Capital Programme Review and New Bids 2022/23 to 2026/27

Approved Committee 1 paper

Community Services approved this item on Tuesday 11 January 2022. Below is the council's own wording, with the papers it was decided on.

Item541

Resolved

RESOLVED THAT COMMITTEE: 1. Confirm the schemes in the existing capital programme; 2. Request £77,000 of additional funding from Policy and Finance committee for those schemes where estimates have changed; and 3. Approve all the new capital bids as outlined in the report to be forwarded to Policy and Finance committee to be considered as part of the Overall Capital Programme.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Community Services

Background

2.1This report will review the schemes that were approved in to the capital programme in March 2021, for the financial years 2022/23 to 2024/25. Also, new bids received from Heads of Service covering 2022/23, 2025/26 and 2026/27 are presented for consideration. No bids have previously been requested for 2025/26 or 2026/27.

2.2In the same manner as previous years, all Heads of Service were asked to submit new capital bids.

3 REVIEW OF THE CAPITAL PROGRAMME 2022/23 TO 2024/25

3.1For this Committee there were originally 23 schemes approved for the financial years 2022/23 to 2024/25, totalling £1,833,900. These schemes are shown in Annex 1.

3.2Review of the schemes by Heads of Service has identified proposed amendments to 9 previously approved schemes, totalling £77,000, as follows:

 AMENDMENT 1: Replacement of John Deere Mower 4x4 (PE15 YVR) – the cost of the replacement machine has increased since the original bid was submitted. An addition to the budget of £3,500 is sought.

 AMENDMENT 2: Replacement of Kubota Mower PN09 KXP – the cost of the replacement machine has increased since the original bid was submitted. An addition to the budget of £5,000 is sought.

 AMENDMENT 3: Replacement Football Goals – the cost of replacement football goals has increased since the original bid was submitted. An addition to the budget of £1,000 is sought.

 AMENDMENT 4: Replacement of Refuse 4 Tonne Tipper PO60 AYK – the cost of the replacement vehicle has increased since the original bid was submitted. An addition to the budget of £5,400 is sought.

 AMENDMENT 5: Replacement of High Top Transit Van PJ63 WUC – the cost of the replacement vehicle has increased since the original bid was submitted. An addition to the budget of £14,500 is sought.

 AMENDMENT 6: Replacement of Refuse Collection Vehicle VN12 KYK – the cost of the replacement vehicle has increase due to safety features required and an increase in steel prices. An addition to the budget of £1,000 is sought.

15-21cm 1 of 8  AMENDMENT 7: Castle Keep Lime Re-pointing Works and Repairs (subject to external funding) – The Castle Keep's condition is depreciating each year, due to the prominent location of the building it is exposed to all weather conditions. The cost of works needed has increased since the original bid was submitted. An addition to the budget of £34,100 is sought. Please also note that external funding has not yet been able to be secured in respect of this scheme.

 AMENDMENT 8: Replacement of Refuse Collection Vehicle PK63 JZP – the cost of the replacement vehicle has increase due to safety features required and an increase in steel prices. An addition to the budget of £4,500 is sought.

 AMENDMENT 9: Replacement of Refuse Collection Vehicle VN65 WHR – the cost of the replacement vehicle has increase due to safety features required and an increase in steel prices. An addition to the budget of £8,000 is sought.

3.3The table below shows the 9 proposed amendments and their financial impact on the 2022/23 to 2024/25 capital programme for this Committee. The proposed amendments are also included at Annex 1.

2022/23 2023/24 2024/25 TOTAL £ £ £ £ Previously Approved Capital Programme for Community 920,100 462,800 451,000 1,833,900 Services Committee (Annex 1) AMENDMENT 1: Replacement of 3,500 3,500 John Deere Mower 4x4 (PE15 YVR) AMENDMENT 2: Replacement of 5,000 5,000 Kubota Mower PN09 KXP

AMENDMENT 3: Replacement 1,000 1,000 Football Goals

AMENDMENT 4: Replacement of 5,400 5,400 Refuse 4 Tonne Tipper PO60

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Review and New Bids 2022/23 to 2026/27Report 391 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 24 attended
RN
Councillor Richard NewmarkChair, present
JA
Councillor Jan Alcock JPCommittee Member, present
SA
Councillor Stephen AtkinsonCommittee Member, apologies
DB
Councillor David BirtwhistleCommittee Member, present
SB
Councillor Stella Brunskill JPCommittee Member, present
SC
Councillor Stuart CarefootCommittee Member, expected
R(
Councillor Rosemary (Rosie) ElmsVice-Chair, present
SF
Councillor Stewart FletcherCommittee Member, present
AH
Councillor Angeline HumphreysCommittee Member, apologies
GM
Councillor Ged MirfinCommittee Member, present
SO
Councillor Simon O'RourkeCommittee Member, present
SR
Councillor Sarah RainfordCommittee Member, present

All 24 on the meeting page

On this subject at Ribble Valley

Search all
  1. Capital Programme Review and New Bids 2022/23 to 2026/27This decision
  2. Overall Revised Capital Programme 2025/26Approved
  3. Four Year Capital Programme 2026/27 to 2029/30Decided
  4. Revised Capital Programme 2025/26Approved
  5. Capital Programme Review 2026/27 - 2029/30Approved
  6. Revised Capital Programme 2025/26Approved

More from Ribble Valley Community Services

All decisions
MeetingDecisionOutcome
25 Aug 2026 Ribblesdale PoolIt was agreed that the solar panel element should be removed from the current contract and considered separately. Thi... Agreed Open
25 Aug 2026 Clitheroe WellsRESOLVED THAT COMMITTEE: Authorise to the Director of Community Services to continue to take the required steps towar... Decided Open
25 Aug 2026 Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co... Approved Open
25 Aug 2026 Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 3 of Part 1 of Schedule 12A of t... Decided Open
26 May 2026 Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approved the slippage of £1,000,940 as set out at paragraph 3.6 of the report. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies