Resolved
That the report and presentation be noted.
Moorlands Partnership Board noted this item on Wednesday 14 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report and presentation be noted.
1.1That the report is noted.
2.1This report deals with progress to date on those projects awaiting commencement, on site or, completed since the last meeting of the Moorlands Partnership Board.
2.2This report is for information but it does offer Members an opportunity to comment on progress.
3 Background and Detail
Projects Update
2015/16 OFFERS
Gazebo, Whitehough, Ipstones The applicant has installed the new leaded windows so just has the door to complete.
2016/17 OFFERS
67 Tape Street, Cheadle Works delayed and will not commence until Oct 2019. At a previous meeting the board agreed to honour an extension to the grant offer to meet this date. 9 – 11 High Street Dilhorne Works have now been completed satisfactorily and a final payment of £1,000 has been made.
Endon and Stanley Interpretation panels Payment made and panels in situ.
The Trough – Biddulph Awaiting commencement.
2017/2018 OFFERS
Leekbrook to Leek (Cornhill) heritage rail link Planning permission has now been granted for the reinstatement of the rail link. Legal professionals have been appointed to provide advice to the Council regarding the Heads of Terms and these are being discussed between the Council and the Churnet Valley Railway (CVR). The full cost for construction of the line is circa £810,000. There is an 18-month construction period that would only commence once funding is confirmed. CVR will be responsible for raising the funding to cover the construction costs. CVR have been invited to make a full application for funding to EAFRD.
Leekbrook Station Works have been completed to restore Leekbrook station waiting room. The building is an exact replica and received its official opening in October.
Cheddleton Station The architect has now completed a set of plans and proposals for the repair and refurbishment of the building and is awaiting estimates. There will be a delay to the works due to the required bat survey, which cannot take place until May 2019.
Funerary Monuments At the last meeting. Members were advised that the following monuments were priorities for repair:
5 Chest Tombs at Church of All Saints, Dilhorne; 4 Chest tombs at Church of All Saints, Dilhorne; Prince Memorial Church of St Leonard, Ipstones; Yates Memorial, Endon.
A contractor has been appointed to undertake the repair of the above 4 monuments at a cost of £7,456. The total budget for this project is £10,000. To date, the cost of the accredited architect is £3,965. This leaves a remaining budget of £6,035 for funerary repairs. Officers have secured a further £1,500 from the SMDC monuments and cemeteries budget. This will enable the above 4 to be repaired as one contract. A grant enquiry to the Staffordshire Historic Churches Trust has been unproductive. Officers have approached the Parish Councils for funding but this has not proved successful. As such, the Council has sufficient funds to repair the above priorities but cannot fund any further works.
The architects need to obtain faculty approval for the repair works and this has proved to be protracted. It is hoped that the repairs works will commence shortly.
Biddulph Town Council Projects Railings A57 – Deposit paid to Ironage Designs. Gillow Heath Station - A small working group has been formed, and this has turned into a four phase project. Stage one will be moving the fence on the District Council land and installation of benches. Stage two would be restoring the edge of the platform. Stage three is the installation of signage and interpretation boards. Stage four is to repair the nearby footbridge, constructed using the old rails, which is one of only two in the country, the other being at Rudyard Lake. Well at Tower Hill Road - Being kept tidy by the lengsthman. Hopefully complete before the end of the year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Current Status of Projects.Report | 66 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Summary of ProjectsThat the report be received. | Decided | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.