DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO COMMUNITY SERVICES COMMITTEE
meeting date: 11 JANUARY 2022 title: REVISED CAPITAL PROGRAMME 2021/22 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To approve the 2021/22 revised estimate for this Committee’s capital programme.
1.2Relevance to the Council’s ambitions and priorities:
Community Objectives – none identified. Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs. Other Considerations – none identified.
2 2021/22 CAPITAL PROGRAMME BACKGROUND
2.1Five capital schemes for this Committee’s original estimate budget, totalling £1,555,000, were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2021 and March 2021 respectively. This included three new schemes for 2021/22 and budget for two 2020/21 schemes that had been moved from the 2020/21 capital programme to the 2021/22 capital programme.
2.2In addition to the original estimate budget above, the following budget changes have been made so far in 2021/22:
Three capital schemes were not completed by 31 March 2021 and had unspent budget available at that date. The total unspent budget of £60,320 on those schemes, known as slippage, has been moved into the 2021/22 capital programme budget, after approval by this Committee in May 2021.
One additional capital scheme with a budget of £45,000 was approved by Policy and Finance Committee in March 2021.
One additional capital scheme with a budget of £24,000 was approved and one scheme had additional budget of £62,660 approved on it by Policy and Finance Committee in June 2021.
One additional capital scheme with a budget of £25,200 was approved and one scheme had additional budget of £17,940 approved on it by Policy and Finance Committee in September 2021.
One additional capital scheme with a budget of £18,780 was approved by Policy and Finance Committee in November 2021.
2.3As a result of the above, the total approved budget for this Committee’s capital programme of twelve schemes was £1,808,900. This is shown at Annex 1.
16-21cm 1 of 5 3 REVISING THE 2021/22 CAPITAL PROGRAMME
3.1We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect their progress and estimated full year expenditure. Following this review, the proposed revised estimate is £591,360 for twelve schemes, a reduction of £1,217,540 from the total approved budget. The reasons for this are:
Replacement of Refuse Collection Vehicle VU62 HXK (-£2,850): The actual cost of the vehicle was £2,850 lower than the 2021/22 original estimate budget of £232,000, so it is proposed that the 2021/22 revised estimate for the scheme is reduced to £229,150.
Installation of a Second Parking Deck on Chester Avenue Car Park (-£1,215,000): The scheme is still at feasibility stage on the second site being considered. A progress report is to be taken to Community Committee in January 2022. Given this, there is the possibility of some initial feasibility study spend only in-year, so it is proposed that the majority of the scheme budget, £1,215,000, is moved to the 2022/23 financial year and the 2021/22 revised estimate for the scheme is reduced to £15,000. NOTE - This scheme was included in the capital programme on the basis that a feasibility study is undertaken to prove the need for additional car parking spaces, and that this be reported to Policy and Finance Committee for further consideration before the capital scheme and any associated expenditure can go ahead.
Replacement of Pickup Ford Ranger PK60 HKN (+£310): The order price for this vehicle purchase is £308 higher than the 2021/22 budget of £25,250, so it is proposed that the 2021/22 revised estimate for the scheme is increased to £25,560.
3.2Annex 1 shows the full capital programme by scheme, including the budget and expenditure to date. The summary position is shown below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.