That the Board approved that: · Authority is given to the Chief Executive: a) To undertake the procurement of the works and the evaluation of bids received, and b) In consultation with the section 151 officer, to award a contract for the works to the preferred bidder, subject to sufficient funding being in place. · The project team report back to Board with a project update in Autumn 2023 to confirm the expected start date of April 2024.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
1.1The proposed scheme will reduce tidal flood risk to 211 properties in Forton over the next 50 years, to a 1 in 100-year event (1% Annual Exceedance Probability) up to 2069. Work on site commenced in April 2022 but encountered a badger sett. With no viable way forward, works were stopped to avoid the forecast project budget being exceeded and to protect the remaining funding.
1.2The Community and Environment Board has previously received reports on 10 January and 1st March 2023 providing details on issues on site, project expenditure, funding and consents.
1.3This report provides further updates on project progress, including amounts spent since the previous report, additional funding secured, and the proposed way forward as requested at the previous Community and Environment Board.
2.0Report
2.1Progress Update:
Since March 2023, the project team has:
Secured an additional £592,635 from the Regional Flood and Coast Committee (RFCC) following a successful local levy bid. Further details are presented in Section 2.3. Submitted an inflation claim for funding from the Environment Agency towards construction costs. Held a design workshop and developed an outline design to mitigate the badger risk by re-designing around the Early Years Centre (EYC) building. St Vincent College has endorsed this approach. Updated the previous construction works contract documents.
2.2Stakeholder Communications:
St Vincent College has been updated with the project progress and understand the need for a new alignment around the EYC to avoid the badger sett on site. Future stakeholder communications will be developed and delivered following Community and Environment Board. Information on the proposed programme will then be provided to the local community and public.
2.3Funding:
Expenditure to date:
The project has spent £24,801 since January 2023. The spend has funded project critical activities including all funding applications, financial analysis, project reporting, stakeholder engagement, design and procurement activities and contract management.
The £24,801, is in addition to the historic spend as outlined in the previous report at the Community and Environment Board in March 2023 (£610,531). The total project spend (since 2019) is £635,332.
Funding forecast and gap:
The original scheme secured £852,800 of funding for delivery in 2022, as reported to Community and Environment Board in February 2021. While stopping works on site protected the remaining funds available to the project, these were insufficient to allow works to restart on site. Therefore, additional funding had to be secured to top this up.
Since previously reported on 1st March 2023, the scheme has been allocated an additional £592,635 by the RFCC through a successful Local levy bid, which was confirmed on 19th April 2023.
The total project funding now secured and available (excluding expenditure to date) is £1,969,352 including contingency funds. This funding is made up from:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.