Resolved – That Reading Buses Completing the Connection project be given full financial approval in the sum of £1,541,243 Local Growth Funds in 2020/21. This was on the terms of the funding agreement set out at paragraph 11 step 5 of the report, subject to meeting the following condition: (a) Agreement to provision of ongoing operating costs in relation to the investment to demonstrate compliance with state aid requirements. Details will be agreed with input from a solicitor with state aid expertise and added to the grant letter.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.44: Reading Buses Completing the Connection.
2. The ‘Completing the Connection’ project is designed for two core purposes: 2.1. provide a complete travel picture to existing and prospective public transport customers by enabling bus operators across Berkshire to securely store, manage and make available live bus time predictions to customers via the real time information (RTI) system; and 2.2. be scalable, by allowing, for example, the subsequent addition of new or upgraded screens at transport interchanges, bus stops and on-board buses
3. In summary this includes: • A new software platform and applications to underpin the RTI system using open data principles to calculate and disseminate to customers live departure information for multiple transport operators; • Installation of audio-visual information screens and speakers on 51 local buses, to inform and help all passengers and specifically assist customers with aural or visual impairments; • Installation of three large-format bus departure screens at two key railway stations, showing live departure information derived from the RTI system for multiple operators’ bus and coach services; and • Development of an online travel shop, allowing customers to purchase and receive tickets either on their mobile or in smartcard format.
4. The scheme was given programme entry status in March 2020.
Recommendation
5. You are recommended to give Reading Buses Completing the Connection project full financial approval in the sum of £1,541,243 Local Growth Funds in 2020/21. This is on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions:
5.1Agreement to provision of ongoing operating costs in relation to the investment to demonstrate compliance with state aid requirements. Details will be agreed with input from a solicitor with state aid expertise and added to the grant letter.
Other Implications
Financial
Item 10: Financial Approval for 2.44 Reading Buses Completing the Connection project 6. A call for bids process was undertaken in January 2020 and a list of prioritised projects were agreed at the BLTB meeting March 2020. Scheme 2.44 Reading Buses Completing the Connection was a named scheme.
7. This report recommends that Reading Buses be authorised to draw down the capital sum £1,541,243 from the Local Transport Body funding for this scheme.
8. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
9. The risk management arrangements already put in place by the Local Transport Body are as follows:
The Assurance Framework1 has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes
Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 2) on the full business cases for the scheme
The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
10. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Supporting Information
11. The scheme will be carried out by Reading Buses.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.