(Councillors Gledhill, Hart and Riley had declared interests and did not vote on the item relating to Cheddleton Station.) 1) That the update report be NOTED . 2) That the £4,000 grant offered against the repair of Cheddleton Station building was reallocated against the reinstatement of diamond cut blue bricks to allow the original brick pattern to be restored be APPROVED . 3) The Board APPROVED the ‘in principle’ allocation of £20,000 against the Victoria Buildings to be reallocated against other grant applications.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
1.2That the £4,000 grant offered against the repair of Cheddleton Station building is reallocated against the reinstatement of diamond cut blue bricks to allow the original brick pattern to be restored.
1.3That the ‘in principle’ allocation of £20,000 against the Victoria Buildings is reallocated against other grant applications.
Summary
2.1This report deals with progress to date on those projects, awaiting commencement, on site or, completed since the last meeting of the Moorlands Partnership Board.
2.2This report is for information, but does offer Members an opportunity to comment on progress.
3 Project Updates
2015/16 OFFERS Gazebo, Whitehough, Ipstones Still waiting for doors to be installed and then the scheme will be complete.
2016/17 OFFERS The Trough – Biddulph Awaiting commencement. Listed building consent has been approved and works will be undertaken in better weather. The Town Council are waiting to hear if SCC Highways will install bollards to protect the trough form being hit. 2017/2018 OFFERS Cheddleton Station Anticipated costs to repair the station building are well in excess of the original budget and works to repair the whole of the station building will not commence in the near future. Rather than loose the £4,000 grant from the MPB, the applicant has requested that the grant is reallocated against the repair of Cheddleton Platform. This consists of reinstating diamond cut and plain blue platform bricks to restore the original pattern. The cost of the works totals £6,480.
Funerary Monuments The continued repair of the funerary monuments project has been supplemented by a further £5,000 grant from the MPB and an additional £5,000 grant from the Staffordshire Historic Churches Trust (SHCT). This allows the repair of all the remaining listed and at risk funerary monuments to be completed. Works will commence shortly.
Biddulph Town Council Projects
Railings A527 – Railings installed and grant paid.
Gillow Heath Station - A small working group has been formed, and this has turned into a four phase project:
Stage 1: Will be moving the fence on the District Council land and installation of 2 new benches – SMDC Assetts are being chased about the removal of the fence before benches can be installed.
Stage 2: Will be restoring the edge of the platform – the North Staffordshire Railway Company has been working to source edging stones. There is positive news that these have now been sourced.
Stage 3: Is the installation of signage and interpretation boards – No update.
Stage 4: Is to repair the nearby footbridge.
2018/2019 Grant Offers Foxlowe, Leek Works to repair the roof are complete but the final payment of grant is not yet made. The applicant is confident that works to Phase 2 – Window and render repairs can proceed when the weather improves.
1 High Street, Cheadle Works are still on site but have halted due to the submission of planning permission for conversion to holiday accommodation, which is yet to be determined. Leekbrook Interpretation Panels Historic photographs and text are in the process of being sourced.
2019/2020 Grant Offers Victoria Buildings, Leek This financial year, the MPB set aside £20,000 for the repair of the building which is in 4 separate ownerships. The cost to repair the building is around £52,459 but this figure does not include preliminaries, contingencies, fees or VAT. The likely final figure could be around £90,000. Officers have contacted all the owners requesting a grant application. Members are asked to note the following update:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.