The Cabinet noted the spending forecasts summarised at Table 1 in the report . The Cabinet noted the new approvals and virements outlined at paragraphs 4.2.3 and 4.3.1 in the report and authorised under Chief Officer delegations . 173/2013 The Cabinet recommended to Council the addition to the capital programme outlined at paragraph 4.2.2 in the report. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1The approved capital programme for 2013/14 and future years is £81.6m, being £41.6m in respect of brought forward schemes and £40m in respect of new approvals.
2.2This report consolidates the capital monitoring undertaken by each directorate and this is summarised in the appendices. 3. Progress
3.1Table 1 below summarises the current overall expenditure and the forecast position against the capital programme, representing a summary of the detailed information at Appendix 1. Appendices 2 to 5 show the position by directorate.
Table 1: Summary – capital spend and forecasts
Forecast spend
Forecast spend in later years Programme
March 2013 Approved
Spend to
Forecast Variance 2013-14 Directorate
£’000 £’000 £’000 £’000 £’000 Business Support 34,023 28,528 2,659 2,836 0 Department Children and 160,749 129,002 24,677 7,130 61 Adult Services Regeneration, Community and 96,615 52,914 26,154 17,547 0 Culture Member Priorities 1,332 707 330 284 (11) TOTAL 292,719 221,151 53,821 27,797 50
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
Scheme progressing on time and within budget Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget. Table 2 summarises the projects progress. Full detail is shown in the appendices:
Table 2: Project Progress Summary
Progress Monitoring Total Schemes BSD 7 3 0 10 Children & Adults 34 19 0 53 RCC 44 6 0 50 Member Priorities 16 3 0 19 Total 101 31 0 132
4. Specific Scheme Monitoring Issues and Completions 77% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support (Appendix 2)
4.1.1 There are no new additions since Q1.
4.1.2 The directorate forecast reflects the planned phasing of expenditure and forecasts a roll forward of £2.9m into future years. There are no areas of concern to report.
4.2Children and Adults (Appendix 3)
4.2.1 The Children and Adult Services directorate is currently working to a 2013/14 capital programme of £31.7 million.
4.2.2 Cabinet is requested to recommend to Council a £59,085 addition to the capital programme for 2013-14. This a revenue contribution to capital, funded from a New Burdens Grant, to fund pressures against the Integrated Care System project. This does not appear in table 1 at present.
4.2.3 Members may also be aware that the local authority was successful in bidding for Targeted Basic Needs funding, to deliver three priority schemes – the new Chatham Primary Academy, the relocation and expansion of Abbey Court (Rainham) and the expansion of Danecourt. Officers recently received confirmation of the final allocation, which totals £9.7 million and will allow the Council to address capacity issues both in terms of the requirement for primary school places and additional SEN places. This is ringfenced funding, which the Section 151 Officer is authorised to add to the capital programme under his delegated powers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.