Resolved
RESOLVED -That the report be noted.
Moorlands Partnership Board noted this item on Tuesday 14 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED -That the report be noted.
1.1That the report is noted.
2.1This report deals with progress to date on those projects awaiting commencement, on site or completed since the last meeting of the Moorlands Partnership Board.
2.2This report is for information but it does offer Members an opportunity to comment on progress.
3 Background and Detail
Projects Update
2011/2012 OFFERS
Bourne Fountain, Cheadle Awaiting commencement.
2013/2014 OFFERS
Mile Marker, Froghall to Uttoxeter Works completed and grant paid.
Cheddleton Station Crossing Gates Awaiting commencement. 2014/2015 OFFERS
14 Market Place, Leek Commencement due May 2017.
36 Stockwell Street, Leek Repairs to sash windows complete but decoration still to be undertaken.
Kissing gate, Whitemore Awaiting commencement.
Kissing gate and railings, Old Forge Dyeworks Awaiting commencement.
2015/16 OFFERS
18 Deansgate, Leek Works completed but additional works required before grant payment.
Cheddleton Flint Mill Works started but ongoing.
No3 Clerk Bank, Leek Works complete and grant paid.
Gazebo, Whitehough, Ipstones Awaiting commencement.
Barn, Whitehough, Ipstones Awaiting commencement.
High St House, Leek Awaiting commencement.
No1 Clerk Bank, Leek Works on site but issues about quality of work.
2016/17 OFFERS
War Memorial Oakamoor Works complete and grant paid.
67 Tape Street, Cheadle Awaiting commencement.
7C Stanley Street Application withdrawn. 17 Edward Street, Leek Awaiting commencement.
Derby Street Bollards, Leek Awaiting commencement.
4 Implications
4.1Community Safety: Nil.
4.2Workforce: Nil.
4.3Equality and Diversity: This report has been compiled in accordance with the Council’s Diversity and Equality Policies.
4.4Financial This report deals with those projects for which Considerations funding has already been allocated.
4.5Legal: Nil.
4.6Sustainability: The repair and reuse of historic buildings is an important sustainability objective.
Dai Larner Executive Director
Background Papers Location Contact Project Applications Regeneration Service Jo Brooks File 6366 Regeneration Officer 0345 129 7777 ext 3654
Decision:
Reason:
Interests Declared:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Current Status of Projects.Report | 58 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Summary of ProjectsThat the report be received. | Decided | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.