Resolved

171/2014 The Cabinet approved the procurement of a contractor via the Kent Business Portal to carry out the additional works at New Horizons Academy in Chatham . Reasons: The proposed procurement process will encourage the greatest level of competition from the market and offer opportunities to local SMEs.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

CABINET 30 SEPTEMBER 2014 GATEWAY 1 PROCUREMENT COMMENCEMENT: SEN PROVISION AT NEW HORIZONS ACADEMY, CHATHAM Portfolio Holder: Councillor Mike O’Brien, Children’s Services (Lead Member)

Report from: Barbara Peacock, Director of Children and Adults Services

Authors: Paul Clarke, Strategic Planning Analyst Janet Elliott, Category Lead SUMMARY

This report seeks permission to commence the procurement of a works contractor to carry out Phase 2 of refurbishment works at the New Horizons Children’s Academy, Chatham to deliver accommodation for therapy and counseling services for up to 20 pupils per day. This Gateway 1 report has been approved for submission to the Cabinet after review and discussion at Children and Adults Directorate Management Team Meeting on 3 September 2014 and Procurement Board on 10 September 2014.

The Children and Adults Directorate Management Team has recommended that this project be approved as a Category B, high-risk procurement.

1. BACKGROUND INFORMATION

1.1Budget and Policy Framework

1.1.1 The project supports the Council’s School Organisation Plan 2011 – 2016, approved by Cabinet on 1 November 2011(decision number 143/2011) and the Special Educational Needs – An Inclusive Policy and Strategy for Medway 2009 – 2014. Delivery of this provision will also reduce the number of children placed in out of area independent provision.

1.1.2 Funding for the new academy has been provided by the government’s Targeted Basic Need Programme which was granted to the Council as a result of a successful bidding process.

1.1.3 The cost of the project to provide the buildings for the mainstream school did not require the entire amount of the bid funding that was awarded. Conditions of the funding mean that the money must be spent on the New Horizons project, and must be spent by September 2015, otherwise the remaining funding could be clawed back by the Education Funding Agency (EFA).

1.1.4 The availability of this funding affords an assured opportunity to provide the therapy provision at Hew Horizons, whereas, in the future no funding may be available to provide this facility.

1.1.5 At the Children and Adults Directorate Management Team Meeting on 23 June 2014 it was agreed that the remainder of the funding from this bid should be utilised for SEN provision at New Horizons Children’s Academy

1.2Service Background Information

1.2.1 The New Horizons Children’s Academy opened in September 2014 on the site of the former Chatham South school and will, over time, provide primary education for 630 mainstream children plus a nursery group.

1.2.2 There was always an in-principle agreement between the Thinking Schools Trust and the Local Authority that the academy would accommodate SEN provision for pupils in some form, but it was agreed with the Trust that this would not be from the outset, enabling the academy to establish itself before taking on the additional provision.

1.2.3 The form that the additional provision will take was not formally agreed when the design of the academy was agreed although the Trust initially indicated that a nurture group would be their preference.

1.2.4 The building highlighted for the additional provision at New Horizons is the science block on the former Chatham South site. This building did not form part of the project to create mainstream primary provision. The mainstream works are now complete and have been handed over to the Academy Trust.

1.2.5 It is proposed to use the science block for offices and consulting rooms for the Therapy Team to be relocated from its current base in the Elms building at Silverbank, which will create additional space enabling additional pupils to be admitted into Silverbank Pupil Referral Unit, which will reduce the numbers of pupils having to be placed in more expensive out of area and independent provision.

1.2.6 The therapy team will require 5 therapy rooms, 3 offices, staff room and facilities, 2 waiting areas and client WC’s as well as access to ICT and telephones.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1 Procurement Commencement: SEN Provision at New Horizons Academy, ChathamReport 37 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 16 attended
RC
Councillor Rodney Chambers, OBE (Con)Committee Member, apologies
AJ
Councillor Alan Jarrett (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
PH
Councillor Peter Hicks (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
KT
Councillor Kelly Tolhurst (Con)Committee Member, apologies
ND
Neil DaviesOfficer, in attendance
KC
Kim CareyOfficer, in attendance
MH
Mick HaywardOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Gateway 1 Procurement Commencement: SEN Provision at New Horizons Academy, ChathamThis decision
  2. Gateway 1: Procurement of Housing Related Support ServicesAgreed
  3. Gateway 1 Procurement Commencement: Repairs and Maintenance for Temporary Accommodation Owned, One Medway Lettings, One Medway – Inspiring Change LA Hostels, Housing Revenue Account (HRA) Requirements, Medway Development Company (MDC) and the Sanctuary SchemeAgreed
  4. Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayAgreed
  5. Gateway 1 Procurement Commencement: Innovation Park Medway NorthAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies