Resolved – That scheme 2.34 Slough MRT Phase 2 be given full financial approval in the sum of £13,300,000, with £10,242,000 in 2018/19 from BRRP1 and £3,058,000 in 2019/20 from BRRP2 on the terms of the funding agreement set out at paragraph 12 step 5 of the report. (Matthew Taylor rejoined the meeting)
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.34 Slough MRT Phase 2 from the Business Rates Retention Pilot.
2. The A4 forms the spine of a 12km strategic public transport corridor that links Maidenhead, Slough and Heathrow and plays an important role in providing surface access to the airport. Phase 2 will extend the Slough Mass Rapid Transit (SMaRT) project from its current end point at Langley and take it onto the Heathrow service road. Bus lanes and other priority measures will be provided in the new section between Langley and Heathrow.
3. The scheme will also provide a 600-car park and ride site at Brands Hill.
Recommendation
4. You are recommended to give scheme 2.34 Slough MRT Phase 2 full financial approval in the sum of £10,242,000 in 2019/20 on the terms of the funding agreement set out at paragraph 12 step 5 below.
Other Implications
Financial
5. Scheme 2.34 Slough MRT Phase 2 is funded by the Business Rates Retention Pilot. This scheme has been previously submitted for funding from the Local Growth Deal as far back as 2014. Though Phase 2 was never prioritised for funding, Phase 1 was included in the first Local Growth Deal approvals as scheme 2.08, which was completed in 2018.
6. Scheme 2.34 Slough MRT Phase 2 was originally presented to BLTB requesting £13,300,000 but received Programme Entry Status for a lower amount, due to limited funds being available. The remaining top-up funding of £3,058,000 would be made available to Slough Borough Council as a priority for BRRP 2 funds, should the pilot be successful. 7. This report recommends that Slough Borough Council be authorised to draw down the capital sum £10,242,000 from BRRP funds for this scheme.
8. The funding agreement set out at paragraph 12 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
9. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 12, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
10. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Supporting Information
11. The scheme will be carried out for Slough Borough Council.
12. The full details of the scheme are available from the Slough websiteii. A summary of the key points is given below:
Task Timescale Procurement Via the Council’s Term Contractor Contractor appointed As above Construction May 2019 Open to public April 2020
Activity Funder Cost (approx) Scheme development Slough Borough £0 Major scheme funding Berkshire Local Transport Body £10,242m Section 106 agreements Developers etc £0 Total £10,242m 13. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of Assurance Frameworkiii.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.