Resolved
RESOLVED – That the Council’s current risk position be NOTED .
Audit & Accounts Committee noted this item on Friday 26 October 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Council’s current risk position be NOTED .
2.1That the committee notes the Council’s current risk position and the mitigation plans summarised within Appendix A (strategic risks) and Appendix B (operational risks).
3.1The Council’s Strategic, Operational and Project Risk Registers are reviewed by the Audit and Accounts Committee on an exception basis. This report is based upon the Council’s position as at June 2018.
3.2The latest analysis of the Strategic Risk Register reveals that the Council has identified and assessed 12 strategic risks, of which 42% are rated as 'high' and therefore above the Council’s risk tolerance threshold. The five ‘high’ rated risks are listed in full at Appendix A.
3.3The Operational Risk Registers reveal that the Council has identified and assessed 32 operational risks in total, of which 13% are rated as ‘high’ and therefore above the Council’s risk tolerance thresholds. The four risks falling within the ‘high’ category are listed in full at Appendix B.
3.4The project risk registers now cover six projects with the new addition of AES. The risk profile is bulleted below:
0% Critical 0% High 13% Medium – 3 risks 87% Low – 20 risks
4. How this report links to Corporate Priorities
4.1Risk Management impacts on all service areas and therefore links to each of the Council’s Corporate Plan aims.
5.1There are no options to consider.
ANDREW P STOKES Executive Director (Transformation) & Chief Finance Officer
Background Papers Location Contact details
Risk Registers – June 2018 Moorlands House Information Business Partner [email protected] Tel Ext 4057 6. Detail
6.1The Council ensures that it undertakes a deliberate and systematic identification of the key risks that might prevent, degrade, delay or enhance the achievement of its objectives and priorities. The Council's Risk Management Strategy sets out the process for undertaking this on an ongoing basis.
6.2In addition to the identification of risks, managers also have to quantify them in terms of likelihood and potential impact. The risks are then recorded in the Council's Risk Registers. These have three aspects – strategic, operational and project risks.
6.3Under the Risk Management Strategy, the Council’s ‘risk tolerance’ threshold is set along the border between ‘medium’ and ‘high’ rated residual risks. The Strategy stipulates that mitigating actions should be identified for all risks that exceed this threshold.
6.4The Council’s Strategic, Operational and Project Risk Registers are reviewed on a quarterly basis and reported into the Corporate Risk Management Group and the Audit and Accounts Committee on an exception basis. The appendices provide details of all risks that have been rated as ‘high’ or above, and therefore beyond the Council’s risk tolerance threshold.
7. Strategic Risks
7.1The June 2018 analysis of the Strategic Risk Register reveals that the Council has identified and assessed 12 Strategic Risks, of which 42% are rated as 'high' and therefore above the Council’s risk tolerance threshold. There are also two opportunity risks within the register – New Homes Bonus and Business Rates Retention - from which the Council is aiming to maximise the financial opportunities they present for the area.
7.2The Council’s risk profile is displayed below and shows no change from the position reported previously.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management UpdateAppendix A | 58 KB | Download |
PDF |
Risk Management UpdateAppendix B | 53 KB | Download |
PDF |
Risk Management UpdateReport | 118 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.