Resolved – (a) That scheme 2.26 Wokingham Winnersh Relief Road Phase 2 be given financial approval in the sum of £6,260,000 (£3,000,000 in 2018/19 and £3,260,000 in 2019/20) on the terms of the funding agreement set out at paragraph 13 step 5 of the report, subject to meeting the following conditions: (b) The supply of further evidence which supported the conclusions reached in the Full Business Case in respect of: · The provision of cycle lanes and footpaths and their social impacts; · Revisions to the net land value uplift calculation and adjusted present value of costs in the Economic Case; · Sensitivity tests, scheme build cost, risk contingency, financial profiles, inflation, maintenance, renewals and optimism bias in the Financial Case; · Procurement and management of project cost variations; · The risk register, risk management, contract management and contingency plans.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.26 Wokingham Winnersh Relief Road Phase 2 from the Business Rates Retention Pilot.
2. The full project will deliver a new relief road to the west of Winnersh, avoiding the current Winnersh Crossroads junction. The work will be delivered in two phases. The first phase, delivered by a Bovis / Persimmon, opened on in June 2018. The second phase will be delivered by Wokingham Borough Council and will provide a new junction on the A329 Reading Road and will dual the section of Lower Earley Way (B3270).
3. This scheme will provide 1,415 new houses and enhance urban connectivity.
Recommendation
4. You are recommended to give scheme 2.26 Wokingham Winnersh Relief Road Phase 2 financial approval in the sum of £6,260,000 (£3,000,000 in 2018/19 and £3,260,000 in 2019/20) on the terms of the funding agreement set out at paragraph 13 step 5 below subject to meeting the following conditions:
4.1The supply of further evidence which supports the conclusions reached in the Full Business Case in respect of: • the provision of cycle lanes and footpaths and their social impacts; • revisions to the net land value uplift calculation and adjusted present value of costs in the Economic Case; • sensitivity tests, scheme build cost, risk contingency, financial profiles, inflation, maintenance, renewals and optimism bias in the Financial Case; • procurement and management of project cost variations; • the risk register, risk management, contract management and contingency plans
Other Implications
Financial
5. Scheme 2.26 Wokingham Winnersh Relief Road Phase 2 was a named scheme in the Thames Valley Berkshire Growth Deal 3i announced on 2 February 2017ii. You gave it programme entry status in March 2017. Item 6 BLTB 15 November 2018 Financial Approval for 2.26 Wokingham Winnersh Relief Road Phase 2 6. In July 2018 you agreed to change the funding source for this scheme from Local Growth Deal to the Business Rates Retention Pilot. All other aspects of the scheme remained unchanged.
7. This report recommends that Wokingham Borough Council be authorised to draw down the capital sum £6,260,000 for this scheme.
8. The funding agreement set out at paragraph 13 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
9. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Frameworkiii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
10. The scheme promoter is a local authority and they must act within the law. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Supporting Information
11. The scheme will be carried out for Wokingham Borough Council.
12. The full details of the scheme are available from the Wokingham websiteiv. A summary of the key points is given below:
Task Timescale Procurement November 2018 Contractor appointed As above Construction Autumn 2019 Open to public September 2020
Activity Funder Cost (approx) Scheme development Wokingham Borough £7.204m Major scheme funding Berkshire Local Transport Body £6.260m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.