Resolved – (a) That scheme 2.27 Maidenhead Town Centre: Missing Links be given financial approval in the sum of £2,241,787 (£243,310 in 2018/19 and £817,718 in 2019/20 and £1,180,759 in 2020/21) on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions: (b) The supply of further evidence which supports the conclusions reached in the Full Business Case in respect of: · the impact of disruption caused during scheme construction; · the impact of interim arrangements for cycling and walking pending development of key sites; · the impact of late- or non-delivery of inter-dependent development; · the demand forecasts and monetised benefits in the Economic Case · procurement, cost estimates, spend profile and inflation; · the risk register; · the monitoring and evaluation and contingency plans.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.27 Maidenhead Town Centre: Missing Links
2. The purpose of this scheme is to complete the ‘missing links’ between planned major development areas in and around Maidenhead and to improve their connectivity to the town centre, surrounding residential areas and local facilities. A new ‘inner-ring’ is proposed for pedestrians and cyclists, which will be tied into new or enhanced crossings of the A4. The routes will tie into the infill public realm areas in the town, which will in turn trigger a review of the core town centre road network.
Recommendation
3. You are recommended to give scheme 2.27 Maidenhead Town Centre: Missing Links financial approval in the sum of £2,241,787 (£243,310 in 2018/19 and £817,718 in 2019/20 and £1,180,759 in 2020/21) on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions:
3.1The supply of further evidence which supports the conclusions reached in the Full Business Case in respect of: • the impact of disruption caused during scheme construction; • the impact of interim arrangements for cycling and walking pending development of key sites; • the impact of late- or non-delivery of inter-dependent development; • the demand forecasts and monetised benefits in the Economic Case • procurement, cost estimates, spend profile and inflation; • the risk register; • the monitoring and evaluation and contingency plans.
Other Implications
Financial
Item 7 BLTB 15 November 2018 Financial Approval for 2.27 Maidenhead Town Centre: Missing Links 4. Scheme 2.27 Maidenhead Town Centre: Missing Links is a named scheme in the Thames Valley Berkshire Growth Deal 3i announced by the Government on 2 February 2017ii. You gave it programme entry status in March 2017.
5. This report recommends that the Royal Borough of Windsor and Maidenhead be authorised to draw down the capital sum £2,241,787 from the Local Transport Body funding for this scheme.
6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
7. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Frameworkiii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
8. The scheme promoter is a local authority and they must act within the law. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Supporting Information
9. The scheme will be carried out for the Royal Borough of Windsor and Maidenhead.
10. The full details of the scheme are available from the Royal Borough of Windsor and Maidenhead website. A summary of the key points is given below:
Task Timescale Procurement October 2019 Contractor appointed As above Construction July 2020 Open to public March 2021
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.