Resolved
That the revised as detailed at Appendix 1 of the report be approved.
Audit & Accounts Committee approved this item on Friday 15 September 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the revised as detailed at Appendix 1 of the report be approved.
2.1That members approve the revised Risk Management Strategy as detailed at Appendix 1.
3.1The Alliance Risk Management Strategy is reviewed every two years in order to ensure the Council’s approach reflects changing circumstances.
3.2The 2023 strategy review has been informed by a number of considerations, including:
An external deep dive review of 5 project risk registers by our Insurance partner, Zurich Municipal Findings of internal audit and other reviews Financial challenges facing the Council over the course of its Medium Term Financial Plan, our response to world events and how this might affect our tolerance to financial risk Consultation with Heads of Service and the corporate Risk Management Group
1 4. How this report links to Corporate Priorities
4.1Risk Management is embedded across all service areas and therefore links to each of the Council’s Corporate Plan aims.
5.1The committee can approve the 2023 strategy or suggest amendments.
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998) None
6.2Workforce Employee wellbeing has been included within the strategic risk register and continues to be monitored (after being identified as a new risk as part of the Horizon scan exercise in 2021)
6.3Equality and Diversity/Equality Impact Assessment This report has been prepared in accordance with the Council's Diversity and Equality Policies
6.4Financial Considerations Effective Risk Management contributes to the Council’s financial objectives
6.5Legal None
6.6Sustainability Compliance with environmental regulatory frameworks is included as a risk within the council’s strategic risk register
6.7Internal and External Consultation Heads of Service have been consulted on the current risk tolerance thresholds through the Risk Management Group
6.8Risk Assessment Establishing the Council’s risk tolerance is central to delivering a successful Risk Management Strategy.
ANDREW P STOKES Chief Executive
Background Papers Location Contact details Medium Term Financial Plan. Available on request Julie Nankivell Global Risks Report 2023 – OD & Transformation, World Economic Forum. Ext 5579 Zurich Risk Review – 2023.
2 7. Background
7.1The Council’s Joint Risk Management Strategy was first adopted in December 2010. In line with the commitment given in the Strategy to undertake regular reviews, the Strategy is now in its ninth iteration.
8. 2023 Review
8.1The 2023 strategy review has been informed by the areas bulleted below, which are explored in more detail in the following paragraphs.
An external deep dive review of 5 project risk registers from our Insurance partner, Zurich Municipal Findings of internal audit and other reviews relating to risk management Financial challenges facing the Council over the course of its Medium Term Financial Plan, our response to world events and how this might affect our tolerance to financial risk
8.2External Review – During 2023, the Alliance commissioned Zurich to review project risk management across the organisation. The aim of this work has been an overall assessment of the risk awareness and identification within these project. The review concluded that ‘Senior Managers and Members are actively building the risk culture and are seeking to learn and develop their approach towards risk identification and management’.
8.3The review will not only help develop the risk management within the projects but also help provide a guide moving forward.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 588 KB | Download |
PDF |
Risk Management StrategyReport | 323 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.