182/2013 The Cabinet approved this Gateway 1 high risk report for progression to Gateway 2 of the procurement process for the further competition/mini tender within the Government Procurement Service Framework RM875 Modular Building Systems as set out in paragraph 4.1 of the report (preferred option) . Reasons: This will provide: Greater choice and flexibility; A quicker route to market; Procurement with confidence through a fully EU compliant offering. Reduced procurement costs and resources. Full compliance with building regulations including “part L/Section six” conservation of fuel and power. Up to sixty years design life with minimum maintenance costs. Covers both the hire of the modular building and the appropriate enabling or connection works.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to commence the procurement of Temporary Accommodation Hire for 2 years (including enabling works) to allow Saxon Way Primary School, Gillingham, to expand to a two form of entry (2FE) listed as Option 3a on the outline business case as approved at Cabinet on 6 August 2013 (decision number: 136/2013). The Saxon Way Primary School expansion to 2FE project may consist of 3 stages:
Temporary Accommodation Hire for 2 years (including enabling works) to be completed by September 2014 The preferred approach will be to initially install temporary accommodation to enable the first phase of expansion to take place.
The following two phases will only progress once Medway Council is sure that the expected number of students actually materializes. If the student numbers do not increase the Council will not proceed with Phases 1 and 2.
Phase 1:PPA, SEN & SENCO - due to be completed by September 2016 Phase 1 will provide a purpose built staffroom, Planning Preparation and Assessment (PPA) room, a Special Educational Needs (SEN) group room, speech and language and Special Educational Needs Coordinators (SENCO) office. The learning resource centre with ICT provision will be created. This will enable the existing staff room and SEN and ICT rooms to be reinstated as classroom spaces.
Phase 2:Single Storey Extension - due to be completed by September 2017 Phase 2 will provide a single storey extension with four additional classrooms, required from September 2017 onwards. This Gateway 1 report for Temporary Accommodation Hire for 2 years (including enabling works) has been approved for submission to Cabinet after review and discussion at Children’s and Adult’s Directorate Management Team meeting on 1 October 2013 and Procurement Board on 15 October 2013.
The Children and Adults Directorate Management Team has recommended that this procurement project be approved as a Category B High Risk procurement project at Procurement Gateway 1 by Cabinet. This is because although this procurement project is a Goods Category B Low Risk procurement with a total contract value below £250,000.00, there are political implications and/or service sensitivities that Cabinet should be aware of.
These political implications and/or service sensitivities are:
Ofsted placed the Saxon Way school into Special Measures in May 2012,a factor which is inconsistent with the policy of good schools expanding. However, an interim head teacher and an Interim Executive Board have been appointed to drive standards forward and a recent monitoring inspection by Ofsted in December 2012, highlighted that the school is making reasonable progress.
Colleagues from School Improvement are of the view that in this case Saxon Way should not be dismissed from expansion considerations as improvement in standards is evident, and expansion could help the school’s progress and viability.
Saxon Way converted to academy status on 1 September 2013 under the sponsorship of the Griffin’s School’s Trust, when the first additional places were be required. Academy status, in itself, does not need to affect the expansion; the local authority are the commissioner of places and as this is a basic needs expansion from a 1FE to a 2FE, the funding responsibility falls to the Local Education Authority. The Council does however need the cooperation of the sponsor in any expansion project. The sponsor has confirmed that it will be supportive of an expansion at the school.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.