Resolved
RESOLVED – That the Council’s current risk position be NOTED , together with the mitigation plans which were summarised in Appendices A (Strategic) and B (Operational).
Audit & Accounts Committee noted this item on Friday 9 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Council’s current risk position be NOTED , together with the mitigation plans which were summarised in Appendices A (Strategic) and B (Operational).
2.1That the committee note the Council’s current risk position and the mitigation plans summarised within Appendix A (strategic risks) and Appendix B (operational risks).
3.1The Council’s Strategic, Operational and Project Risk Registers are reviewed by the Audit and Accounts Committee on an exception basis. This report is based upon the Council’s position as at December 2017.
3.2The latest analysis of the Strategic Risk Register reveals that the Council has identified and assessed 12 strategic risks plus two opportunity risks. Of these 12 risks 42% are rated as 'high' and therefore above the Council’s risk tolerance threshold. The five ‘high’ rated risks are listed in full at Appendix A.
3.3The Operational Risk Registers reveal that the Council has identified and assessed 31 operational risks in total, of which 16% are rated as ‘high’ and therefore above the Council’s risk tolerance thresholds. The five risks falling within the ‘high’ category are listed in full at Appendix B.
3.4The new Project Risk Registers (five to date) have risk profiles that are all within the Council’s tolerance thresholds, with no ‘high’ rated risks:
0% Critical 0% High 18% Medium – 3 risk 82% Low – 14 risks
4. Evaluation of Options
4.1There are no options to consider
5. How this report links to Corporate Priorities
5.1Risk Management impacts on all service areas and therefore links to each of the Council’s Corporate Plan aims.
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998) None
6.2Workforce None
6.3Equality and Diversity/Equality Impact Assessment This report has been prepared in accordance with the Council's Diversity and Equality Policies
6.4Financial Considerations Effective Risk Management contributes to financial objectives
6.5Legal None
6.6Sustainability None
6.7Internal and External Consultation None
6.8Risk Assessment The Council’s Risk Registers are a critical element in the Council’s Risk Management Framework. ANDREW P STOKES Executive Director (Transformation) & Chief Finance Officer
Background Papers Location Contact details
Risk Registers – December 2017 Moorlands House Information Business Partner [email protected] Tel Ext 4057 7. Background and Introduction
7.1The Council ensures that it undertakes a deliberate and systematic identification of the key risks that might prevent, degrade, delay or enhance the achievement of its objectives and priorities. The Council's Risk Management Strategy sets out the process for undertaking this on an ongoing basis.
7.2In addition to the identification of risks, managers also have to quantify them in terms of likelihood and potential impact. The risks are then recorded in the Council's Risk Registers. These have three aspects – strategic, operational and project risks.
7.3Under the Risk Management Strategy, the Council’s ‘risk tolerance’ threshold is set along the border between ‘medium’ and ‘high’ rated residual risks. The Strategy stipulates that mitigating actions should be identified for all risks that exceed this threshold.
7.4The Council’s Strategic, Operational and Project Risk Registers are reviewed on a quarterly basis and reported into the Corporate Risk Management Group and the Audit and Accounts Committee on an exception basis. The appendices provide details of all risks that have been rated as ‘high’ or above, and therefore beyond the Council’s risk tolerance threshold.
8. Strategic Risks
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Update (overview of strategic, operational and project risks).Report | 214 KB | DownloadRead as text |
PDF |
SMDC: Risk Management Update App A (09-02-18)Appendix | 119 KB | Download |
PDF |
SMDC: Risk Management Update App B (09-02-18)Appendix | 18 KB | Download |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.