RESOLVED i. To appoint T&B (Contractors) Ltd in the amount of £1,444,238.15 for a contract period of 57 weeks. This will allow timely delivery of the project to enable accommodation of an additional for of entry by September 2016. ii. To issue a letter of intent not exceeding 10% of the contract sum as allowed under CSO 9.07.3 whilst formal works contracts are being prepared. Alternative Options Considered The proposed expansion of St Mary’s CE Primary School is expected to support additional cohorts from September 2016. A do nothing option would not support local demand for additional pupil places. The feasibility report considered 5 design options for the Rectory Gardens site, with emphasis on flexibility, programme, impact on the school and financial viability. Options 1, 2, 4 and 5 were discounted by stakeholders on the basis that the design did not offer the most beneficial outcomes to meet the project objectives and success criteria. Option 3 was considered the preferred option and approved for progression to design development. Reasons for decision To award a contract which will enable the timely mobilisation and construction of works to St Mary’s CE Primary School Rectory Gardens Site which aims to support the Council’s requirement for additional school places from September 2016.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
St Mary’s CE Primary Expansion Project – Rectory Gardens Title: Construction Contract Award
Report Authorised by: Jon Abbey, Director of Children’s Services
Michael Baldwin, Project Manager, Corporate Property and Major Lead Officer: Projects
Ward(s) affected: Hornsey Report for Key Decisions: Yes
1. Describe the issue under consideration 1.1 This Cabinet item is to request approval to award a contract for construction works to be undertaken on the St Mary’s CE Primary School building located on the Rectory Gardens site so it can accommodate an additional form of entry. 1.2 This contract is to be awarded on the basis of the most economically advantageous tender. 1.3 This paper seeks approval to award the contract to T&B (Contractors) Ltd for Construction works in the amount of £1,444,238.15 for a contract period of 57 weeks. 1.4 In addition, if Cabinet sees fit to approve the award of the contract, this authority requests approval to instruct Haringey Council’s Legal Services to issue a Letter of Intent permitting orders to be raised by T&B (Contractors) Ltd with their supply chain; up to and not exceeding 10% of the contract sum as allowed under CSO 9.07.3 whilst formal works contracts are being prepared.
2. Cabinet Member introduction (Cllr Ann Waters) 2.1 The principle of expanding St Marys CE Primary School (N8) was agreed by Cabinet on the 17th March 2015 in response to the increasing number of children requiring primary school places in this area. This tender process to conclude an award of contract has been undertaken in accordance with the Council’s contract standing orders Page 1 of 6 3. Recommendations 3.1 To appoint T&B (Contractors) Ltd in the amount of £1,444,238.15 for a contract period of 57 weeks. This will allow timely delivery of the project to enable accommodation of an additional for of entry by September 2016. 3.2 To issue a letter of intent not exceeding 10% of the contract sum as allowed under CSO 9.07.3 whilst formal works contracts are being prepared.
4. Alternative options considered 4.1 The proposed expansion of St Mary’s CE Primary School is expected to support additional cohorts from September 2016. A do nothing option would not support local demand for additional pupil places. 4.2 The feasibility report considered 5 design options for the Rectory Gardens site, with emphasis on flexibility, programme, impact on the school and financial viability. 4.3 Options 1, 2, 4 and 5 were discounted by stakeholders on the basis that the design did not offer the most beneficial outcomes to meet the project objectives and success criteria. 4.4 Option 3 was considered the preferred option and approved for progression to design development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.