Resolved – (a) That scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 be given conditional financial approval in the sum of £2,123,200 in 2019/20 and £2,090,000 in 2020/21 on the terms of the funding agreement set out at paragraph 12 step 5 below, subject to meeting the following conditions: (b) The supply of further evidence which supported the conclusions reached in the Full Business Case in respect of: · Additional detail outlining the approach adopted to determine the dependent development sites and preferred junction enhancements. · Further detail on how the package of junction improvements will address the secondary objectives relating to accidents, air quality and accessibility for walking & cycling. · Additional detail on the RBWM-HM2 model, its baseline calibration and validation, and how it reflects current junction performance. · Detailed workings to support the outputs of the quantified economic assessment. · Inclusion of sensitivity tests to understand the impact of any variability in the benefits and costs of the scheme. · Full assessment of environmental and social impacts of the scheme and inclusion of an Appraisal Summary Table. · Further detail around scheme costs, contingency (linked to a quantified risk assessment), and levels of cost inflation. · Clarifications to the Commercial Case in relation to the procurement processes. · Provision of a full project programme, risk register and Quantified Risk Assessment · That the scheme retains high or better value for money once these conditions have been met. (Matthew Taylor withdrew from the meeting at this point)
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1.
2. This scheme consists of a package of traffic management measures to deliver additional capacity at key junctions around Maidenhead where modelling has indicated that severe peak hour congestion is likely to occur as a result of planned development and regeneration activity. It will facilitate economic growth by unlocking major housing and commercial development. It will also improve journey times for passengers accessing the Great Western Main Line / Elizabeth Line. The works will be progressed in phases in order to minimise the impact on the local road network.
Recommendation
3. You are recommended to give scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 conditional financial approval in the sum of £2,123,200 in 2019/20 and £2,090,000 in 2020/21 on the terms of the funding agreement set out at paragraph 12 step 5 below, subject to meeting the following conditions:
3.1The supply of further evidence which supports the conclusions reached in the Full Business Case in respect of:
Additional detail outlining the approach adopted to determine the dependent development sites and preferred junction enhancements. Further detail on how the package of junction improvements will address the secondary objectives relating to accidents, air quality and accessibility for walking & cycling. Additional detail on the RBWM-HM2 model, its baseline calibration and validation, and how it reflects current junction performance. Detailed workings to support the outputs of the quantified economic assessment. Inclusion of sensitivity tests to understand the impact of any variability in the benefits and costs of the scheme. Full assessment of environmental and social impacts of the scheme and inclusion of an Appraisal Summary Table. Further detail around scheme costs, contingency (linked to a quantified risk assessment), and levels of cost inflation. Clarifications to the Commercial Case in relation to the procurement processes. Provision of a full project programme, risk register and Quantified Risk Assessment That the scheme retains high or better value for money once these conditions have been met.
Other Implications
Financial
4. Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 is a replacement scheme being funded from the Thames Valley Berkshire Growth Deal 3i announced on 2 February 2017ii.
5. In July 2018, you re-allocated some previously approved Local Growth Deal schemes for funding from the Business Rates Retention Pilot. This scheme was submitted as part of the process to reallocate Local Growth Deal allocations.
6. This report recommends that the Royal Borough of Windsor and Maidenhead be authorised to draw down the capital sum £4,213,200 from the Local Transport Body funding for this scheme.
7. The funding agreement set out at paragraph 12 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.