Salford City Council - Record of Decision I Councillor Tracy Kelly, Deputy City Mayor , in exercise of the powers contained within the City Council constitution do hereby a pprove the proposed programmes of work as detailed in the Highways Investment Programme (HIP) for 2024/25 The Reasons are to facilitate continuous improvement of the highway infrastructure as part of the defined Network Recovery Plan as part of the ongoing rolling programme of repair works Options considered and rejected : none Assessment of Risk : Low - The targeted spend of available funding will ensure that the City Council’s statutory obligations are met while at the same time facilitating continuous improvement of the highway infrastructure. The source of funding is : Prudential Code funding (Capital) Legal advice obtained : Helen Chapman, Principal Solicitor and Tony Hatton Shared Legal Service Financial advice obtained : Yes - Adam Flaherty Senior Accountant, Finance Division Procurement Advice obtained: Yes - Heather Stanton Category Manager HR advice/implications: N/A Climate Change advice obtained: Michael Hemmingway, Principal Officer Climate Change and Mick Horsfall, Team Leader Environment Policy Report submitted to Property/Regeneration Briefing on 22 April 2024 Contact Officer: Steve Mangan - Group Engineer Highway Asset Management * This decision is not subject to consideration by another Lead Member Executive Director * The appropriate scrutiny committee to call-in the decision is the Growth and Prosperity Scrutiny Panel. Signed: Councillor Tracy Kelly Deputy City Mayor Dated: 22 April 2024 * This decision was published on Monday 22 April 2024 * This decision will come in force at 4.00 p.m. on Monday 29 April 202 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting.Source: sccdemocracy.salford.gov.uk
That the City Mayor notes the proposed programmes of work for the Highway Investment Programme (HIP) 2024/25 and subject to any matters arising the report is further submitted for approval on 22nd April 2024
EXECUTIVE SUMMARY: The financial provision for the Highway Investment Programme funding for 2024/25 has been set at £3,800,000 made up from £3m unsupported borrowing and £800k from the GMCA Highway Maintenance Grant. The budget apportionments outlined in the report, and detailed within the background document, outline the 2024/25 scheme proposals as part of the ongoing Highway Investment Programme.
BACKGROUND DOCUMENTS:
Appendix A -Highway Investment Programme- List of Provisional Footway Schemes 2024/25 and beyond
Appendix B- Highway Investment Programme-List of Provisional Carriageway Schemes 2024/25 and beyond
1 KEY DECISION: Yes-this report will be presented to the City Mayor for briefing and approval.
DETAILS:
1. The Highway Investment Programme
1.1The Capital allocation for the Highway Investment Programme during 2024/25 has been specified as £3,800,000. 1.2 Salford City Council implemented a Network Recovery Plan (delivered through the Highway Investment Programme) in 2009/10. This was put in place to arrest the deterioration of the highway network initially and to enable the Council to tackle the critical sections of highway thereafter. 1.3 Since the start of the current Highway Investment Programme in 2010, the following condition indices for both footway and carriageway have been achieved.Targets are the aspirational figures that are reviewed each year based on previous year’s results and are not projections. These will vary based on levels of investment. These are therefore currently affected by the investment levels provided which has until last year been less than the investment requested. Tables 1 and 2 below provide the overall condition indices for the carriageways (Table 1) and footways (Table2). The indices provided are based on the current investment levels provided.
Table 1 – Carriageway Condition Index Summary % of classification within each category
(The Highway Improvement Programme commenced in 2009/10) *Targets are aspirational figures that are reviewed each year based on previous year’s results and are not projections. These will vary based on levels of investment provided. £2.5m provides investment so that the overall footway condition remains at a steady state.
red 2 1.4 2 2 3.4 4 4 5 6 7 7 amber 19.6 14.2 16 17 17.9 18 17 16 16 15 13 yellow 57 50.4 61 60 43 43 41 32 33 35 36 green 21.4 34 21 21 35.7 35 38 47 45 43 44 (The Highway Improvement Programme commenced in 2009/10) *Targets are aspirational figures that are reviewed each year based on previous year’s results and are not projections. These will vary based on levels of investment provided. £1.2m provides investment so that the overall footway condition remains at a steady state.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.