Medway Council
Cabinet, Tuesday 17 January 2012 at 3.00pm

Gateway 4 Procurement Post Project Completion Review: Organic Waste (Garden and Kitchen) Processing

Noted Executive 1 paper

Cabinet noted this item on Tuesday 17 January 2012. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

The Cabinet noted the progress made to date with the garden/food waste processing contract. 9/2012 The Cabinet agreed to continue with the current contract, negating the need for further Gateway 4 or Gateway 5 reporting requirements, unless a change in contract term was required. Reasons: The decisions are on the basis that this contract is providing value for money, and that Countrystyle are delivering high quality services for the residents of Medway while greatly assisting to achieve our statutory Landfill Allowance Trading Scheme (LATS) targets.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission from Cabinet to review the progress of the garden and food waste processing contract currently delivered through Countrystyle.

This is based upon the procurement process that was undertaken during 2007 -2009 and which led to an award of contract by Cabinet on 22 September 2009 for service commencement on 4 October 2010.

The commencement and delivery of this procurement requirement was approved by Cabinet at Procurement Gateway 1 on 20 February 2007 and subsequent approval for contract award was provided by Cabinet at Procurement Gateway 3 on 22 September 2009.

Approved Procurement Gateway 1 and 3 Reports relating to this Gateway 4 report are available upon request.

This Procurement Gateway 4 report has been approved for submission to Cabinet after review and discussion Regeneration, Community and Culture Directorate Management Team meeting on 24 November 2011 and Strategic Procurement Board on 30 November 2011.

1. Budget and Policy Framework

1.1Post Project Appraisal / Contract Management

1.1.1 This procurement post project appraisal and its subsequent review is within the Council’s policy and budget framework and ties in with all the identified Core Values, Strategic Priorities, Strategic Council Obligations and Departmental/Directorate service plans as highlighted within the Procurement Gateway 1 Report.

Background

2.1Contract Details

This contract is a services contract.

2.1.1 Supplier Details

This Gateway 4 Report relates to the Organic Waste (Garden and Kitchen) Processing contract currently delivered by Countrystyle.

2.1.2 Contract Description

This contract is for the processing for collected garden and food waste (i.e. materials collected and delivered to their site at Ridham Docks, Sittingbourne, under the waste collection contract) with the aim of diverting biodegradable waste from landfill and producing a compost style product suitable for use on local agricultural land. This contract follows the Council’s core values to ensure we give value for money and fits with the strategic priority of a clean and green environment. Such services need to support the Council’s Waste Strategy that in turn provides the basis for targets in performance and community plans. The primary objectives are to:  Ensure compliance with statutory duties.  Meet statutory performance targets.  Ensure continuity of a front line service.  Provide services within agreed budgets.  Meet requirements to achieve efficiency gains.  Provide environmentally sustainable services

2.2Permissions Required

This report seeks to provide Cabinet with a post project appraisal and continue this termed contract for remainder of the contract duration of 15 years (2010- 2025) without any further Gateway 4 or 5 reporting requirements.

This request is on the basis that this contract has fulfilled requirements in accordance with the service specification and associated contract terms and conditions (see section 4.1.1 Procurement Project Outputs / Outcomes) in the first year and because no major issues have been identified which cause concern for further continued contract management reporting to Cabinet.

It is acknowledged that if this option is granted and in the event of any major issues arising for the remainder of the contract term, a Gateway 5 report will be submitted with immediate effect for review by Cabinet or if so required and instructed for review by Cabinet during the remainder of the contract term.

Options

In arriving at the preferred option as identified within Section 4.1 ‘Preferred Option’, the following options have been considered with their respective advantages and disadvantages.

3.1Conclude Current Contract and Provide Action Plan

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 4 Procurement Post Project Completion Review: Organic Waste (Garden and Kitchen) ProcessingReport 249 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
RC
Rose CollinsonOfficer, in attendance
RC
Robin CooperOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Gateway 4 Procurement Post Project Completion Review: Organic Waste (Garden and Kitchen) ProcessingThis decision
  2. Gateway 1: Procurement of Housing Related Support ServicesAgreed
  3. Gateway 1 Procurement Commencement: Repairs and Maintenance for Temporary Accommodation Owned, One Medway Lettings, One Medway – Inspiring Change LA Hostels, Housing Revenue Account (HRA) Requirements, Medway Development Company (MDC) and the Sanctuary SchemeAgreed
  4. Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayAgreed
  5. Gateway 1 Procurement Commencement: Innovation Park Medway NorthAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies