172/2013 The Cabinet noted the forecast position following the second round of quarterly revenue monitoring for 2013/2014 and instructed Directors to come forward with further proposals for management action to reduce the potential deficit . Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council. Where a budget overspend is forecast, Cabinet supported by the corporate management team must identify measures to remove any excess expenditure .
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report details the revenue budget forecasts as at the end of Quarter 2 (April to September 2013) and highlights the major financial risks remaining in respect of the 2013/2014 General Fund revenue budget.
1. Budget and Policy Framework
1.1It is the responsibility of Cabinet to ensure that income and expenditure remains within the budget approved by Council.
1.2The Cabinet is asked to accept this report as urgent to enable Cabinet to receive and consider the latest budget information at the earliest opportunity.
Background
2.1At its meeting on 21 February 2013, the Council set a budget requirement of £348.511 million for 2013/2014, whilst Council Tax was increased by 1.99%, just below the cap imposed by Central Government. Subsequent increases to DSG have increased the budget requirement to £352.028 million.
2.2This is the second quarter’s monitoring report, summarising reports that have been considered by directorate management teams, based on returns submitted by individual budget managers. In preparing their returns, budget managers have been asked to take account of last years outturn, actual income and expenditure for the year to date and, most importantly, their knowledge of commitments and service requirements anticipated for the remainder of the financial year.
2.3Table 1 below contains a summary of the forecast position with further detail at divisional level, prior to management action, included at Appendix 1. 3. Summary Revenue Budget Position 2013/2014
3.1It can be seen from Table 1 that, including the management action reported by RCC and BSD, the forecast outturn for 2013/2014 is estimated at £4.4 million. Management action plans are being formulated and it is anticipated that this figure will come down as the year progresses.
Children and Adult Services: - DSG and School Specific 138,229) 620) 0) 620) 620 Spend - General Fund Services 118,272) 4,017) (727) 3,290) 3,600 Regeneration, Community 58,999) 1,064) (580) 484) 549 and Culture Business Support 9,661) 111) (195) (84) 207 Department Public Health 12,925) 0) 0) 0) 0 Interest & Financing 14,892) 0) 0) 0) 0 Levies 879) 8) 0) 8) 8 Better for Less (596) 671) 0) 671) 212 Medway Norse Joint (263) 0) 0) 0) 0 Venture Co. Use of Reserves (970) 0) 0) 0) 0
Funded by: Dedicated Schools Grant (138,228) (620) 0) (620) (620) Revenue Support Grant (63,311) 0) 0) 0) 0) Business rate share (42,119) 0) 0) 0) 0) Council Tax (87,565) 0) 0) 0) 0) Public Health Grant (13,170) 0) 0) 0) 0) Specific Grants (7,635) 0) 0) 0) 0) Total Available Funding (352,028) (620) 0) (620) (620)
Net Forecast Variance 0) 5,871) (1,502) 4,369) 4,576 4. Children and Adult Services
4.1The directorate is currently forecasting a £3.3 million overspend against its general fund budgets, the principal reasons for which are as follows:
The predicted overspend within the Children’s Care Division, has increased to £2.3 million, principally because of the need to place a young person in secure accommodation for a short period of time; The SEN transport budget continues to predict a £1.2 million overspend.
4.2Management action has been identified to reduce the predicted overspend and this is outlined below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.