Berkshire Local Transport Body

SloughHeldPapers from democracy.slough.gov.uk
Wednesday 15 July 2020, 4.00pmHeld 2324 days ago.
Virtual Meeting Open to the public.
19 items, 16 papersAbout 4.9 MB, led by 2.09.2 Slough: A4 Cycle Route NCN422 - One Year Evaluation Report.
No exempt items listedEvery item is due to be heard in public.
This meeting was held15 July 2020
19items
16papers
17decisions
–exempt
Running order, sized by papersItem 14 to 32
ReportsProcedureExempt parts

The agenda, item by item

What the committee will consider, in order, with every paper attached to its item.

14
Procedure

Declarations of interest

It is a principle of the BLTB that the interests of the Thames Valley Berkshire area will take precedence over a member’s own interests or those of their nominating authority. All members must declare, and take relevant action, if they believe they have a pecuniary or other interest on a matter to be considered at the meeting in accordance with the Code of Conduct of the nominating authority or LEP. The Chair will...

15
Procedure

Election of Chair 2020/21

To elect the Chair of BLTB for 2020/21 from amongst the Local Authority Members.

Decision: Resolved – That Councillor Page be elected as Chair of BLTB for the 2020/21 municipal year. (Councillor Page in the Chair for the remainder of the meeting) Decision page

16
Procedure

Election of Vice-Chair 2020/21

To elect the Vice-Chair of BLTB for 2020/21 from amongst the Thames Valley Berkshire LEP members.

Decision: Resolved – That Bob Mountain be elected as Vice-Chair of BLTB for the 2020/21 municipal year. Decision page

17
Report

Minutes of the Meeting held on 12th March 2020 and the Extraordinary Meeting held on 4th June 2020

Decision: Resolved – That the minutes of the meeting of the Berkshire Local Transport Body (BLTB) held on 12 th March 2020 and the extraordinary meeting held on 4 th June 2020 be approved as a correct record. Decision page

2 papers, 230 KBSearch inside with Pro
ReportMinutes , 04/06/2020 Berkshire Local Transport Body121 KBDownload
ReportMinutes of the Meeting held on 12th March 2020 and the Extraordinary Meeting held on 4th June 2020109 KBDownload
18
Report

Briefing note – TVBLEP/BLTB “How We Work”

Decision: Resolved – That the BLTB ‘How We Work’ briefing note be noted. Decision page

ReportBriefing note: TVBLEP/BLTB “How We Work”54 KBDownload
19
Report

Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21

Decision: Resolved – That the progress made on the schemes previously given programme entry status, as set out in the composite report be noted. Decision page

1 paper, 147 KBSearch inside with Pro
ReportThames Valley Berkshire Local Growth Deal 2015/16 to 2020/21147 KBDownload
20
Report

Financial approval: Scheme 2.45 Langley High Street Widening Phase 2

Decision: Resolved – That scheme 2.46 Slough Langley High Widening Phase 2 be given conditional financial approval in the sum of £1,033,000 in 2020/21 on the terms of the funding agreement set out at paragraph 14 step 5 of the report, subject to meeting the following conditions: (a) Slough Borough Council (SBC) to demonstrate positive discussions with the Langley Memorial Ground Trustees that result in an outline agreement for the acquisition of the land required to develop the scheme; (b) Production of... Decision page

1 paper, 458 KBSearch inside with Pro
ReportFinancial approval: Scheme 2.45 Langley High Street Widening Phase 2458 KBDownload
21
Report

Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm

Decision: Resolved – That Addendum 2 Access, Turning Head and Urban Realm Improvements for scheme 2.29 Wokingham: Winnersh Triangle Park and Ride be given full financial approval in the sum of £675,000 Local Growth Funds in 2020/21. This was on the terms of the funding agreement set out at paragraph 11 step 5 of the report. Decision page

1 paper, 261 KBSearch inside with Pro
ReportFinancial Approval for 2.29 Winnersh Triangle Park & Ride: Addendum 2 Access, Turning Head and Urban Realm261 KBDownload
22
Report

Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)

Decision: Resolved – That scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 be given re-profiled financial approval in the sum of £4,213,000 from the Local Growth Fund (LGF) and £1,068,000 from the Business Rates Retention Pilot (BRRP) funds in 2020/21 on the terms of the funding agreement set out at paragraph 12 step 5 of the report. Decision page

1 paper, 480 KBSearch inside with Pro
ReportFinancial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)480 KBDownload
23
Report

Financial approval: Scheme 2.44 Reading Buses Completing the Connection

Decision: Resolved – That Reading Buses Completing the Connection project be given full financial approval in the sum of £1,541,243 Local Growth Funds in 2020/21. This was on the terms of the funding agreement set out at paragraph 11 step 5 of the report, subject to meeting the following condition: (a) Agreement to provision of ongoing operating costs in relation to the investment to demonstrate compliance with state aid requirements. Details will be agreed with input from a solicitor with state aid... Decision page

1 paper, 501 KBSearch inside with Pro
ReportFinancial approval: Scheme 2.44 Reading Buses Completing the Connection501 KBDownload
24
Report

Financial approval: Scheme 2.40: Windsor Town Centre Package

Decision: It was agreed that the scheme be given full financial approval on the terms set out in the report. Resolved – That scheme 2.40 Windsor Town centre package be given full financial approval in the sum of £1,562,500 Local Growth Funds in 2020/21. This is on the terms of the funding agreement set out at paragraph 11 step 5 below. Decision page

1 paper, 420 KBSearch inside with Pro
ReportFinancial approval: Scheme 2.40: Windsor Town Centre Package420 KBDownload
25
Report

2.09.2 Slough: A4 Cycle Route NCN422 - One Year Evaluation Report

Decision: Resolved – That the reports from the scheme promoter and the Independent Assessor be noted. Decision page

1 paper, 1.7 MBSearch inside with Pro
Report2.09.2 Slough: A4 Cycle Route NCN422: One Year Evaluation Report1.7 MBDownload
26
Report

2.22 Slough: Burnham Station Access - One Year Evaluation Report

Decision: It was agreed that the reports be noted. Resolved – That the reports from the scheme promoter and the Independent Assessor be noted. Decision page

1 paper, 219 KBSearch inside with Pro
Report2.22 Slough: Burnham Station Access: One Year Evaluation Report219 KBDownload
27
Report

Requested scheme updates following June BLTB meeting

Decision: Resolved – That the following update reports from the scheme promoters be noted. Decision page

ReportRequested scheme updates following June BLTB meeting68 KBDownload
28
Report

Thames Valley Berkshire - Call for bids announce July 2020

Decision: Resolved – That a new call for bids be approved as set out in Appendices 1 to 3 to the report and as per the updated LGF prioritisation methodology. Decision page

1 paper, 205 KBSearch inside with Pro
ReportThames Valley Berkshire: Call for bids announce July 2020205 KBDownload
29
Report

Update to the BLTB re Business Rate Retention Pilot monies - Revenue Support

Decision: Resolved – (a) That the report be noted. (b) That Transport officers supply regular updates to the LEP with latest spend levels and developments on projects. Decision page

ReportUpdate to the BLTB re Business Rate Retention Pilot monies: Revenue Support67 KBDownload
30
Report

Proposed BLTB letter of support for TfSE Proposal to Government

Decision: Resolved – That the letter of support for Transport for the South East ( TfSE ) and their Proposal to government be endorsed. Decision page

ReportProposed BLTB letter of support for TfSE Proposal to Government92 KBWithheld: personal details
32
Procedure

Date of next meeting: Thursday 12th November 2020, 4pm

Read inside all 16 papersPro opens every page, searches every appendix, and keeps the papers if the council removes them.

Every paper for this meeting

All 16 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.

PaperSizeOur copy
Minutes , 04/06/2020 Berkshire Local Transport BodyItem 17, Minutes of the Meeting held on 12th March 2020 and the Extraordinary Meeting held on 4th June 2020
121 KB
Kept 3 Oct
Minutes of the Meeting held on 12th March 2020 and the Extraordinary Meeting held on 4th June 2020Item 17, Minutes of the Meeting held on 12th March 2020 and the Extraordinary Meeting held on 4th June 2020
109 KB
Kept 3 Oct
Briefing note: TVBLEP/BLTB “How We Work”Item 18, Briefing note – TVBLEP/BLTB “How We Work”
54 KB
Kept 3 Oct
Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21Item 19, Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21
147 KB
Kept 3 Oct
Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Item 20, Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
458 KB
Kept 3 Oct
Financial Approval for 2.29 Winnersh Triangle Park & Ride: Addendum 2 Access, Turning Head and Urban RealmItem 21, Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
261 KB
Kept 3 Oct
Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)Item 22, Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
480 KB
Kept 3 Oct
Financial approval: Scheme 2.44 Reading Buses Completing the ConnectionItem 23, Financial approval: Scheme 2.44 Reading Buses Completing the Connection
501 KB
Kept 3 Oct
Financial approval: Scheme 2.40: Windsor Town Centre PackageItem 24, Financial approval: Scheme 2.40: Windsor Town Centre Package
420 KB
Kept 3 Oct
2.09.2 Slough: A4 Cycle Route NCN422: One Year Evaluation ReportItem 25, 2.09.2 Slough: A4 Cycle Route NCN422 - One Year Evaluation Report
1.7 MB
Kept 3 Oct
2.22 Slough: Burnham Station Access: One Year Evaluation ReportItem 26, 2.22 Slough: Burnham Station Access - One Year Evaluation Report
219 KB
Kept 3 Oct
Requested scheme updates following June BLTB meetingItem 27, Requested scheme updates following June BLTB meeting
68 KB
Kept 3 Oct
Thames Valley Berkshire: Call for bids announce July 2020Item 28, Thames Valley Berkshire - Call for bids announce July 2020
205 KB
Kept 3 Oct
Update to the BLTB re Business Rate Retention Pilot monies: Revenue SupportItem 29, Update to the BLTB re Business Rate Retention Pilot monies - Revenue Support
67 KB
Kept 3 Oct
Proposed BLTB letter of support for TfSE Proposal to GovernmentItem 30, Proposed BLTB letter of support for TfSE Proposal to Government
92 KB
Kept 3 Oct
Withheld: personal detailsRead here
BLTB Forward Plan 2020/21Item 31, BLTB Forward Plan 2020/21
41 KB
Kept 3 Oct

Last time, and what carried over

The committee last met on 4 June 2020. 12 of its items lead into this meeting; 6 items are new. Point at any item to follow a thread. Procedural items are left out.

Jun4
4 June 202013 items, 11 papers
Held
carried over
Jul15
15 July 202019 items, 16 papers
Held
2
Briefing Note - TVB LEP/BLTB 'How We Work'
3
Covid 19 and Local Growth Fund timing update
4
Revised Local Growth Fund Programme 2015/16 to 2020/21 - Update June 2020
5
Financial Approval 2.37 Bracknell: A322/ A329 Corridor Improvements - re-profiled
6
Financial Approval Superfast Berkshire Broadband Complete Coverage project
7
Financial Approval: Scheme 2.30 TVB Smart City Cluster extension
8
Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancements
9
Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements
10
Financial Approval 2.45 Slough: Langley High Street/ Meadfield Road Junction Improvements Phase 1
11
Financial Approval: Scheme 2.38 Theale Railway Station upgrade
12
BLTB Forward Plan
13
Date of Next Meeting - Wednesday 15th July 2020, 4pm
17
Minutes of the Meeting held on 12th March 2020 and the Extraordinary Meeting held on 4th June 2020
18
Briefing note – TVBLEP/BLTB “How We Work”
19
Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21
20
Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
21
Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
22
Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
23
Financial approval: Scheme 2.44 Reading Buses Completing the Connection
24
Financial approval: Scheme 2.40: Windsor Town Centre Package
25
2.09.2 Slough: A4 Cycle Route NCN422 - One Year Evaluation ReportNew this time
26
2.22 Slough: Burnham Station Access - One Year Evaluation ReportNew this time
27
Requested scheme updates following June BLTB meetingNew this time
28
Thames Valley Berkshire - Call for bids announce July 2020New this time
29
Update to the BLTB re Business Rate Retention Pilot monies - Revenue SupportNew this time
30
Proposed BLTB letter of support for TfSE Proposal to GovernmentNew this time
31
BLTB Forward Plan 2020/21
32
Date of next meeting: Thursday 12th November 2020, 4pm

The threads

  • Briefing Note - TVB LEP/BLTB 'How We Work' leads to item 18, Briefing note – TVBLEP/BLTB “How We Work”
  • Covid 19 and Local Growth Fund timing update leads to item 19, Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21
  • Revised Local Growth Fund Programme 2015/16 to 2020/21 - Update June 2020 leads to item 17, Minutes of the Meeting held on 12th March 2020 and the Extraordinary Meeting held on 4th June 2020
  • Revised Local Growth Fund Programme 2015/16 to 2020/21 - Update June 2020 leads to item 19, Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21
  • Financial Approval 2.37 Bracknell: A322/ A329 Corridor Improvements - re-profiled leads to item 20, Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
  • Financial Approval 2.37 Bracknell: A322/ A329 Corridor Improvements - re-profiled leads to item 21, Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
  • Financial Approval 2.37 Bracknell: A322/ A329 Corridor Improvements - re-profiled leads to item 22, Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
  • Financial Approval 2.37 Bracknell: A322/ A329 Corridor Improvements - re-profiled leads to item 23, Financial approval: Scheme 2.44 Reading Buses Completing the Connection
  • Financial Approval 2.37 Bracknell: A322/ A329 Corridor Improvements - re-profiled leads to item 24, Financial approval: Scheme 2.40: Windsor Town Centre Package
  • Financial Approval Superfast Berkshire Broadband Complete Coverage project leads to item 20, Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
  • Financial Approval Superfast Berkshire Broadband Complete Coverage project leads to item 21, Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
  • Financial Approval Superfast Berkshire Broadband Complete Coverage project leads to item 22, Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
  • Financial Approval Superfast Berkshire Broadband Complete Coverage project leads to item 23, Financial approval: Scheme 2.44 Reading Buses Completing the Connection
  • Financial Approval Superfast Berkshire Broadband Complete Coverage project leads to item 24, Financial approval: Scheme 2.40: Windsor Town Centre Package
  • Financial Approval: Scheme 2.30 TVB Smart City Cluster extension leads to item 20, Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
  • Financial Approval: Scheme 2.30 TVB Smart City Cluster extension leads to item 21, Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
  • Financial Approval: Scheme 2.30 TVB Smart City Cluster extension leads to item 22, Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
  • Financial Approval: Scheme 2.30 TVB Smart City Cluster extension leads to item 23, Financial approval: Scheme 2.44 Reading Buses Completing the Connection
  • Financial Approval: Scheme 2.30 TVB Smart City Cluster extension leads to item 24, Financial approval: Scheme 2.40: Windsor Town Centre Package
  • Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancements leads to item 20, Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
  • Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancements leads to item 21, Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
  • Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancements leads to item 22, Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
  • Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancements leads to item 23, Financial approval: Scheme 2.44 Reading Buses Completing the Connection
  • Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride Addendums 1 Car Park enhancements leads to item 24, Financial approval: Scheme 2.40: Windsor Town Centre Package
  • Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements leads to item 20, Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
  • Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements leads to item 21, Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
  • Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements leads to item 22, Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
  • Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements leads to item 23, Financial approval: Scheme 2.44 Reading Buses Completing the Connection
  • Financial Approval 2.24 Newbury: Railway Station Addendum 1 Ticket Gate Line & Addendum 2 Cycle Hubs and Office Space enhancements leads to item 24, Financial approval: Scheme 2.40: Windsor Town Centre Package
  • Financial Approval 2.45 Slough: Langley High Street/ Meadfield Road Junction Improvements Phase 1 leads to item 20, Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
  • Financial Approval 2.45 Slough: Langley High Street/ Meadfield Road Junction Improvements Phase 1 leads to item 21, Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
  • Financial Approval 2.45 Slough: Langley High Street/ Meadfield Road Junction Improvements Phase 1 leads to item 22, Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
  • Financial Approval 2.45 Slough: Langley High Street/ Meadfield Road Junction Improvements Phase 1 leads to item 23, Financial approval: Scheme 2.44 Reading Buses Completing the Connection
  • Financial Approval 2.45 Slough: Langley High Street/ Meadfield Road Junction Improvements Phase 1 leads to item 24, Financial approval: Scheme 2.40: Windsor Town Centre Package
  • Financial Approval: Scheme 2.38 Theale Railway Station upgrade leads to item 20, Financial approval: Scheme 2.45 Langley High Street Widening Phase 2
  • Financial Approval: Scheme 2.38 Theale Railway Station upgrade leads to item 21, Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban Realm
  • Financial Approval: Scheme 2.38 Theale Railway Station upgrade leads to item 22, Financial Approval Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 (reprofiled)
  • Financial Approval: Scheme 2.38 Theale Railway Station upgrade leads to item 23, Financial approval: Scheme 2.44 Reading Buses Completing the Connection
  • Financial Approval: Scheme 2.38 Theale Railway Station upgrade leads to item 24, Financial approval: Scheme 2.40: Windsor Town Centre Package
  • BLTB Forward Plan leads to item 31, BLTB Forward Plan 2020/21
  • Date of Next Meeting - Wednesday 15th July 2020, 4pm leads to item 32, Date of next meeting: Thursday 12th November 2020, 4pm

Not carried over

Everything from last time returns in some form.

See the 4 June meeting

This committee over time

Every Berkshire Local Transport Body meeting we have read, the dates it has set for the future, and each time those dates have changed.

41 meetings, 2013 to 2025Dot size shows the number of papers
2013201520172019202120232025
HeldThis meeting
MeetingItemsPapers
6 Mar 2025Thursday
0items
0papers
HeldOpen
7 Nov 2024Thursday
0items
0papers
HeldOpen
4 Jul 2024Thursday
0items
0papers
HeldOpen
7 Mar 2024Thursday
6items
4papers
HeldOpen
9 Nov 2023Thursday
6items
8papers
HeldOpen
13 Jul 2023Thursday
9items
8papers
HeldOpen
9 Mar 2023Thursday
11items
9papers
HeldOpen
10 Nov 2022Thursday
9items
12papers
HeldOpen
14 Jul 2022Thursday
10items
10papers
HeldOpen
10 Mar 2022Thursday
0items
0papers
HeldOpen
11 Nov 2021Thursday
11items
9papers
HeldOpen
15 Jul 2021Thursday
10items
7papers
HeldOpen
11 Mar 2021Thursday
9items
7papers
HeldOpen
12 Nov 2020Thursday
13items
10papers
HeldOpen
16 Jul 2020Thursday
0items
0papers
HeldOpen
15 Jul 2020Wednesday, this meeting
19items
16papers
4 Jun 2020Thursday
13items
11papers
HeldOpen
12 Mar 2020Thursday
11items
11papers
HeldOpen
14 Nov 2019Thursday
13items
15papers
HeldOpen
18 Jul 2019Thursday
15items
15papers
HeldOpen
14 Mar 2019Thursday
12items
13papers
HeldOpen
31 Jan 2019Thursday
10items
10papers
HeldOpen
15 Nov 2018Thursday
12items
17papers
HeldOpen
19 Jul 2018Thursday
18items
16papers
HeldOpen
15 Mar 2018Thursday
10items
9papers
HeldOpen
16 Nov 2017Thursday
13items
16papers
HeldOpen
20 Jul 2017Thursday
10items
9papers
HeldOpen
16 Mar 2017Thursday
10items
15papers
HeldOpen
17 Nov 2016Thursday
7items
8papers
HeldOpen
21 Jul 2016Thursday
11items
9papers
HeldOpen
17 Mar 2016Thursday
8items
8papers
HeldOpen
19 Nov 2015Thursday
9items
12papers
HeldOpen
16 Jul 2015Thursday
8items
5papers
HeldOpen
19 Mar 2015Thursday
6items
4papers
HeldOpen
20 Nov 2014Thursday
13items
16papers
HeldOpen
24 Jul 2014Thursday
11items
9papers
HeldOpen
19 Mar 2014Wednesday
0items
0papers
HeldOpen
13 Mar 2014Thursday
7items
5papers
HeldOpen
14 Nov 2013Thursday
7items
5papers
HeldOpen
18 Jul 2013Thursday
7items
5papers
HeldOpen
14 Mar 2013Thursday
6items
3papers
HeldOpen

Follow the Berkshire Local Transport Body

Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.

What should we tell you?

Slough, Berkshire Local Transport Body

Berkshire Local Transport Body: 3 kinds of updateSlough, sent the same day
PDF
16 papers published for 15 July2.09.2 Slough: A4 Cycle Route NCN422 - One Year Evaluation Report and 15 more papers
DAT
Meeting dates updatedAny date added, moved or dropped
DEC
Decisions from 15 JulyThe committee's resolutions, the day they are recorded
ABC
"slough" found in 2 papers2.09.2 Slough: A4 Cycle Route NCN422: One Year Evaluation Report and 2.22 Slough: Burnham Station Access: One Year Evaluation Report
Each update links to the paper and the council's own copy
Free: one weekly alert. Pro: every option, the same day. Pro Plus: straight into your own systems.

Free

One alert, sent weekly, on titles and decisions.

£0for good
  • 1 alert, weekly summary
  • Titles and decisions
  • Link to every official paper
Save this alert free
Most chosen

Pro

Unlimited alerts the same day, searching every page.

£99per user a month
  • Unlimited alerts, same day
  • Matches inside every page and appendix
  • Every council, not just this one

Pro Plus

Your team, with every match pushed into your own tools.

£449a month, 3 users included
  • Everything in Pro, for 3 users
  • Alerts as webhooks into Slack or a CRM
  • API key and bulk export of this council

Data licence

Every council's records in your own products and research.

£12,000a year, from
  • Unlimited API and full archive delivery
  • Rights to use the data in your products
  • Back to 2000, every council
Talk to us

Never miss what this committee decides

Papers, decisions and date changes for the Berkshire Local Transport Body, and every other committee you follow, the day they appear.

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies