Guildford Borough Council
Executive, Thursday 19 March 2026 at 6.00pm

Procurement Pipeline Report - over £200k (2025-2026)

Approved Executive 2 papers

AI summaryGuildford Borough Council Executive approved starting procurement for projects over £200k listed in the pipeline appendix, with delegated award authority to the Joint Strategic Director for Finance and Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement to begin for Appendix 1 projects; award delegated to officer
MoneyOver £200k thresholdTriggers Executive approval as potential Key Decision
What happens nextProceed to marketProcurement team and Service Area to tender the listed projects
Who it affectsSuppliers and service areasIncluding SMEs, VCSE sector and Waverley Borough Council

What was decided

The Executive approved the commencement of the procurement process for the projects listed in Appendix 1 to the report. Report P5, 1.2

The Executive delegated authority to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance, to award the contracts listed in Appendix 1 on selection of a successful contractor. Report P6, 1.3

The report does not commit the Council to running the listed procurements, to a specific sourcing route, or to collaborating with Waverley Borough Council; individual activities may be withdrawn, expedited or deferred. Report 6.6

Why

The Council's Contract Procedure Rules require the Executive to approve any procurement that could result in a Key Decision award, either because the estimated value is over £200k or it significantly impacts two or more wards. Report 1.1, 3.1, 6.2

Forward planning of procurement is said to support effective stakeholder management, compliance with legislation and the Council's own rules, ethical sourcing, climate and social value considerations, and securing best value across the contract life. Report 3.2, P10, P11, P12, P13, P14, P15

A consolidated pipeline report avoids submitting multiple individual approval requests, making the approval process more agile. Report 3.3

What happens next

If approved, the Procurement team and the relevant Service Area will proceed to market for the procurements in Appendix 1 and, on conclusion, will run the award process and obtain relevant approvals. Report 4.1, P18

Any public consultation needed for each procurement will be carried out at the appropriate time before tendering. Report 9.1, P36

If a procurement concludes in a Key Decision award that is not covered by this delegation, a separate Executive report will be brought for approval of the award. Report 3.4

The money

  • £200k Threshold above which a procurement may be a Key Decision needing Executive approval Report 1.1
  • £100m (inc VAT) Annual third party spend level that would trigger pipeline notice duties under the Procurement Act 2023 Report 6.5
  • £2m (inc VAT) Threshold above which individual pipeline notices of future procurements would need publishing every 18 months Report 6.5

Options considered

  • Chosen: Bring a consolidated procurement pipeline to the Executive at periodic intervals. Saves officer and Executive time and supports a more strategic, planned approach to procurement Report P40
  • Rejected: Bring each individual procurement item to the Executive separately. Would take more time and cost to write individual reports Report P41

Implications

  • Financial: The report states there are no financial implications; financial approval will be sought before any procurement commences. Report P43
  • Legal: The report records no direct legal implications, with project-specific advice to be provided by the Procurement and Legal teams. Report P44, P45
  • Equalities: The report records no equality and diversity implications, with duties to be considered by project teams for each procurement. Report P47, P48, P49, P50
  • Climate: The report records no climate change or sustainability implications, with ethical and climate factors to be considered as part of planning each procurement. Report 12.4, 12.5, P14
  • Risk: The new Contract Procedure Rules may need more Procurement team and service area resource, and without planned pipelines there is a heightened risk of non-compliant spend if contracts expire before re-procurement. Report 10.1, 10.2
  • Other: Opportunities to collaborate with Waverley Borough Council, and others, are to be considered by the relevant project team for each procurement. Report 6.3, 8.1, 8.2

Who and where

  • The Council's Procurement team and relevant service areas Report 4.1, 10.1
  • Suppliers, including small and medium enterprises and the voluntary, community and social enterprise (VCSE) sector Report 7.2
  • Waverley Borough Council, as a potential collaboration partner Report 6.3, 8.1
  • Two or more wards within the Borough, where a procurement significantly affects them Report 1.1

Timeline

  • June 2024: New Contract Procedure Rules introduced, changing who must approve procurements and awards Report 6.1, 6.2
  • 26 February 2026: Previous procurement pipeline presented to the Executive Report 1.2
  • 19 March 2026: Updated procurement pipeline report considered by the Executive Report 1.2

Plain English for the jargon

  • Contract Procedure Rules (CPRs): The Council's own rules governing how procurement and contract awards must be carried out.
  • Key Decision: A decision that, because of its value over £200k or its significant impact on two or more wards, must be taken by the Executive.
  • VCSE: Voluntary, Community and Social Enterprise sector, including local suppliers and charities.
  • SME: Small and medium-sized enterprises, which public sector procurement rules require councils not to exclude.
  • Procurement Act 2023: New UK legislation governing how public bodies run procurements, with added pipeline notice duties for high-spend councils.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX151

Resolved

Approve commencement of the procurement process for the project(s) listed in Appendix 1 to this report. 2. Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contract(s) as listed in Appendix 1. Reason(s): 1. The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. 2. Planning procurement activity ensures: · effective stakeholder management ? · effective procurement and sourcing ? · compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules ?? · there is consideration on how contract price is to be managed in contract and what contract price model will be used ? · our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk. ?? · how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. 3. This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 4. When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provide that the Executive must give permission to commence any procurement activity which could result in the award being a Key Decision as the estimated value is greater than £200k or it significantly impacts two or more wards within the Borough.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 26 February 2026. The pipeline set out in Appendix 1 to this report includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence.

1.3In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to:

(1) Approve commencement of the procurement process for the project(s) listed in Appendix 1 to this report.

(2) Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contract(s) as listed in Appendix 1.

3 Reason(s) for recommendation:

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. Procurement Pipeline Report – over £200k (2025-2026)

3.2Planning procurement activity ensures:

• effective stakeholder management

• effective procurement and sourcing

• compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

• there is consideration on how contract price is to be managed in contract and what contract price model will be used

• our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.

• how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract.

3.3This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity.

3.4When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_GBC Procurement Pipeline 260326Appendix 1 218 KB Download
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 127 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
JM
Councillor Julia McShaneChairperson, present
VK
Councillor Vanessa KingVice-Chairperson, present
PB
Councillor Phil BellamyCommittee Member, apologies
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present, as expected, virtual
FW
Councillor Fiona WhiteCommittee Member, present
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Procurement Pipeline Report - over £200k (2025-2026)This decision
  2. Procurement Pipeline Report - over £200k (2025-2026)Approved
  3. Procurement Pipeline Report - over £200k (2025-2026)Approved
  4. Procurement Pipeline Report - over £200k (2025-2026)Approved
  5. Procurement Pipeline Report - over £200k (2025-2026)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open