Cabinet, Tuesday 17 January 2012 at 3.00pm

Gateway 4 Procurement Post Project Completion Review: Waste Collection and Disposal Contracts

Noted Executive 1 paper

Cabinet noted this item on Tuesday 17 January 2012. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

The Cabinet noted the progress made to date with the collection and disposal contracts. 8/2012 The Cabinet agreed that the waste collection contract with Veolia be extended by 2 years to enable the authority to realise the cost savings as detailed in the exempt appendix to the report. Reasons: The decisions are provided on the basis of value for money, a realisation of annual cost savings and that Veolia have a track record of delivering high quality services for the residents of Medway with very high satisfaction levels recorded.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission from the Cabinet to review the progress of the Waste Collection and Disposal Contracts currently delivered through Veolia Environmental Services and to approve acceptance of the collection contract extension from 7 years to 9 years to achieve efficiencies as laid out in the exempt appendix.

This is based upon the procurement process which was undertaken during 2007-2010 and which led to an award of contract by Cabinet on 18 March 2010 for service commencement on 4 October 2010.

The commencement and delivery of this procurement requirement was approved by Cabinet at Procurement Gateway 1 on 20 July 2007 and subsequent report on 5 August 2008 and approval for contract award was provided by the Cabinet at Procurement Gateway 3 on 18 March 2010.

Approved Procurement Gateway 1 and 3 Reports relating to this Gateway 4 report are available upon request.

This Procurement Gateway 4 report has been approved for submission to the Cabinet after review and discussion with Regeneration, Community and Culture Directorate Management Team meeting on 24 November 2011 and Procurement Board on 30 November 2011.

1. Budget and Policy Framework

1.1Post Project Appraisal / Contract Management

1.1.1 This procurement post project appraisal and its subsequent review is within the Council’s policy and budget framework and ties in with all the identified Core Values, Strategic Priorities, Strategic Council Obligations and Departmental/Directorate service plans as highlighted within the Procurement Gateway 1 Report.

Background

2.1Contract Details

This contract is a services contract.

2.1.1 Supplier Details

This Gateway 4 Report relates to the Waste Collection and Disposal Contracts currently delivered through Veolia Environmental Services.

2.1.2 Contract Description

This contract covers: - Waste Collection and Street Cleansing services (residual waste collection, recycling collection from kerbside and bring sites, materials recycling facility provision and end markets for all recycling materials, food and garden waste collection and street cleansing). It commenced on 1 October 2010 and is for 7 years with an option to extend, at any time, for a further 2 years. - Disposal of residual waste via a combination of landfill and energy form Waste, ensuring the Council meets as a minimum, its landfill diversion targets as set down by Government. This contract follows the Council’s core values to ensure we have services that put our customers at the heart of everything we do at the same time as giving value for money and fits with the strategic priority of a clean and green environment. Such services need to support the Council’s Waste Strategy that, in turn, provides the basis for targets in performance and community plans. The primary objectives are to:  Ensure compliance with statutory duties.  Meet statutory performance targets.  Ensure continuity of a front line service.  Provide services within agreed budgets.  Meet requirements to achieve efficiency gains.  Provide environmentally sustainable services

2.2Permissions Required

2.2.1 This report seeks permission to provide Cabinet with a post project appraisal and continue this termed contract for remainder of the contract duration of 7 years (from October 2010 – September 2017) with the inclusion of further Gateway 5 reporting requirements 2.2.2 This report further seeks permission from Cabinet to agree the uptake of the 2-year extension making the collection contract 9 years (from October 2010 – September 2019) with the inclusion of further Gateway 5 reporting requirements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 4 Procurement Post Project Completion Review: Waste Collection and Disposal ContractsReport 412 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
RC
Rose CollinsonOfficer, in attendance
RC
Robin CooperOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Gateway 4 Procurement Post Project Completion Review: Waste Collection and Disposal ContractsThis decision
  2. Gateway 1: Procurement of Housing Related Support ServicesAgreed
  3. Gateway 1 Procurement Commencement: Repairs and Maintenance for Temporary Accommodation Owned, One Medway Lettings, One Medway – Inspiring Change LA Hostels, Housing Revenue Account (HRA) Requirements, Medway Development Company (MDC) and the Sanctuary SchemeAgreed
  4. Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayAgreed
  5. Gateway 1 Procurement Commencement: Innovation Park Medway NorthAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies