January 2023 and sets out the next stages for the project. Recommendation That the Board notes that this report provides further project details as requested at the previous Community and Environment Board held on 10th January 2023. 1.0 Background
1.1A project status update was given to the Community and Environment Board on 10th January 2023. The Board requested a report be brought back to Board containing further information around project expenditure and funding.
2.0Report
2.1Funding:
Expenditure to date: The scheme is primarily funded from Environment Agency Grant Aid totalling £932,238. Table 1 summarises the amount claimed to date on the project (£932,238), and of that sum, £907,629 has been spent on the project and £24,609 budget remains.
Table 1.
Since 2018, £907,628 has been spent on the project over five financial years (Table 2).
Table 2. Figure 1 confirms the majority of the project expenditure has been utilised on ‘non- construction’ activities and which were required to develop the project from the Outline Business Case to the detailed design stage, gain the required licencing and consents, and then works procurement. This included payments to the design consultant to cover ground investigations and preparation of the design drawings and scope. Construction related activities represent 29% of the overall spend to date.
HR, Admin & Other, 4% (£40,078)
Project Management , Construction, Site 29% (£261,808) works and Supervision, 29% (£266,985)
Procurement, 5% (£44,153) Communications and Engagement, 6% (£52,101)
Detailed Design, Funding and Licensing and Consents & Approvals and PCS, Environmental Studies, 17% (£153,055) Mitigation and Enhancements, 10% (£89,449)
Figure 1. Spend breakdown associated with Project activities.
A project timeline which provides further detail on activities and expenditure over the past 5 years is provided in Appendix 1.
3.0Funding forecast and gap:
The project has a potential estimated £442,878 of remaining available project funding as shown in Table 3. Further funding options continue to be explored.
The available funding remains insufficient to meet the expected outturn costs of the construction, and which have risen through inflation.
Table 3. Secured funding (not spent) 4.0 Way forward
The project continues with the phased approach to the exception plan as outlined within the 10 January Community and Environment Board update.
Licences and Consents: Licenses and consents have already been obtained for the Alverstoke FCERM Scheme. Due to the delay to the construction start date in 2021 (Covid-19) and the pause of construction works in 2022 (HV cables & inflation), the status of current licences and consents can be seen in Table 5.
A GBC six-month extension to planning permissions that would have expired between 19 August 2020 and 31 December 2020 did not apply to the Alverstoke FCERM scheme as the approval was granted after those dates, and the planning permission does not expire until December 2023.
Table 5. Status update on Alverstoke FCERM scheme licences and consents Licence or Expiration Status: Cost to renew: Consent Date: Planning application 8 December In date, works must start If new permission on the existing 2023 before expiration date required, £262 (based design on previous application) Marine Licence December Expired £1,400 based on 2022 previous application FRAP Outdated Requires a new application, Estimated £1,595 – as the previous applicant’s based on previous name is out of date application Crown Estate Expired Extension required. Estimate £500 (including admin fees)
4.0Risk Assessment
4.1The project risks are as per the exception plan as outlined within the 10th January Community and Environment Board update.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Alverstoke_CB_Appendix 1Appendix | 205 KB | Download |
PDF |
Construction of Flood Defence Structures at AlverstokeReport | 181 KB | DownloadRead as text |
Follow Community & Environment Board at Gosport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the meeting of the board held on 17 June 2026 and 15 July 2026That the minutes of the meetings held on 17 June 2026 and 15 July 2026 were signed as a true and correct record. | Decided | Open |
| 16 Sep 2026 | Project Integra Joint Municipal Waste management Strategy- A Resources and Waste Strategy for HampshireThat the Board approved: i) The revised project Integra Joint Municipal Waste Management Strategy 2026 to 2035 (A Res... | Approved | Open |
| 17 Jun 2026 | Election of ChairmanThat Councillor Ricketts is elected as Chairman for the municipal year 2026-2027 | Decided | Open |
| 17 Jun 2026 | Election of Vice ChairmanThat Councillor Bond was elected as Vice Chairman for the municipal year 2026-2027 | Decided | Open |
| 17 Jun 2026 | Minutes of the meeting of the board held on 25 February 2026That the minutes of the meeting held on 25 February were signed as a true and correct record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.