RESOLVED THAT COMMITTEE: 1. Considered and agreed a future capital programme for this Committee’s services for onward recommendation to Policy and Finance Committee for the period 2023/24 to 2027/28, based on the proposals included in this report with the addition of a bandstand in Longridge at an approximate cost of £200,000. 2. Recognise that further capital bids will be submitted to the Policy and Finance Committee by the political groups, which may impact on this Committee. 3. Agreed that officers submit a report to the next meeting of this Committee on the return of the toilets on Berry Lane Longridge to the ownership of RVBC. Agreed to bring the new feasibility study bid on Ribblesdale Pool forward to 2023/24.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
2.1The Council usually operates a five-year capital programme, but only a three-year capital programme for 2022/23 to 2024/25 was approved last year. This is because the Council was awaiting the outcome of the Government’s fair funding review before committing to setting a longer term five-year capital programme. Committees had however submitted capital scheme bids for 2025/26 to 2026/27 as part of last year’s capital programme review.
2.2This year, the aim is to return to a five-year capital programme, covering the period 2023/24 to 2027/28. Therefore, Heads of Service were asked to: review the capital schemes already approved for 2023/24 and 2024/25 review any previously submitted capital scheme bids for 2025/26 and 2026/27; and submit new capital scheme bids for 2027/28.
2.3Once this committee has considered the schemes within this report, and any further schemes that members may wish to submit, the capital programme reviews and new bids for each Committee area will then be considered alongside each other by the Budget Working Group and Policy and Finance Committee in producing the Council’s capital programme for 2023/24 to 2027/28.
3 REVIEW OF PREVIOUSLY APPROVED CAPITAL PROGRAMME SCHEMES FOR 2023/24 TO 2024/25
3.1For this Committee there were originally twelve schemes approved for the 2023/24 to 2024/25 capital programme, totalling £926,300. These schemes are shown in Annex 1.
3.2Review of the schemes by Heads of Service has resulted in proposed amendments to all of the previously approved schemes. This is mainly as a result of updating the scheme values for increased levels of price inflation since last year’s capital programme review. It should also be noted that a further late bid is to be submitted for the Refurbishment of Mardale Playing Field Changing Rooms scheme to request additional resources to better reflect the latest plans for this scheme. The costs of the original scheme plan only are included in this capital programme review.
5-23cm Page 1 3.3 The table below shows the financial impact of the proposed amendments put forward by Heads of Service. The proposed amendments for each scheme are shown in Annex 1.
2023/24 2024/25 TOTAL £ £ £ Previously Approved Capital Programme Costs for Community 467,300 459,000 926,300 Services Committee Proposed Cost Amendments to the Previously Approved Capital 20,700 43,800 64,500 Programme Amended Capital Programme for 488,000 502,800 990,800 Community Services Committee
3.4The proposed amendments to the previously approved capital schemes for 2023/24 to 2024/25 will result in increased costs of £64,500, thus increasing the previously approved capital programme for this Committee to £990,800.
4 REVIEW OF PREVIOUSLY SUBMITTED CAPITAL SCHEME BIDS FOR 2025/26 to 2026/27
4.1For this Committee, thirty-one capital scheme bids were submitted last year for the financial years 2025/26 to 2026/27, totalling £10,500,050. A list of the scheme bids are shown in Annex 2. The individual scheme bid documents were reported to this Committee in January 2022.
4.2Review of these previously submitted bids by Heads of Service has resulted in proposed amendments to the vast majority of the bids. This is mainly as a result of updating the bid values for inflation since the bids were submitted last year.
4.3The table below shows the financial impact of the proposed bid amendments put forward by Heads of Service. The proposed bid amendments for each scheme are shown in Annex 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.