Gateway 4 Procurement Post Project Completion Review: Elaine Primary School, Oaklands Primary School, Walderslade Primary School and Sir Joseph Williamson's Mathematical School
NotedExecutive1 paper
Cabinet noted this item on Tuesday 29 October 2013. Below is the council's own wording, with the papers it was decided on.
The Cabinet noted that the contracts were one-off contracts with no additional termed requirements, which were now complete and would therefore no longer be required (as set out as the preferred option within paragraph 4.1 of the report) . Reasons: The contracts were one off procurements, which have now finished .
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report provides Cabinet with a review of the progress of the Elaine Primary School, Oaklands Primary School, Walderslade Primary School and Sir Joseph Williamson (SJW) Mathematical School works contracts awarded to the suppliers highlighted within 2.1.2 of this report.
This is based upon the procurement processes for building and associated works which were undertaken between April 2009 and September 2011, and which led to the award of the contracts in November 2011 for Elaine Primary School, June 2011 for Oaklands Primary School, July 2009 for Walderslade School & March 2011 for SJW Mathematical School.
Cabinet at Procurement Gateway 1 approved the commencement and delivery of these procurement requirements on 2 August 2011 for Elaine Primary School, 8 March for Oaklands Primary School, 2009 for Walderslade Primary and 30 November 2010 for SJW Mathematical School. Subsequent approval for contract award was provided at Cabinet/Procurement Board at Gateway 3 on 29 November 2011 for Elaine Primary School, 8 June 2011 for Oaklands Primary School, 23 June 2009 for Walderslade School and 8 March 2011 for SJW Mathematical School.
All approved Procurement Gateway 1 and 3 Reports (apart from Walderslade Gateway 1 as it was run externally) relating to this Gateway 4 report are available upon request.
This Procurement Gateway 4 report has been approved for submission to Cabinet after review and discussion at Procurement Board on 15 October 2013. 1. Budget and Policy Framework
1.1Post Project Appraisal / Contract Management
1.1.1 This procurement post project appraisal and its subsequent review is within the Council’s policy and budget framework and ties in with all the identified Core Values, Strategic Priorities, Strategic Council Obligations and Departmental/Directorate service plans as highlighted within the Procurement Gateway 1 Report.
1.2Statutory Requirements
1.2.1 Elaine Primary -The Council has a statutory duty to provide sufficient school places, and enabled the school to take the pupils expected at the school.
1.2.2 Oaklands Primary - The procurement was a key project in Medway’s Primary Strategy for Change Programme, which attracted £11million of Government funding to support the Council’s strategic objective. The project was consistent with the Council’s School Organisation principals.
Within the primary phase Medway’s School Organisation Plan principles are: • to review the future of schools with low standards; • all Infant and Junior schools should be amalgamated over time; • to review the future of schools that are at risk of becoming unviable; • to enable popular and successful schools to expand.
1.2.3 Walderslade Primary & SJW Mathematical School projects - In support of Medway’s policy of replacement of temporary accommodation with permanent buildings and supports our planning principles.
Background
2.1Contract Details
2.1.1 These contracts were a Works/Construction contract
2.1.2 Supplier Details
This Gateway 4 Report relates to the: Elaine Primary School contract awarded to B W May Ltd. Oaklands Primary School contract awarded to Coombs Ltd. Walderslade Primary School contract awarded to Mansells Construction Services Ltd SJW Mathematical School contract awarded to Coombs Ltd and Birkby Construction Ltd 2.1.3 Contract Description The School and Councils objectives and service delivery were met. The works were:
Elaine Primary School:
To provide an additional classroom to accommodate the forecast increase in roll in 2011/12 Provide a safer parking provision.
Oaklands Primary School:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gateway 4 Procurement Post Project Completion Review: Elaine Primary School, Oaklands Primary School, Walderslade Primary School and Sir Joseph Williamson's Mathematical SchoolReport
16Gateway 4 Procurement Post Project Completion Review: Elaine Primary School, Oaklands Primary School, Walderslade Primary School and Sir Joseph Williamson's Mathematical SchoolThis decision
Gateway 4 Procurement Post Project Completion Review: Elaine Primary School, Oaklands Primary School, Walderslade Primary School and Sir Joseph Williamson's Mathematical SchoolThis decision
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.