169/2013 The Cabinet agreed to proceed with the option to develop additional housing on Housing Revenue Account (HRA) sites, as set out in paragraph 4.1 of the report and the option to develop additional housing on one General Fund site at Beatty Avenue, Gillingham, as set out in paragraph 4.2 of the report . 170/2013 The Cabinet agreed to delegate authority to the Assistant Director of Legal and Corporate services in consultation with the Portfolio Holder for Finance and Deputy Leader to appropriate the land at Beatty Avenue from the General Fund to the Housing Revenue Account (HRA) . 171/2013 The Cabinet agreed to delegate authority to the Director of Regeneration Community and Culture in consultation with the Portfolio Holder for Housing and Community Services to add further sites to the HRA site programme as they become available, as set out in paragraph 4.1.7 of the report . Reasons: This proposed development programme would both improve and add to the HRA’s existing housing stock, which will benefit existing tenants and Medway residents that qualify for affordable housing .
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1It has been agreed to increase Medway’s existing housing stock by using the available headroom to finance a house-building programme.
2.2Proposed work streams for inclusion within the HRA Development Programme have been identified as follows: 2.3 Develop additional housing on HRA owned sites: This would add to Medway Council’s housing stock enabling more affordable housing to be made available to those on Medway’s housing list. The opportunity cost of developing the HRA land will need to be factored in when considering whether the project offers value for money.
2.4Develop housing on surplus General Fund Land: This would also add to Medway Council’s housing stock; however the appropriation cost of the land would need to be factored in when considering whether the project offers value for money.
2.5The acquisition of development sites and or land and build package arrangements with contractors/developers: This could represent poorer value for money because the land would need to be acquired. However it is likely that these opportunities could be brought forward within a short time frame.
2.6Remodel homes for independent living: Some of Medway’s independent living schemes (formerly sheltered) are outdated and in need of improvement. Options could include either remodelling or demolition and a new building created in its place. This would benefit residents and improve the service to customers.
2.7Remodelling of all or part of an existing Council estate: This is a long-term option where the Council could promote a sense of place through the introduction of new tenures, good design and visual identity. It would have to demonstrate substantial additional amenity value to residents and increased asset value to the stock.
2.8From the five work streams identified above and considered by Full Council on 17 October 2013, this report requests approval to proceed with the first two work streams: The development of some HRA garage sites Land at Beatty Avenue, which is unused General Fund Land.
Options
3.1Develop additional housing on HRA owned sites At the meeting of Council on the 17 October 2013, Members were advised of the HRA sites currently under consideration. These are garage sites that are generally underused for car parking and are, in many instances, in a poor condition. All garage sites within the HRA have been considered for development and those suitable selected for further consideration.
3.2Develop housing on surplus General Fund Land At the meeting of Council on the 17 October 2013, Members were advised that the site at Beatty Avenue (which is part of the former Gillingham Community College site) has been identified as potentially suitable for affordable homes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.