St Mary's CE Primary Expansion - Church Lane Site

Approved Executive 2 papers

Cabinet approved this item on Tuesday 19 January 2016. Below is the council's own wording, with the papers it was decided on.

Item175

Resolved

RESOLVED 1. To appoint T&B (Contractors) Ltd in the amount of £686,663.60 for a contract period of 27 weeks. To allow timely delivery of the project to enable accommodation of an additional form of entry by September 2016. 2. To approve the issuance of a Letter of Intent not exceeding 10% of the contract sum. Reasons for decision To award a contract which will enable the timely mobilisation and construction works to St Marys CE Primary School Church Lane Site which aims to support the Council’s requirement for additional school places from September 2016. Alternative options considered The proposed expansion of St Mary’s CE Primary School is expected to support additional cohorts from September 2016. A do nothing option would not support local demand for additional pupil places. Four contractors were invited to tender and therefore considered to undertake the required construction works at St Marys CE Primary School Church Lane site. The tenderers proposals were evaluated using a 60% quality and 40% price weighting and on this basis the recommended contractor is deemed to be the most economically advantageous tender representing the best value option to deliver the required works.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Reasons for decision

4.1To award a contract which will enable the timely mobilisation and construction works to St Marys CE Primary School Church Lane Site which aims to support the Council’s requirement for additional school places from September 2016.

Alternative options considered

5.1The proposed expansion of St Mary’s CE Primary School is expected to support additional cohorts from September 2016. A do nothing option would not support local demand for additional pupil places.

5.2Four contractors were invited to tender and therefore considered to undertake the required construction works at St Marys CE Primary School Church Lane site. The tenderers proposals were evaluated using a 60% quality and 40% price weighting and on this basis the recommended contractor is deemed to be the most economically advantageous tender representing the best value option to deliver the required works.

6. Background information

6.1The principle of expanding St Mary’s CE Primary was agreed by Cabinet Committee in March 2015 based on previous school roll projections that showed a borough wide deficit of reception places from 2015.

6.2St Mary’s C. E. Primary School is a church school located in Hornsey within the London Borough of Haringey that takes children aged 3-11. It was formerly arranged as separate infant and junior schools and is now joined to create a primary school split between separate sites at Church Lane and Rectory Gardens, approximately 10 minutes walk apart.

6.3A feasibility study was commissioned in November 2013 to explore the potential of expanding St Mary’s CE Primary from 2 FE to 3 FE and undertake works to the existing nursery to consider inclusion of 12 2 year old spaces.

6.4In developing the feasibility preferred options in more detail, it was recognised that, as the sites are approximately half a mile apart, any construction would require two contractor compounds and it was more effective to undertake the construction works at each site at different times within the overall expansion programme.

Page 2 of 6 6.5 Construction works are currently underway at the Rectory Gardens site to provide the required infrastructure to accommodate the additional form of entry.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EqIA: St Marys C of E Primary School Expansion ProjectAppendix A 492 KB Download
PDF
St Mary's CE Primary Expansion: Church Lane SiteMinutes 210 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 15 attended
AK
Angela KawaCouncil Staff, expected
CK
Councillor Claire KoberChair, present
JA
Councillor Jason ArthurCommittee Member, present
AD
Councillor Ali DemirciCommittee Member, apologies
JG
Councillor Joe GoldbergCommittee Member, apologies
SM
Councillor Stuart McNamaraCommittee Member, apologies
PM
Councillor Peter MortonCommittee Member, apologies
AS
Councillor Alan StricklandCommittee Member, present
BV
Councillor Bernice VanierCommittee Member, present
AW
Councillor Ann WatersCommittee Member, present
LG
Lyn GarnerOfficer, expected
BR
Bernie RyanOfficer, expected

All 15 on the meeting page

On this subject at Haringey

Search all
  1. St Mary's CE Primary Expansion - Church Lane SiteThis decision
  2. Earlsmead Primary School - Condition Works - Permission to initiate tender action for a Construction Works ContractDecided
  3. Mulberry Primary School - Condition Works - Permission to initiate tender action for a Construction Works ContractDecided
  4. Crowland Primary School - Condition Works - Permission to initiate tender action for a Construction Works ContractDecided
  5. Coleridge Primary School - Condition Works - Permission to initiate tender action for a Construction Works ContractDecided
  6. Stamford Hill Primary School added to the New Homes ProgrammeDecided

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies