Resolved – (a) That it be noted that: · the allocated funding for scheme 2.33 GWR Maidenhead to Marlow Branch Line for £1,525,000 had been withdrawn; · the allocated funding for Scheme 2.37 Bracknell A322/A329 Corridor Improvements had been changed from £2,000,000 to £400,000. (b) That programme entry status be granted to the following schemes: · 2.29 Wokingham Winnersh Park and Ride addendum 2 Turning Head and Urban Realm Improvements for £675,000; · 2.24 Newbury Station addendum 2 Cycle Hubs and Office Space Improvements for £340,000; · 2.45 Slough: Langley High Street Improvements phase 1 for £1,324,000; and · 2.46 Slough: Langley High Street Improvement phase 2 for £1,033,000.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To note two changes to the current programme of LGF schemes:
1.1Scheme 2.33 GWR Maidenhead to Marlow Branch Line upgrade has been withdrawn by Buckinghamshire Thames Valley LEP and GWR 1.2. Scheme 2.37 Bracknell A322/A329 Corridor Improvements has been Reprofiled.
2. Consequently, to grant programme entry status to four schemes from the approved March 2020 BLTB list of prioritised pipeline schemes:
2.1Scheme 2.29 Wokingham Winnersh Park and Ride addendum 2 Turning Head and Urban Realm improvements 2.2. Scheme 2.24 Newbury Station addendum 2 Cycle Hubs and Office Space Improvements 2.3. Scheme 2.45 Slough Langley High Street Improvements phase 1 2.4. Scheme 2.46 Slough Langley High Street Improvement phase 2.
Recommendation
3. You are recommended to note: 3.1. the withdrawal of the allocated funding for scheme 2.33 GWR Maidenhead to Marlow Branch Line for £1,525,000; 3.2. the change in the allocated funding for Scheme 2.37 Bracknell A322/A329 Corridor Improvements from £2,000,000 to £400,000.
4. You are therefore recommended to grant programme entry status to schemes:
4.12.29 Wokingham Winnersh Park and Ride addendum 2 Turning Head and Urban Realm Improvements for £675,000; 4.2. 2.24 Newbury Station addendum 2 Cycle Hubs and Office Space Improvements for £340,000; 4.3. 2.45 Slough: Langley High Street Improvements phase 1 for £1,324,000; and 4.4. 2.46 Slough: Langley High Street Improvement phase 2 for £1,033,000.
Item 4 BLTB 4 June 2020 Revised Local Growth Fund Programme 2015/16 to 2020/21 update Other Implications
Financial
5. The LGF programme covers six financial years, 2015-16 to 2020-21, and the expectation is that the funds allocated to Thames Valley Berkshire LEP will be spent in that period, or failing that, fully committed to schemes that have started on site by March 2021 and have a “tail” of funding carried over into financial year 2021-22.
6. In July 2018 programme entry status was awarded to scheme 2.33 GWR: Maidenhead to Marlow Branch Line Upgrade, allocating £1,525,000 from Thames Valley Berkshire LEP’s Local Growth Fund. Thames Valley Berkshire LEP was the junior funder, with Buckinghamshire Thames Valley LEP awarding £1,700,000 to the project. In April 2020, Buckinghamshire Thames Valley LEP (BTV LEP), notified Thames Valley Berkshire LEP that the scheme was unable to progress within the required timescales and as such they would reallocate their LGF money for scheme 2.33 GWR: Maidenhead to Marlow Branch Line Upgrade to other Buckinghamshire Thames Valley LEP priorities. See appendix 3. Thames Valley Berkshire LEP are therefore proposing to reallocation £1,525,000 to the agreed March 2020 prioritised pipeline of schemes.
7. In January 2019, programme entry status was awarded to the following schemes:
7.1Scheme 2.37 Bracknell A322/A329 Corridor Improvements was allocated £1,200,000, with a further £800,000 being allocated at the July 2019 BLTB meeting bringing the total funds allocated to £2,000,000; 7.2. Scheme 2.39 Wokingham Coppid Beech Northbound On-Slip Widening was allocated £2,322,431. 7.3. Notification was provided at the March 2020 meeting that scheme 2.39 Wokingham Coppid Beech Northbound On-Slip Widening was being withdrawn. Due to the linked nature of schemes 2.39 and 2.37, Bracknell Forest Council decided to reduce the scope of scheme 2.37 Bracknell A322/A329 Corridor Improvements. This reconfigured scheme is now requesting £400,000 of its original allocation of £2,000,000 to deliver part of the scheme.
8. The amount available for reallocation is £3,436,882, as set out in Table 1 below. This report recommends that this reallocated LGF funding allows pipeline schemes to be brought forward.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.