Resolved
RESOLVED – That the ... view the full minutes text for item 59.
Audit & Accounts Committee decided this item on Friday 3 December 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the ... view the full minutes text for item 59.
2.1That the committee notes the Council’s current risk position and the mitigation / fruition plans summarised within Appendix A (strategic risks), Appendix B (operational risks), Appendix C (project risks) and Appendix D (opportunity risks).
3.1The Council’s Strategic, Operational and Project Risk Registers are reviewed by the Audit and Accounts Committee on an exception basis. This report is based upon the Council’s position as at September 2021.
3.2The latest analysis of the Strategic Risk Register reveals that the Council has identified and assessed 16 strategic risks, of which 50% are rated as 'high' and therefore above the Council’s risk tolerance threshold. The strategic risk profile has changed since last reported, with the addition of one new risk. The eight ‘high’ rated risks are listed in full at Appendix A. 3.3 The Operational Risk Registers reveal that the Council has identified and assessed 42 operational risks in total, of which nine are rated as ‘high’ and therefore above the Council’s risk tolerance thresholds. The details of all the significant changes can be found at paragraph 9. The risks falling within the ‘high’ category are listed in full at Appendix B.
3.4The project risk registers now cover 13 projects, with additions and completions adjusting this figure accordingly. The project risk profile is bulleted below:
0% Critical 4% High – 3 risks 73% Medium – 49 risks 22% Low – 15 risks
4. Evaluation of Options
4.1There are no options to consider
5. How this report links to Corporate Priorities
5.1Risk Management impacts on all service areas and therefore links to each of the Council’s Corporate Plan aims.
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998) None
6.2Workforce None
6.3Equality and Diversity/Equality Impact Assessment This report has been prepared in accordance with the Council's Diversity and Equality Policies
6.4Financial Considerations Effective Risk Management contributes to financial objectives
6.5Legal None
6.6Sustainability None
6.7Internal and External Consultation None 6.8 Risk Assessment The Council’s Risk Registers are a critical element in the Council’s Risk Management Framework.
ANDREW P STOKES Chief Executive
Background Papers Location Contact details
Risk Registers – Sept 2021 Moorlands House Information Business Partner [email protected] Tel Ext 4057 7. Background and Introduction
7.1The Council ensures that it undertakes a deliberate and systematic identification of the key risks that might prevent, degrade, delay or enhance the achievement of its objectives and priorities. The Council's Risk Management Strategy sets out the process for undertaking this on an ongoing basis.
7.2In addition to the identification of risks, managers also have to quantify them in terms of likelihood and potential impact. The risks are then recorded in the Council's Risk Registers. These have three aspects – strategic, operational and project risks.
7.3Under the Risk Management Strategy, the Council’s ‘risk tolerance’ threshold is set along the border between ‘medium’ and ‘high’ rated residual risks. The Strategy stipulates that mitigating actions should be identified for all risks that exceed this threshold.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
for Risk Management UpdateAppendix A | 262 KB | Download |
PDF |
for Risk Management UpdateAppendix B | 264 KB | Download |
PDF |
for Risk Management UpdateAppendix C | 217 KB | Download |
PDF |
for Risk Management UpdateAppendix D | 264 KB | Download |
PDF |
Risk Management UpdateReport | 629 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.