Gosport Borough Council
Community & Environment Board, Wednesday 28 February 2024 at 6.00pm

Construction of Flood Defence Structures at Forton

Noted Committee 1 paper

Community & Environment Board noted this item on Wednesday 28 February 2024. Below is the council's own wording, with the papers it was decided on.

Item27

Resolved

That the Board noted: · The works procurement is completed, and a contractor has been appointed · The project is fully funded · Planning permission for the scheme has been obtained · The project is programmed and on target for an April 2024 start date on site, with planned completion in November 2024 · Public communications about the scheme works will be issued before construction.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Community & Environment Board

Background

1.1The proposed scheme will reduce tidal flood risk to 211 properties in Forton over the next 50 years, to a 1 in 100-year event (1% Annual Exceedance Probability) up to 2069.

1.2The Community and Environment Board was updated on 21 June 2023, covering the project budget, consents and procurement. Delegated authority was given to the Deputy Chief Executive and Section 151 Office to award a contract for the works to the preferred bidder, subject to sufficient funding being in place. This report provides further updates on project progress, funding and the expected start date.

2.0Report

2.1Progress Update:

Since June 2023:

 All design work has been completed including an alignment change to mitigate disturbance risks to a badger sett in the vicinity of the works.  The project is fully funded, following a successful inflation uplift claim to the Environment Agency.  Full planning permission for the scheme was granted on 15 November 2023.  Following a successful procurement stage, JT Mackley & Co Ltd, have been appointed as works contractor. Contract execution is being undertaken by GBC with support from Portsmouth City Council legal department.

2.2Stakeholder Communications:

 Continued engagement with, and endorsement from, St Vincent College with the project progress.  Wider public communications will commence in February 2024, including social media, webpage updates. Local letter drops are planned six- weeks in advance of construction. The project is carrying out engagement with local educational establishments as part of the conditions of the Department for Education grant award. This engagement aims to engage children and young people local to the Forton flood defence scheme.

2.3Funding:

Project budget:

Since previously reported on 21 June 2023, the scheme was awarded an additional £103,683 in July 2023 by the Environment Agency (EA), following a successful inflation uplift claim.

With this additional sum, the scheme is fully funded, with a project budget - comprising all secured funding, less expenditure to date of £1,907,221.93. This sum is the amount available to deliver the remainder of the scheme including construction, project management, supervision, and contingency.

2.4Way Forward:

Key activities and target dates:  Execute works contract. (February 2024).  Stakeholder engagement and public communications ahead of construction (February 2024)  Mobilisation (March 2024)  Works start on site (April 2024)  Works complete (November 2024)

3.0Risk assessment Key risks are described below:

3.1Programme  An extended contract execution period which impacts the planned April 2024 works start could increase project costs and duration.

3.2Finance  Costs exceeding project budget. As mitigation, detailed tracking and management of project costs and programme will be undertaken to monitor the project budget. A 30% ‘risk pot’ is available to cover contingency during the works.

4.0Conclusion

4.1The project has successfully secured full funding for project delivery and has secured planning permission for construction.

4.2A works contractor is appointed and following contract execution works will start on site in April 2024 and will be completed by November 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Construction of Flood Defence Structures at FortonReport 223 KB DownloadRead as text

At this meeting

Whole meeting
24Minutes of the meeting of the board held on 10 January 2024Decided
27Construction of Flood Defence Structures at FortonThis decision

Who was there

7 of 9 attended
MZ
Councillor Mrs Zoe HugginsCommittee Member, present
JW
Councillor Julie WesterbyChairman, present
MJ
Councillor Murray JohnstonCommittee Member, present
BM
Councillor Bob MaynardCommittee Member, present
MM
Councillor Mrs Margaret MorganCommittee Member, present
PC
Councillor Peter Chegwynex-Officio, in attendance
MP
Councillor Martin Pepperex-Officio, expected
SM
Councillor Stephen MarshallVice-Chair, present
SP
Councillor Stephen PhilpottCommittee Member, present

On this subject at Gosport

Search all
  1. Construction of Flood Defence Structures at FortonThis decision
  2. Construction of Flood Defence Structures at FortonApproved
  3. Construction of Flood Defence Structures at FortonNoted
  4. Construction of Flood Defence Structures at AlverstokeNoted
  5. Construction of Flood Defence Structures at AlverstokeNoted
  6. Construction of Flood Defence Structures at FortonNoted

More from Gosport Community & Environment Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the meeting of the board held on 17 June 2026 and 15 July 2026That the minutes of the meetings held on 17 June 2026 and 15 July 2026 were signed as a true and correct record. Decided Open
16 Sep 2026 Project Integra Joint Municipal Waste management Strategy- A Resources and Waste Strategy for HampshireThat the Board approved: i) The revised project Integra Joint Municipal Waste Management Strategy 2026 to 2035 (A Res... Approved Open
17 Jun 2026 Election of ChairmanThat Councillor Ricketts is elected as Chairman for the municipal year 2026-2027 Decided Open
17 Jun 2026 Election of Vice ChairmanThat Councillor Bond was elected as Vice Chairman for the municipal year 2026-2027 Decided Open
17 Jun 2026 Minutes of the meeting of the board held on 25 February 2026That the minutes of the meeting held on 25 February were signed as a true and correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies