Procurement Update 2024/25

Approved Finance 1 paper

Nottingham Fire and Rescue Authority - Finance and Resources approved this item on Friday 21 March 2025. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

Resolved to: 1) approve the proposed procurement award route to be undertaken for contracts exceeding WTO GPA thresholds; 2) delegate authority to the Head of Finance, in consultation with the Chair of Finance and Resources Committee, to award contracts for the three current procurement schemes, as detailed in the report; 3) to note that the Committee scrutinised the single source supplier contracts awarded in 2024/25.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Finance and Resources

Recommendations

It is recommended that Members:

 Consider the proposals for the award of contracts exceeding WTO GPA threshold detailed in 2.1 and approve the procurement award route to be undertaken.  Give delegated authority to the Head of Finance to award the three contracts detailed in 2.1.  Scrutinise the single source supplier contracts awarded in 2024/25.

CONTACT OFFICER Bev Bull Name: Head of Finance and Treasurer to the Fire Authority Tel: 0115 8388648

Email: [email protected]

Media Enquiries Corporate Communications Team Contact: (0115) 967 0880 [email protected] 1. BACKGROUND

1.1The Finance and Resources Committee are required to consider proposals for awards of contracts exceeding the World trade Organisation (WTO) and Government Procurement Agreement (GPA) Thresholds. This replaced the OJEU Threshold post Brexit. The current WTO GPA threshold limits are £214,904 for supplies and services and £5,336,937 for works contracts (both limits include VAT).

1.2The overarching requirement of public sector procurement is to achieve value for money defined as “the best mix of quality and effectiveness for the least outlay over the period of use of the goods or services bought”. The procurement of goods, works, and services should be achieved through competition, unless there are compelling reasons to the contrary.

1.3Financial Procedures outline specific circumstances where the tendering procedures may be waived, and the Procurement Policy requires in these circumstances that a Single Source Supplier form is completed for approval by the Procurement Manager, the Area Manager of Resources and the Head of Finance and Treasurer.

1.4The Finance and Resources Committee are required to receive an annual report on all instances where exemptions have been applied to waive the tendering procedures in accordance with Financial Procedures. This annual report is contained within this report.

2. REPORT

Current procurement activity above World trade Organisation (WTO) and Government Procurement Agreement (GPA) Thresholds

2.1The tendering procedures for the following three contracts are currently being considered:

 Bulk Fuels - This is the contract by which all diesel is delivered to fire stations for use by the appliances. The value of the contact is estimated to be £400k per annum. The proposal is to use the ESPO framework and enter into a contract for 4 years. The rates of the suppliers on the framework are being compared to identify best value and a direct award through the framework will be completed.

 Tyres – replacement tyre contract for all service vehicles including appliances to light fleet. The value of the contact is estimated to circa £80k per annum, the proposal is to use the ESPO framework and enter into a contract for 4 years. The price and quality of service are being compared to identify best value and a direct award through the framework will be completed.

 Stockhill Build Project Manager – This is the contract for the project manager for the Stockhill build. The value of the contact is estimated to be circa £200k based on a percentage of the overall build cost. The proposal is to undertake a mini competition using an appropriate framework.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement Update 2024/25Report 183 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
JC
Councillor John Clarke MBEChair, present
CB
Councillor Callum BaileyCommittee Member, apologies (personal reasons)
RB
Councillor Richard ButlerCommittee Member, present
SF
Councillor Sybil FieldingCommittee Member, present
AK
Councillor Anwar KhanCommittee Member, present
TS
Councillor Tom SmithCommittee Member, apologies (personal reasons)
CZ
Catherine Ziane-PryorClerk, present
BB
Bev BullOfficer, present

On this subject at Nottingham

Search all
  1. Procurement Update 2024/25This decision
  2. Fleet Services Procurement Activity 2026-2032Approved
  3. Procurement of replacement Backup and Disaster Recovery infrastructureApproved
  4. Procurement of replacement core infrastructure serversApproved
  5. Procurement of digital, AI, automation and telephony platforms - key decisionApproved
  6. Procurement of new railway gantry - key decisionApproved

More from Nottingham Nottingham Fire and Rescue Authority - Finance and Resources

All decisions
MeetingDecisionOutcome
19 Jun 2026 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... Approved Open
19 Jun 2026 Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... Approved Open
19 Jun 2026 External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... Decided Open
19 Jun 2026 Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... Noted Open
27 Mar 2026 Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies