RESOLVED THAT COMMITTEE: Approved the 2022/23 revised estimate of £671,320 for this Committee’s capital programme, as set out in Annex to the report. Approved the move of the following capital scheme budgets from 2022/23 to 2023/24: · Castle Keep Lime Repointing Works and Repairs, £307,600. · Replacement of Refuse Iveco Tipper (PO60 AYK), £46,000. · Replacement of High Top Transit Van PJ63 WUC, £34,500. · Mardale Playing Pitches Drainage, £80,440. · Edisford Playing Pitches Drainage Works, £10,900.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO COMMUNITY SERVICES COMMITTEE
meeting date: 10 JANUARY 2023 title: REVISED CAPITAL PROGRAMME 2022/23 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To approve the 2022/23 revised estimate for this Committee’s capital programme.
1.2Relevance to the Council’s ambitions and priorities:
Community Objectives – none identified.
Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs.
Other Considerations – none identified.
2 2022/23 CAPITAL PROGRAMME BACKGROUND
2.1Fifteen capital schemes for this Committee’s original estimate budget, totalling £2,280,500, were approved by the Policy and Finance Committee and Full Council at their meetings in February 2022 and March 2022 respectively. This included fourteen new schemes for 2022/23 and one scheme that had been moved from the 2021/22 capital programme to the 2022/23 capital programme.
2.2Five capital schemes were not completed by 31 March 2022 and had some unspent budget available at that date. The total unspent budget of £153,240 on those schemes, known as slippage, was moved into the 2022/23 capital programme budget, after approval by this Committee in May 2022.
2.3As a result of the above, the total approved budget for this Committee’s capital programme of nineteen schemes was £2,433,740. This is shown at Annex 1.
3 REVISING THE 2022/23 CAPITAL PROGRAMME
3.1We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect progress on the schemes and estimated full year expenditure. Following this review, the proposed revised estimate is £671,320 for sixteen schemes, a reduction of £1,762,420 from the total approved budget. The reasons for this are as follows:
Clitheroe Town Centre Car Park Scheme (-£1,230,000): At its meeting in August 2022, this Committee approved the removal of this scheme from the capital programme, because the review of car parking spaces in Clitheroe had concluded that there was, presently, no need for extra town centre parking provision, but that LCC should continue to be lobbied to assist in making the market car park more accessible. Therefore, the 2022/23 revised estimate budget for this scheme is reduced to nil.
3-23cm 1 of 7 Castle Keep Lime Repointing Works and Repairs (-£307,600): At the end of November 2022, a bat survey had been ordered and is likely to be completed in-year. Also, the external consultants that are being engaged for the pre-contract stages of this scheme have been selected and are likely to be formally appointed in early 2023, subject to final contract agreement and their work may be completed in 2022/23, subject to final contract agreement. However, given the time involved in specifying and designing this type of scheme and then tendering, it is not expected that there will be any work undertaken on the main contract works in 2022/23, Therefore, it is expected that only a small part of the scheme budget will be spent in 2022/23, estimated to be £19,700.
Given the above, it is proposed that £307,600 of the scheme budget is moved to the 2023/24 capital programme and the 2022/23 revised estimate scheme budget is reduced to £19,700.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.