Resolved
That the report be noted.
Moorlands Partnership Board noted this item on Wednesday 13 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
1.1That the report is noted.
2.1This report deals with progress to date on those projects, awaiting commencement, on site or, completed since the last meeting of the Moorlands Partnership Board.
2.2This report is for information but it does offer Members an opportunity to comment on progress.
3 Background and Detail
Projects Update
2015/16 OFFERS
Gazebo, Whitehough, Ipstones Doors to be installed during the spring/summer.
2016/17 OFFERS
67 Tape Street, Cheadle Works delayed and will not commence until Oct 2019. At a previous meeting the board agreed to honour an extension to the grant offer to meet this date.
The Trough – Biddulph Awaiting commencement
1 2017/2018 OFFERS
Leekbrook to Leek (Cornhill) heritage rail link
Moorlands Partnership board allocated £22,000 towards bringing forward the heritage railway to Leek. To date, £28,626 has been spent on project development including planning permission, legal advice & fees associated with the cost of land transfer (the balance of funds coming from the regeneration revenue budget). The planning application has been approved, an expression of interest to co-fund the construction has been invited to full application (EAFRD – European Agricultural Fund for Rural Development). The signing of the Lease agreements is expected to take place by end of February 2019 (following approval by SMDC cabinet in December 2018). The full cost for construction of the line is circa £810,000. There is an 18-month construction period that would only commence once funding is confirmed.
There is an option to physically start constructing 200 meters of track in April 2019. This would run from Leekbrook Station northwards. Churnett Valley Railway can fund £21,000 and are seeking funding of £19,000 from the MPB to complete these works. This grant request is subject to a separate funding application report.
Cheddleton Station Tenders have now been returned for the completion of the works to repair Cheddleton Station. However works can not start on site until a bat survey has been completed in May 2019.
Funerary Monuments Faculty approval has now been gained for the repair of the following monuments. Works will commence shortly and will be supervised by a conservation architect.
5 Chest Tombs at Church of All Saints, Dilhorne 4 Chest tombs at Church of All Saints, Dilhorne Prince Memorial Church of St Leonard, Ipstones Yates Memorial, Endon
There are sufficient funds to repair the above monuments and Endon Parish Council have also agreed to make a £250 contribution towards the repair of the Yates Memorial in Endon.
However there are a further 7 listed memorials that are on the buildings at risk register. The cost to repair the additional monuments would be £9,076. Officers have confirmed that a further £1,000 can be allocated towards the additional work from the closed cemeteries budget for 2019/2020. 2 Biddulph Town Council Projects Railings A57 – Deposit paid to Ironage Designs. Gillow Heath Station - A small working group has been formed, and this has turned into a four phase project. Stage one will be moving the fence on the District Council land and installation of benches. Stage two would be restoring the edge of the platform. Stage three is the installation of signage and interpretation boards. Stage four is to repair the nearby footbridge, constructed using the old rails, which is one of only two in the country, the other being at Rudyard Lake. Well at Tower Hill Road - Being kept tidy by the lengsthman. Hopefully complete before the end of the year.
Biddulph Grange Works to the leat are complete and paid and interpretation panels (3) will be installed shortly.
Cattle Market Cottage, Leek The property has now been sold and the grant withdrawn.
Foxlowe, Leek
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Current Status of Projects.Report | 72 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Summary of ProjectsThat the report be received. | Decided | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.