Resolved – (a) That scheme 2.14 and 2.25 East Reading MRT Phases 1 and 2 be deleted from the LGF programme following notification from Reading Borough Council that it cannot now be progressed before March 2021. (b) That programme entry status be granted to the following schemes (agreed at the meeting of the BLTB in July 2018): · 2.35 Reading: Reading West Station Upgrade · 2.36 Wokingham: Coppid Beech Park and Ride · 2.37 Bracknell: A322 A329 Corridor Improvements · 2.38 Theale: Theale Station Park and Rail Upgrade · 2.39 Wokingham: Coppid Beech northbound on-slip widening · 2.40 Windsor: Town Centre Package (c) That consideration of programme entry status for scheme 2.41 Slough: SMaRT Phase 3 A4 West Park and Ride be deferred until the meeting of the BLTB in March.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To report on the delay to the progress of scheme 2.14 and 2.25 East Reading MRT Phases 1 and 2, and the subsequent confirmation from the scheme promoter that it cannot be delivered within the current Local Growth Fund (LGF) programme, i.e. by the end of 2020/21.
2. To propose the re-allocation of £19,067,000 LGF allocated to scheme 2.14 and 2.25 East Reading MRT Phases 1 and 2 - to seven schemes taken from the previously agreed prioritised list.
Recommendation
3. You are recommended to delete scheme 2.14 and 2.25 East Reading MRT Phases 1 and 2 from the LGF programme following notification from Reading Borough Council that it cannot now be progressed before March 2021.
4. You are recommended to grant programme entry status to the following schemes (agreed at the meeting of the BLTB in July 2018):
a. 2.35 Reading: Reading West Station Upgrade b. 2.36 Wokingham: Coppid Beech Park and Ride c. 2.37 Bracknell: A322 A329 Corridor Improvements d. 2.38 Theale: Theale Station Park and Rail Upgrade e. 2.39 Wokingham: Coppid Beech northbound on-slip widening f. 2.40 Windsor: Town Centre Package
5. You are recommended to defer consideration of programme entry status for scheme 2.41 Slough: SMaRT Phase 3 A4 West Park and Ride until the meeting of the BLTB in March.
Other Implications
Financial
6. The LGF programme covers six financial years, 2015-16 to 2020-21, and the expectation is that the funds allocated to Thames Valley Berkshire LEP will be spent in that period, or failing that, fully committed to schemes that have started
Item 4 BLTB 31 January 2019 Revised Local Growth Fund Programme 2015/16 to 2020/21 on site by March 2021 and have a “tail” of funding carried over into financial year 2021-22.
7. Reading Borough Council (RBC), in accordance with the conditions of the capital grant, have notified the LEP that they cannot now achieve a start on site for the East Reading (ER) MRT scheme. There is therefore, £19,067,000 of LGF available for reallocation. This report recommends that seven new schemes from the previously agreed list be considered for programme entry status.
8. The amount available for reallocation is £20,233,000, comprising £1,166,000 as yet unallocated (at November 2018) and £19,067,000 from the ER MRT scheme. The total of the seven schemes considered for programme entry status is £18,744,931.
Table 1: Reallocation amounts Unallocated amount as at November 2018 1,166,000 Add: 2.14 and 2.25 East Reading MRT phases 1 and 2 19,067,000 20,233,000 Less: 2.35 Reading: Reading West Station Upgrade 3,100,000 2.36 Wokingham: Coppid Beech Park and Ride 2,400,000 2.37 Bracknell: A322 A329 Corridor Improvements 1,200,000 2.38 Theale: Theale Station Park and Rail Upgrade 4,000,000 2.39 Wokingham: Coppid Beech northbound on-slip widening 2,322,431 2.40 Windsor: Town Centre Package 1,562,500 14,584,931 Available 5,648,069 Less: if agreed 2.41 Slough: SMaRT Phase 3 A4 West Park and Ride 4,160,000 Available 1,488,069
9. Although the vast majority of LGF is ringfenced for strategic transport schemes there remains the possibility that the LEP will bring forward skills capital projects for consideration, if these offer VfM, make more of a strategic impact and can be delivered swiftly. This will be confirmed before the BLTB meeting in March.
10. If no new schemes are given programme entry status and the £20,233,000 remained uncommitted at March 2021, it would have to be returned to the government unspent.
Risk Management 11. There remains a risk that the new schemes identified in this report will be unable to mobilise quickly enough to achieve the necessary start on site by March 2021; in that event any LGF not committed would be liable for return the government unspent.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.