Berkshire Local Transport Body, Wednesday 15 July 2020 at 4.00pm

Financial approval: Scheme 2.44 Reading Buses Completing the Connection

Approved Committee 1 paper

Berkshire Local Transport Body approved this item on Wednesday 15 July 2020. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

Resolved – That Reading Buses Completing the Connection project be given full financial approval in the sum of £1,541,243 Local Growth Funds in 2020/21. This was on the terms of the funding agreement set out at paragraph 11 step 5 of the report, subject to meeting the following condition: (a) Agreement to provision of ongoing operating costs in relation to the investment to demonstrate compliance with state aid requirements. Details will be agreed with input from a solicitor with state aid expertise and added to the grant letter.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to scheme 2.44: Reading Buses Completing the Connection.

2. The ‘Completing the Connection’ project is designed for two core purposes: 2.1. provide a complete travel picture to existing and prospective public transport customers by enabling bus operators across Berkshire to securely store, manage and make available live bus time predictions to customers via the real time information (RTI) system; and 2.2. be scalable, by allowing, for example, the subsequent addition of new or upgraded screens at transport interchanges, bus stops and on-board buses

3. In summary this includes: • A new software platform and applications to underpin the RTI system using open data principles to calculate and disseminate to customers live departure information for multiple transport operators; • Installation of audio-visual information screens and speakers on 51 local buses, to inform and help all passengers and specifically assist customers with aural or visual impairments; • Installation of three large-format bus departure screens at two key railway stations, showing live departure information derived from the RTI system for multiple operators’ bus and coach services; and • Development of an online travel shop, allowing customers to purchase and receive tickets either on their mobile or in smartcard format.

4. The scheme was given programme entry status in March 2020.

Recommendation

5. You are recommended to give Reading Buses Completing the Connection project full financial approval in the sum of £1,541,243 Local Growth Funds in 2020/21. This is on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions:

5.1Agreement to provision of ongoing operating costs in relation to the investment to demonstrate compliance with state aid requirements. Details will be agreed with input from a solicitor with state aid expertise and added to the grant letter.

Other Implications

Financial

Item 10: Financial Approval for 2.44 Reading Buses Completing the Connection project 6. A call for bids process was undertaken in January 2020 and a list of prioritised projects were agreed at the BLTB meeting March 2020. Scheme 2.44 Reading Buses Completing the Connection was a named scheme.

7. This report recommends that Reading Buses be authorised to draw down the capital sum £1,541,243 from the Local Transport Body funding for this scheme.

8. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk management

9. The risk management arrangements already put in place by the Local Transport Body are as follows:

 The Assurance Framework1 has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes

 Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 2) on the full business cases for the scheme

 The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

10. Slough Borough Council will provide legal support for the BLTB should any questions arise.

Supporting Information

11. The scheme will be carried out by Reading Buses.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial approval: Scheme 2.44 Reading Buses Completing the ConnectionReport 501 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 16 attended
RA
Councillor Robert AndersonCommittee Member, present
MB
Councillor Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, present
GC
Councillor Gerry ClarkCommittee Member, present
PJ
Councillor Pauline JorgensenCommittee Member, present
TP
Councillor Tony Page Reading Borough CouncilChair, present
RS
Councillor Richard SomnerCommittee Member, present
SA
Stuart AtkinsonCommittee Member, present
CE
Charles EalesVice-Chair, present
MK
Malcolm KemptonCommittee Member, present
BM
Bob MountainCommittee Member, present
SR
Simon RatcliffeCommittee Member, apologies
MT
Matthew TaylorCommittee Member, present

All 16 on the meeting page

On this subject at Slough

Search all
  1. Financial approval: Scheme 2.44 Reading Buses Completing the ConnectionThis decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies